3 Max Wilkinson debates involving the Department for Transport

Old Oak Common Station

Max Wilkinson Excerpts
Tuesday 17th December 2024

(5 days, 7 hours ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Max Wilkinson Portrait Max Wilkinson (Cheltenham) (LD)
- Hansard - -

I beg to move,

That this House has considered the impact of Old Oak Common station on rail services to the West and Wales.

It is a pleasure to serve under your chairship, Mr Efford. We all know that opinions on High Speed 2 are many and varied—whether or not that line is a good thing is not up for debate today—but nobody would have expected that the development of a high-speed rail line heading from the north to London and back again would have a negative impact on trains heading west. Something about that statement seems entirely illogical. Unfortunately for people in the west and Wales, it is indeed the case that there will be widespread disruption to trains between London Paddington and the west and south Wales for the next six years, and after that six-year period is over, every train between the west and south Wales and London will be slower.

The reason for the delays and slower services is the new Old Oak Common station, which is being built to serve HS2. At this point, it is important to state that today’s debate, and indeed the wider public discussion, cannot be about whether HS2 happens at all or whether Old Oak Common station is built. HS2 is happening, and anyone who has travelled on the Great Western line recently will know that Old Oak Common is being built. But there are three points that we must all take up on behalf of our constituents. The first is how the impact of construction work at Old Oak Common can be mitigated. The second is how Old Oak Common can become a useful station for our regions. The third is how the Government can use their power to mitigate the long-term impact of slower trains heading to and from the west and south Wales, by improving services in other ways. I will ask a number of questions, and although I am sure that some of them do not yet have answers, I hope the Minister will at least be able to address each one to confirm the Government’s position and their intentions.

First, I will deal with the construction phase. Most people who are aware of the new station will know it as the place where the previous Government had intended to terminate HS2. That was before the new Government decided to bring back the suggestion that HS2 will end at Euston. But it is much more complicated than that. Old Oak Common is being built on the Great Western line, as I mentioned, and consequently a decision has been taken that all trains using the line will eventually stop at Old Oak Common.

That decision makes sense to those in charge of big transport infrastructure, but it will not necessarily make sense to the people we serve in the west and south Wales. Rail industry experts tell us that it will add between four and seven minutes to each journey in the long run. During the period of disruption while construction takes place, we will endure 29 days of disruption in this current operational year—that disruption has already begun—30 days of disruption in 2025-26, 41 days of disruption in 2026-27, including 14 days when no trains run at all, 34 days of disruption in 2027-28, including 11 days when no trains run at all, and 47 days of disruption in 2028-29, including 18 days when no trains run at all. The disruption for the following year is not yet known.

The majority of the impact will fall on Sundays and at Christmas. We might assume that Sunday is a quiet day on the railways, but since my election and my need to travel to London, sometimes on a Sunday evening, I can tell Members that that is not the case, particularly when Great Western Railway is unable to run most of its timetable. The number of constituencies that will be impacted by the work is absolutely huge. Starting from furthest away, it will be every constituency in Cornwall and Devon, most of Somerset, Bristol, parts of Herefordshire and Worcestershire, south Wales, Gloucestershire—my own area of the country—Wiltshire, Berkshire and Oxfordshire. That is a lot of people whose journeys will be slower for a long time, and a lot of people who will have to make alternative arrangements when trains are cancelled.

Andrew George Portrait Andrew George (St Ives) (LD)
- Hansard - - - Excerpts

My constituency, which includes Penzance station, will be deeply affected. We are five hours away from Old Oak Common and will experience much of the pain with no gain. Just a fraction of the £67 billion being spent on HS2—for example, just one two-hundredth of that budget—could address the issue in Dawlish, which is three hours away from Penzance. Those kinds of things need to be addressed if we are to see some kind of compensation.

Max Wilkinson Portrait Max Wilkinson
- Hansard - -

I absolutely agree. Although joining up London with the north and the midlands is a laudable aim, there is a real risk that the west and south Wales could be left out. The amount of money being spent on HS2 is not matched by rail investment towards the west, as those of us who represent constituencies there are well aware.

My first question to the Minister is: what assessment has been made of the fixed-term construction disruption to the economies of the constituencies affected, including my own in Cheltenham? What assessment has been made of the clear risk that the disruption caused by construction is wider than that which is currently being reported, with perhaps extra days of construction work leading to more cancellations? What discussions have Ministers had with Network Rail about whether the speed limit associated with the construction work could be 80 mph rather than 60 mph?

The second area to explore is how Old Oak Common might become a station that serves our constituencies, rather than simply making things less convenient. That is a much more complex discussion, and those of us who have seen the maps will know that that is still up for debate. Rail industry professionals suggest that there is an opportunity to either improve services or significantly mitigate the impact of the potential disruption, but the core problem is clear. At a time when the national rail network is struggling so badly and the Government are promising a brighter future under Great British Railways, our constituents must be able to see benefits.

I am certain that most Members present will agree that those additional four to seven minutes must be offset, and Old Oak Common has the potential to become a significant interchange, enabling travellers from the west and south Wales to switch to the London transport network earlier, perhaps via the Elizabeth line or London Overground services. Achieving that aim would ensure smooth onward journeys, not just into central London but, if it is done right, elsewhere. What assurances can the Minister give us that the station interchange will be just as convenient as Paddington, if not more so? Is the convenience of the interchange with the Elizabeth line as secure as Members have been led to believe in some of the briefings, or is that not yet guaranteed?

If an interchange to the Elizabeth line is secured, can the Minister tell me the anticipated journey time to central London to and from my Cheltenham constituency after those works are complete? Can the Minister also confirm whether technical studies on interchanging with overground services have begun, so that we can work out what is possible? Nothing that Members are hearing so far suggests that the technical work has been properly considered, or even whether it has been started at any level. If studies have begun, what work has been done to cost future works? If they have not, when will those studies take place?

Rebecca Smith Portrait Rebecca Smith (South West Devon) (Con)
- Hansard - - - Excerpts

The rail Minister has expressed the view that enabling those of us from the south-west to connect to the midlands and Birmingham would be one mitigation, but does the hon. Member agree that that is not a good enough result for the overground services? Frankly, we need connections into London, because we can already get to the midlands and the services that HS2 would be offering.

Max Wilkinson Portrait Max Wilkinson
- Hansard - -

I can see why the hon. Member’s constituents in Devon would not be interested in going to London before going to the midlands. She makes a very good point.

If those studies have not begun, what work has been done to cost the future works? If not, when will those studies take place? For those whose journeys are inevitably taking them to the area around Paddington, what reassurances are there that congestion west of Paddington can be dealt with in order to maintain capacity?

My third point is about restoring trust in our railways by making more general improvements to passenger experience—I want to mention some hyper-local issues, which I hope the Minister will listen to. Although there will undoubtedly be a period of disruption and uncertainty, there are also some clear opportunities to improve rail services. Five-carriage inter-city trains routinely run in excess of passenger capacity for large parts of journeys to the west. Will the Minister confirm that, as part of the mitigation of the Old Oak Common disruption, more rolling stock will be found to ensure that passengers do not routinely have to endure journeys in which they are forced to stand for unacceptably long periods of time? I have stood with pensioners and vulnerable people next to the loo for longer than an hour on journeys west from Paddington.

Will the Minister confirm that those of us who use trains for business can expect wi-fi improvements? Although the current GWR service offers wi-fi on board, it routinely proves useless for large parts of the journey, which is definitely a drag on the economy.

Tessa Munt Portrait Tessa Munt (Wells and Mendip Hills) (LD)
- Hansard - - - Excerpts

I want to mention the shocking damage to tourism, given the number of people who leave Paddington and try to go west. My constituents are stunned to find that all this has only just come to light—my hon. Friend referred to six years of closure; I have heard seven, and we all know that projects overrun. I also want to reiterate his point that first-class travel is meaningless on GWR, because those trains are almost always overcrowded—people going west in first class have to stand in the corridor, sit on their suitcases or find somewhere else. Also, the Glastonbury festival finishes on a Sunday, and many people travel in and out of Glastonbury on a Sunday, so this will be incredibly damaging to that event.

Max Wilkinson Portrait Max Wilkinson
- Hansard - -

My hon. Friend is absolutely right. The impact on tourism is felt by all our constituencies in the west, many of which are tourism hotspots. The point about connectivity is important. If we can have 5G on the Elizabeth line in London, which is already well served by public transport, why can I not have 5G in the countryside between Swindon and Stroud when I travel back to my constituency? It makes no sense. The benefits to business users would surely justify the investment.

I have already asked the rail industry whether progress might be made on the frustrating turnaround times at Gloucester, which delay Cheltenham passengers every day. I accept that it is unlikely that any progress will made soon, but what chance is there of improving rail infrastructure around Gloucester, to remove the need for the driver to switch from one end of the train to the other—a very 20th-century solution?

Finally, I come to the trains themselves. The current rolling stock is functional, but what plans do Ministers have to make the carriages more pleasant? Older constituents recall the days of comfortable seats and a buffet carriage with snacks. In other European nations, inter-city trains even have carriages with special family-friendly areas where children can play. A civilised and family-friendly nation should surely consider that.

It is no exaggeration to say that weekends are a nightmare. What are Ministers doing in the short term and during the period of disruption to ensure that a Sunday timetable actually runs between London and the west country?

Claire Young Portrait Claire Young (Thornbury and Yate) (LD)
- Hansard - - - Excerpts

My hon. Friend raises the need for improvements. The key issue for commuters in my constituency is that the existing GWR mainline is not fit for purpose. In recent weeks, we have seen significant delays and diversions caused by flooding and signalling failures, which has created even more pressure on other parts of the already overstretched network. Does he agree that work at Old Oak Common needs to be accompanied by immediate investment in existing infrastructure to improve the reliability of services for people from the west?

Max Wilkinson Portrait Max Wilkinson
- Hansard - -

I absolutely do. My hon. Friend the Member for St Ives (Andrew George) made the point that, compared with HS2, the amount of money that needs to be invested for improvement in the west country is relatively small.

By way of compensation to Cheltenham for the disruption, can the Minister please ask Network Rail to stop blocking the long-awaited extension to the cycle path that links Cheltenham town centre to the station? Network Rail has been getting in the way of that development for years. It just needs to get out of the way to improve connectivity in my constituency.

I have asked a number of questions, which are intended as helpful contributions. I am sure that other hon. Members will have pertinent points about the impact on their constituencies. Before I finish, I would like to pay tribute to the work of the hon. Member for Plymouth Sutton and Devonport (Luke Pollard), the new Minister for the Armed Forces. Having researched this issue in the previous Parliament, he played a leadership role by passing on information to new hon. Members, helping to bring about today’s debate, for which we thank him.

None Portrait Several hon. Members rose—
- Hansard -

--- Later in debate ---
Lilian Greenwood Portrait Lilian Greenwood
- Hansard - - - Excerpts

I can confirm that the station is being constructed to allow all Great Western services to call, but no decision has been made on the future timetable.

None the less, building the station requires realignment of the Great Western main line to curve around new platforms. Unfortunately, that means that even trains that do not stop at the station will have a small increase in journey times. I know the Rail Minister has already asked industry partners to review current plans to ensure the impact of this is minimised. I will come back to this when I answer questions from hon. Members. I also recognise that this disruption comes on top of several years of poor performance on this route. The Government are determined to reverse that trend, improve punctuality and reliability, and rebuild a railway we can once again be proud of.

I do not think I can answer all of the questions that were posed during the debate, but I shall attempt to respond to a few of them. I know that my colleague the Rail Minister has met with many hon. Members to listen to their concerns, and that he is committed to finding the best possible solution that minimises disruption to services to constituencies in Wales and the west. He will continue to engage with hon. Members on this issue. A number of Members asked whether Great Western Railway services will stop at Old Oak Common and raised concerns about the impact on journey times. There will be a small but permanent journey time impact for all services passing through Old Oak Common without stopping. I recognise that that is a disbenefit to hon. Members’ constituents, and the Rail Minister has asked what more can be done to get that down from the estimated 90 seconds.

The hon. Member for Cheltenham asked about increasing running through the station from 60 mph to 80 mph, and Network Rail has already begun to develop proposals. They were discussed at the last Old Oak Common programme board, which the Rail Minister attended. If some or all services are to stop at Old Oak Common—as I said, no decision has been made yet on future timetables; that is some way off—it will, of course, add further to journey times. Four to seven minutes added to journey times has been suggested. That would slow down those services but would allow for potential interchange with the Elizabeth line and access to parts of London via the Elizabeth line and the London Overground. The London Overground does not connect directly, but work has begun on Old Oak Common connectivity and a range of options are under consideration, from improved walking routes through to more material interventions.

Various periods of blockade were discussed. The programme is currently under review, but there will be periods of disruption, as the hon. Member for Cheltenham set out, and those are likely to of the duration that he described or longer. As has been noted, there will be diversions to Euston when the blockades are in place, which will allow services to continue directly into central London for the many constituencies represented here today when the line between Ealing Broadway and Paddington is closed. That will add perhaps 15 to 20 minutes on to journey times.

The hon. Gentleman and others asked about short-form trains. He described clearly the impact on people’s journey experience, which is totally unsatisfactory. I know that the availability of sufficient fleet is vital. I recognise the inadequacy of the situation when the trains are over capacity and I know that the Minister for Rail is working to address this.

The hon. Gentleman also mentioned wi-fi. Free wi-fi is available on Great Western Railway services, but I know from my own travels that there are connectivity issues on part of the network. The Rail Minister has asked officials to explore the feasibility of a range of technology options to improve passenger connectivity on the rail network. The Department is conducting research to measure the strength of mobile phone signals along the network to fully understand where interventions are needed and the potential impacts.

The hon. Gentleman rightly raised the issues of Sunday timetables and cancellations. Problems with infrastructure, fleet reliability, and train crew availability have resulted in high levels of cancellations on Sundays in recent months, and I agree that that is unacceptable. We know these issues must be addressed. They were not addressed by the previous Government and we are working to do so.

Finally, the hon. Gentleman mentioned progress on the extension to the Honeybourne line active travel route in Cheltenham. I know it well, and I agree with his assessment that it would be a valuable extension. I understand that Great Western Railway, Network Rail, and Gloucestershire county council are working to progress the project, and if there is more we can do to hurry it along, I am sure the Rail Minister will be happy to do so.

Max Wilkinson Portrait Max Wilkinson
- Hansard - -

I am aware that I get another chance to speak shortly, but the reason I raised Network Rail’s blocking of that scheme is because of the way it has been done: by extending contract negotiations over years, to the point when a bit of cycle path is costing tens of thousands of pounds per metre because Network Rail demands ever greater levels of infrastructure to be inserted. I have raised this with Ministers and all sorts of people, but it is clear that Network Rail just wanted to kick it into the long grass by making it uneconomic. I know that the Minister is an advocate for active travel, so if she could intervene with Network Rail and just say, “Get it done,” I would be grateful.

Lilian Greenwood Portrait Lilian Greenwood
- Hansard - - - Excerpts

As the hon. Gentleman says, this Government are committed to increasing the number of people who walk and cycle for short journeys. If there is something that my colleagues in the Department and I can do to unblock things and get them moving, we will do it.

Questions were asked about investment in Welsh railways. I assure hon. Members that the Wales Rail Board meets regularly and provides a forum for the UK and Welsh Governments to discuss matters of mutual interest. I understand the new Secretary of State is meeting the Secretary of State for Wales and the Cabinet Secretary for Transport and North Wales, Ken Skates, imminently to discuss transport in Wales. Transport Ministers regularly meet our counterparts in the devolved Governments.

I will close by taking this opportunity to confirm again that the Rail Minister is working with all partners to ensure minimum disruption to travellers on the Great Western main line, both during the construction of Old Oak Common station and when it is in operation. I recognise that these are difficult issues, which hon. Members are right to raise on behalf of their constituents. I thank the hon. Member for Cheltenham and all hon. Members for their participation in this debate. I fully acknowledge and appreciate the importance of the issue to him and his constituents, and indeed to all hon. Members’ constituents. We will work to come up with a viable solution.

--- Later in debate ---
Max Wilkinson Portrait Max Wilkinson
- Hansard - -

Thank you, Mr. Efford; I will speak for no longer than an hour. There is much to reflect on. I am grateful to all colleagues for turning up to this important debate, and to the Minister for addressing a number of the points raised. I appreciate there were probably about 35 questions raised during various speeches, including some from myself. Will the hon. Lady take time later to work with the Rail Minister on responses to my questions about everything from the hyper-local, such as the Honeybourne line, up to the bigger picture stuff around wi-fi connectivity and the delays that Cheltenham passengers suffer at Gloucester?

The main thing to come out of the Minister’s response is that there is still an awful lot to play for. A key point that I took from what she said was that although the station is designed to take all the trains stopping there, including every service from the west, that need not be the case. That is different from what we are generally being briefed on as Members. When we talk about the technical studies that need to go into the future infrastructure that might link into the overground services elsewhere, there is an impact on timings, on the public debate and on the Government’s willingness to fund the studies and the infrastructure. We are now in a period of uncertainty about whether all of the Great Western main line trains will indeed be stopping at Old Oak Common. The opportunity that is being sold by the rail industry, and has been sold by the Government in the very recent past, is thrown into doubt if there is uncertainty about whether all the trains will stop at Old Oak Common, so it seems there is quite a bit of thinking to be done.

I appreciate that the Government are in an imperfect position here. We all are. I suggest that work on the technical studies into the opportunities and economic benefits that we might get in our constituencies and that the nation as a whole might accrue needs to be picked up as soon as possible. I thank the Minister for her response today. I look forward to hearing more in due course.

Question put and agreed to.

Resolved,

That this House has considered the impact of Old Oak Common station on rail services to the West and Wales.

Improving Public Transport

Max Wilkinson Excerpts
Thursday 5th December 2024

(2 weeks, 3 days ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Sarah Dyke Portrait Sarah Dyke
- Hansard - - - Excerpts

I thank my hon. Friend for his intervention. That is vital for rural areas. I have excellent community transport providers in Glastonbury and Somerton: there is Wincanton community transport, and across Somerset we have the Slinky bus that provides on-demand services. They are crucial for people who need to get to surgery appointments and even their jobs, as well as for getting people out and about, and breaking down that rural isolation.

Moving on to integrated transport, if we must wait longer for a station in the Langport and Somerton area, it is crucial that in the meantime the area receives an integrated public transport system to nearby railway stations in the form of rail-bus links. The former Transport Secretary, the right hon. Member for Sheffield Heeley (Louise Haigh), on the day before her departure, set out a vision for more integrated public transport systems. I hope that the new Secretary of State will keep those aims alive, as that is desperately needed in Somerset.

Fragmented transport leaves a traveller trying to get from Wincanton to Castle Cary having to take a bus journey and then walk half a mile to the station to catch a train, with no integration between the bus timetable and the train times. In nearby Devon, local bus operators, the council and Great Western Railway have worked together to launch rail-bus links with improved timetables that correspond with mainline train services, alongside improved service brand visibility. That serves as an example of how integrated rail-bus links can work in rural areas and service communities that do not have a train station.

Max Wilkinson Portrait Max Wilkinson (Cheltenham) (LD)
- Hansard - -

I thank my hon. Friend for bringing this important debate to the Chamber. In my constituency, GWR has been working with the borough and county councils on a new cycle link. Network Rail, unfortunately, is singularly blocking the development. That strategic cycle link will probably not be completed unless Network Rail, which owns the land, gets out the way. Does she agree that different arms of government need to be working together much more strongly and that cultural change in Network Rail is required if we are to solve these problems in public transport and active travel?

Sarah Dyke Portrait Sarah Dyke
- Hansard - - - Excerpts

I wholeheartedly agree with my hon. Friend. Integration between public transport and active travel is vital. He and I live in a beautiful part of the world, which frankly more people should get out and enjoy on two wheels or on two feet.

There are huge opportunities to improve bus services around the country, and especially in Somerset, where they are almost endless—mind you, the starting point is quite low. In 2022, Somerset county council’s bus service improvement plan bid acknowledged that Somerset had the worst-rated bus service in the country at the time, and that was after 13 years of lack of investment under a Conservative-led administration. Bus provision is poor and unreliable.

For example, the 54 bus route, which runs through Glastonbury and Somerton connecting Taunton to Yeovil, lacks an evening or Saturday service. That leaves people who might work unpredictable or unsociable hours unable to trust the bus service and reliant on a private car. Cherie in Glastonbury told me that she has to wait for an hour for her bus home from work, so despite finishing at 5 pm she does not get home until nearly half-past 7. If she were to drive, it would take her 10 minutes.

The unreliability of buses combined with the poor state of bus stops and public information provides a major hurdle for bus users. I thank Somerset bus partnership for its unrelenting work to improve that, having held more than 100 bus stalls to inform local people about their nearest services, filling an information gap that has sadly been left by the service providers. Most bus stops do not have a printed sign timetable or real-time information, and often poor mobile connectivity in rural areas makes it difficult for people to access information online. That was confirmed recently by Iain, who told me that the printed bus timetable in Glastonbury is barely legible. That is so disappointing. Even small interventions could create vastly important changes that would support bus services.

A Campaign for Better Transport survey has found that 52% of people would use more buses if they had better information at bus stops, but the onus on providing that information is sadly lacking. Unlike rail, where there are national standards that mandate that a certain level of information is provided at stations, there is no equivalent for bus stops. Every rail station in Britain has provision for real-time information, but we are a million miles away from achieving similar provision for our bus network. Bus users need certainty, but the availability of up-to-date, co-ordinated information on the bus network is lacking at the best of times and non- existent at the worst of times. That must change.

One of the major barriers preventing simple things like clear information is the fractured nature of bus funding. The previous Government’s competitive strategy turned funding into a postcode lottery, with only 40% of eligible local authorities receiving any of the £1.2 billion of BSIP funding announced in 2021. The Liberal Democrats have been calling for a simplified system of bus funding that could deliver routes where there is local need. Funding is unequal and fractured. Somerset Council receives around £25 per head of funding for buses, yet 12 local authorities across the country get double that amount.

The former Transport Secretary recently announced a big increase in bus funding, with Somerset council receiving £6.5 million. The increase is very welcome, but it will not go far enough to fix the gaping holes in our bus provision. Somerset council also awaits guidance from the Government on what the money can be used for, so that it can prioritise where the need is greatest. The previous Transport Secretary was keen for local authorities to decide where the money is most needed, and I hope that that remains the case.

The Government’s vision for the future of buses appears to be based around franchising and delivering London-style buses around the country. As I stated, better buses are key to achieving a modal shift, hitting net zero targets and delivering opportunity and growth. But with the local authority landscape as it is, franchising simply is not an option in rural areas. If there is not significant funding, franchising is no more than a pipe dream for rural authorities. Somerset council has only three officers to deal with public transport, which is not enough people power to run such an operation. That is not an anomaly, but a local authority standard. If the current situation does not work for rural areas, what is the vision?

I hope that the recent removal of the £2 bus fare cap is not the start of things to come for rural areas. Given the nature of rural bus routes, journeys are longer and people travel further. If the now £3 cap were to be removed, it would be disastrous for rural areas, as prices would rise beyond affordable rates very quickly and disincentivise regular bus patronage. After the 50% fare increase, one constituent from North Cadbury wrote to me concerned about the impact it will have on the future of the No. 1 bus from Yeovil to Shepton Mallet, and the No. 58 in Wincanton, which are both facing cancellation. Those routes, and many like them, are vital for social and economic outcomes.

In the last Session, I introduced the Public Transport (Rural Areas) Bill, which would have created minimum service levels, ensuring that residents can access sites of employment, education and leisure. I believe that those measures are truly needed for rural areas.

Rail Performance

Max Wilkinson Excerpts
Monday 11th November 2024

(1 month, 1 week ago)

Commons Chamber
Read Full debate Read Hansard Text Watch Debate Read Debate Ministerial Extracts
Louise Haigh Portrait Louise Haigh
- View Speech - Hansard - - - Excerpts

Wi-fi is one of the examples of passenger experience that we are clear needs to be delivered through Great British Railways. I take East Midlands Railway, and the wi-fi is even worse on that line. I would be happy to raise that issue with Avanti. We are in the process of attempting to facilitate an agreement with Northern on the conductor issue that my hon. Friend mentions in the north-west, which has the most egregious example of working terms and conditions being outside of a normal working week.

Max Wilkinson Portrait Max Wilkinson (Cheltenham) (LD)
- View Speech - Hansard - -

I join the chorus of those talking about GWR’s shocking Sunday service. Its timetable is a work of fiction akin to “Chuggington”, which I often watch with my daughter. Were that the only problem that my constituents faced, we might be able to look past it. However, the lack of carriages on trains home on a weekday is a huge problem—my hon. Friend the Member for Tewkesbury (Cameron Thomas) recently used some choice language about it, which I urge hon. Members to look up online; I will not report it in the House. We often find that there are only half the carriages that we need to get home. I recently stood by the loo for 90 minutes until Stroud, which was an unpleasant experience shared by many others on the train. What will the Secretary of State do to reassure me that GBR will solve that problem?

Louise Haigh Portrait Louise Haigh
- View Speech - Hansard - - - Excerpts

Again, the current fragmentation of the network means that we have dozens of different types of rolling stock across the network, all procured by different operators at different times, which are not interoperable between operators and cannot be moved around the network precisely when there are issues such as those that the hon. Gentleman described. With the establishment of Great British Railways and a long-term rolling stock strategy, we can procure fewer types of trains and start to move them around. I will take away the specific issue of short-form trains on Great Western Railway and write to him about what action can be taken.