High Speed Rail (West Midlands - Crewe) Bill Debate

Full Debate: Read Full Debate
Department: Department for Transport

High Speed Rail (West Midlands - Crewe) Bill

Lord Grayling Excerpts
2nd reading: House of Commons & Allocation of time motion: House of Commons & Carry-over motion: House of Commons & Money resolution: House of Commons & 2nd reading & Allocation of time motion & Carry-over motion & Money resolution
Tuesday 30th January 2018

(6 years, 9 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Grayling Portrait The Secretary of State for Transport (Chris Grayling)
- Hansard - -

I beg to move, That the Bill be now read a Second time.

It is four years since my predecessor, my right hon. Friend the Member for Derbyshire Dales (Sir Patrick McLoughlin), stood at this Dispatch Box to seek powers for a new railway line between London and the north, the first new major railway line north of London for 120 years. At that time, it was simply a concept—an important one but one that seemed a long way off. We have come a long way since. In February 2017, Parliament granted powers to construct phase 1 of the scheme, from London to the west midlands, and works on part of this route have now begun. This project is now a developing reality. We came a step closer to an operating railway when we announced the shortlist of companies that will bid for the west coast partnership and design, launch and operate the early passenger services on HS2.

This vital new rail capacity project, under construction from London to Birmingham, is only the first part of the project. We need to deliver capacity to our northern cities and bring our country closer together. I am pleased to stand here today, therefore, to start the next phase of this vital project. Phase 2a extends HS2 from the west midlands to Crewe. The first stage of the new line, which will take the midlands engine through to the northern powerhouse, connecting the two together, will accelerate construction of the first section of phase 2 by six years and bring us a step closer to delivering a complete brand-new high-speed line all the way to Manchester. That is the importance of today’s debate. It is this link that will take the railway line towards Manchester—finally to one of our great cities and industrial centres of the north-west.

Jonathan Edwards Portrait Jonathan Edwards (Carmarthen East and Dinefwr) (PC)
- Hansard - - - Excerpts

As the Secretary of State will be aware, the statement of funding policy that accompanied the last comprehensive spending review awarded to Wales a 0% Barnett consequential rating for HS2, whereas Scotland and Northern Ireland both had 100%. Unless he can assure the House that Wales will get a 100% rating in the next CSR, my colleagues and I will have no option but to vote against the Bill this evening.

Lord Grayling Portrait Chris Grayling
- Hansard - -

If the House does not support the Bill, the Crewe hub and the links to north Wales that it will provide will be simply an illusion, so the hon. Gentleman and his colleagues would be doing down Wales, which would be surprising—though, of course, it is typically Conservative Members who are the real champions of Wales. We will continue to ensure we provide the right connections to Wales.

Cheryl Gillan Portrait Dame Cheryl Gillan (Chesham and Amersham) (Con)
- Hansard - - - Excerpts

I thank the Secretary of State for giving way so early in his speech, and I ask him to forgive me as I may not be able to be here for its entirety because I have other duties outside the Chamber, but I hope to return. He says he is very proud of this new railway the Government are building, but can he explain why he is building a railway with old technology? Back in 2015, the Japanese beat all their records with a Maglev train, whereas we appear to be building something from the last century, not something for the future.

Lord Grayling Portrait Chris Grayling
- Hansard - -

It is interesting. I have travelled on the Maglev line in development in Japan. It is a project that has a role to play in the Japanese transport system, but, having studied it at first hand, I do not believe it is the right project for this country, and nor do I believe it could deliver the level of capacity that HS2 will. HS2, of course, is a capacity project that brings with it speed, not the other way around, and that is what our transport system needs more than anything else. It is crucial, too, to the development of the north of England, which has a population of more than 15 million and over 1 million businesses, and which has exports worth upwards of £50 billion. The north of England makes a huge contribution to the success and prosperity of this country, but it needs strong and effective new transport links, and this project will be an important part of that, which is why it is so important to the whole UK.

Cheryl Gillan Portrait Dame Cheryl Gillan
- Hansard - - - Excerpts

The Secretary of State says this is now about capacity, but please can he not change history? When this was first proposed, including the route through my constituency, it was all about speed; otherwise it would not have been allowed to travel on a route that will cause so much environmental damage.

Lord Grayling Portrait Chris Grayling
- Hansard - -

My right hon. Friend will know that I have been consistent all the way through in talking about this as a capacity project. I know that she and I are on different sides of the argument, but, from the time I was shadow Transport Secretary a decade ago, I have always talked about this improvement in terms of capacity, and I will continue to do so, because that is the most important part of it. We can debate the rights and wrongs, but I believe it is a capacity project—the speed is a bonus. I do not believe in building something with old technology—we should have a state-of-the-art railway—but the big difference this will make will be to capacity.

Louise Ellman Portrait Mrs Louise Ellman (Liverpool, Riverside) (Lab/Co-op)
- Hansard - - - Excerpts

I welcome the Bill, but I note that the Minister referred to connecting the west midlands to HS2. What about the northern powerhouse and Liverpool’s connection to the new high-speed line?

Lord Grayling Portrait Chris Grayling
- Hansard - -

I did mention the northern powerhouse. In terms of Liverpool, which, as the hon. Lady knows, is a city I have great affection for, as we move beyond the Bill and develop northern powerhouse rail and integrate what needs to be done in the north with the north-south routes and HS2, I believe that all the great cities of the north—Liverpool, Manchester, Leeds, Newcastle, York, Hull—will benefit, as indeed will places further north, such as Carlisle and Scotland. I will come back to Scotland in a moment.

Kevin Barron Portrait Sir Kevin Barron (Rother Valley) (Lab)
- Hansard - - - Excerpts

If that is the case and Ministers are concerned for the north, why has electrification between cities in the north been cancelled?

Lord Grayling Portrait Chris Grayling
- Hansard - -

As I have said many times in the House, we are delivering a process of modernisation on the midland main line that will transform journey times and deliver much improved rolling stock and brand-new trains much sooner. Our proposed model will deliver the improvements people want in the early 2020s, which is sooner than any other project would have done.

Anna Soubry Portrait Anna Soubry (Broxtowe) (Con)
- Hansard - - - Excerpts

I am grateful to the Secretary of State for giving way; he is being very generous so early in his speech. I agree with him: it is about capacity. We cannot have an effective, modern society unless we have capacity, and we have to have good infrastructure, which means connectivity. Would he therefore consider advancing the Government’s excellent plans for HS2 by bringing on the other piece of the Y to Leeds? I believe that people throughout the whole of the east midlands support HS2, and we want it as soon as possible, please, especially at Toton in Broxtowe.

Lord Grayling Portrait Chris Grayling
- Hansard - -

I absolutely agree with my right hon. Friend. Toton is going to be a fantastic centre in the east midlands for commercial development—transport and residential—whose benefits will ripple out across the area and have a hugely positive effect on the whole of the east midlands. I understand her point. We are working as fast as we can to bring before the House the powers we need for the east midlands and Yorkshire leg. I want to get it right—there are sensitivities on the route, as she will know—and I have travelled much of the route myself and looked at the issues as and when they arrive. We will do everything we can to minimise the impact on residents—I understand that such major projects have a negative effect on some people—but I assure her that we will bring the measure for the rest of the route before the House as soon as we can.

I have talked a bit about the north. Let me now talk about Scotland, because I want it to benefit from HS2 on the day it opens. When the full Y network opens in 2033, HS2 trains will run seamlessly on to the west and east coast main lines from the network that is then built. My Department and Transport Scotland are working closely with Network Rail in looking at options that will go beyond HS2. We want to identify options for strong business cases that can improve journey times, capacity, resilience and reliability. Our ultimate ambition is for three-hour rail journeys between London and Scotland’s central belt—a further strengthening of the Union that we all hold so dear. That, I think, is the point: HS2 will be a transformative project for the entire United Kingdom, including the parts that it does not serve directly. The benefits in terms of job creation, business opportunity and technological development will be enormous for the whole country.

Andrew Jones Portrait Andrew Jones (Harrogate and Knaresborough) (Con)
- Hansard - - - Excerpts

I strongly support the Bill, and agree with my right hon. Friend’s comments about capacity in our rail network and the positive impact that HS2 will have on our northern economy. Can he tell us a little more about the impact on job creation in the north and elsewhere outside London?

--- Later in debate ---
Lord Grayling Portrait Chris Grayling
- Hansard - -

I pay tribute to my hon. Friend for the work that he has done on this project. He has been a very distinguished Transport Minister. He has not only made a major contribution to its development, but has been immensely sensitive in dealing with residents. He should take great credit for that.

The point about jobs is crucial. Our industrial strategy sets out a vision of a Britain that is confident and competitive, a global trading nation that is in charge of its own destiny, and HS2 can play a big part in that. Last year we announced which train builders were vying for the £2.75 billion to deliver Britain’s state-of-the-art high-speed trains. That investment alone will create many opportunities in this country.

I have said previously that during the procurement process, as we pick the organisations that will build these trains, it must be clear that they will have to leave a substantial skills and technology footprint in this country. We will not countenance trains being built in another part of the world, put on a ship and delivered to the UK, with no benefit at all to the UK itself. This project will have a lasting impact. Indeed, the whole construction of this railway will create jobs, careers, technologies and expertise that will last a new generation of engineers for a lifetime. That is another reason why it is so crucial.

Michelle Donelan Portrait Michelle Donelan (Chippenham) (Con)
- Hansard - - - Excerpts

Siemens in my constituency has been shortlisted to provide the signalling for HS2, and Chippenham hopes to benefit from the fact that 70% of the new jobs will be outside London. Does my right hon. Friend agree that this project has the potential to benefit the south-west as well?

Lord Grayling Portrait Chris Grayling
- Hansard - -

My hon. Friend is right, and I am delighted that Siemens has been shortlisted for that work. I want as much of the work as possible to be done in the United Kingdom, so that we can develop that skills footprint, developing those young apprentices and developing the engineering skills that we need for the future. That must happen throughout the United Kingdom: south-west, north-east, Scotland, Northern Ireland, Wales, south-east, midlands, the north and East Anglia. I want to see jobs and opportunities for British businesses, and businesses based in Britain.

Lord McLoughlin Portrait Sir Patrick McLoughlin (Derbyshire Dales) (Con)
- Hansard - - - Excerpts

Does my right hon. Friend agree that we have Crossrail as a model? It is being finalised this year, and will be operating next year. That project was built on the use of suppliers in the United Kingdom, and the spread of its supply network throughout the UK. Although it was a London project, many parts of the country have benefited from it. What HS2 is doing is the natural follow-through from what Crossrail did.

Lord Grayling Portrait Chris Grayling
- Hansard - -

Absolutely. Crossrail may be a project for transport in London, but it is also a project for engineering and industry in the United Kingdom as a whole. It brings benefits to all parts of the United Kingdom, and HS2 will bring benefits to all parts of the United Kingdom. Northern Powerhouse Rail, when it is built, will bring benefits in southern as well as northern England, and, indeed, throughout the United Kingdom. The more that we invest in these projects, the more economic benefits we will deliver across the UK.

Michael Fabricant Portrait Michael Fabricant (Lichfield) (Con)
- Hansard - - - Excerpts

May I ask my right hon. Friend not to take his eye off a distant ball, which is the future of the west coast main line after HS2 is constructed? More than 44 stations on that line will not be served by HS2. It is very important for passenger traffic to be maintained on the west coast main line, and to ensure that it is not used just for freight traffic.

Lord Grayling Portrait Chris Grayling
- Hansard - -

My hon. Friend is right. As one who has sailed through his local station many times, on Pendolino trains, I believe that we can and should do better at such intermediate stations. We should provide better commuter links to Birmingham and to towns such as Northampton and Milton Keynes, and we should provide better links within the Trent valley—from Nuneaton to Lichfield, and up to Stafford. We will be able to do all those things to a greater degree in the future. Yes, there will be a freight benefit. We all want a freight benefit, because we want fewer trucks on the M6 and the M1, but the fact is that we can do both. Creating that extra capacity on HS2, or via HS2, is, to my mind, its great benefit. It will of course be a fast, state-of-the-art railway, but first and foremost it is about giving our transport system the capacity that it will need to enable us to grow in the future.

I know that there are people for whom this project is bad news. There are people who are affected by the routes, many of whom are in my hon. Friend’s constituency. I genuinely wish it were possible—I am sure that Members in all parts of the House wish it were possible—to deliver infrastructure improvements like this without human consequences, but it is not possible. What we must do is try to treat those people decently.

HS2 has not always got it right, and we will not always get it right, but I give the House today an assurance that I have given it before: when an injustice is being done, we will do everything we can as a ministerial team to sort it out. Members need only come to us and say, “This is unfair”, and we will look at it. Indeed, I have already done so in places up and down the route, and I will continue to do so, particularly in respect of this part of the project. A number of constituencies on the route from the Trent valley up to Crewe are affected. As the two Ministers responsible, the Under-Secretary of State for Transport, my hon. Friend the Member for Wealden (Ms Ghani), and I will happily talk to colleagues during this process. There will, of course, be many opportunities for them to make representations about the impacts to the Committee, assuming that the Bill is given a Second Reading today.

Maggie Throup Portrait Maggie Throup (Erewash) (Con)
- Hansard - - - Excerpts

I appreciate what my right hon. Friend is saying today. We have also had many conversations about the ways in which some of my constituents are affected. That has been going on since 2013. We may get there in the end with compensation and agreements, but the problem is that it takes so long—far too long for some people. Some of my constituents are very elderly, and some are quite ill. Can my right hon. Friend reassure me, and my constituents, that we can improve the process?

Lord Grayling Portrait Chris Grayling
- Hansard - -

I absolutely give my hon. Friend that assurance. There are processes that we must rightly follow to protect public money, but there are exceptions that always step outside what is planned. Part of the job that we have, as Ministers, is to ensure that when those exceptions arise—and I know that there are two in my hon. Friend’s constituency, which she and I have been talking about—we must resolve them before we reach a point at which those people are suffering in their lives. We are a little bit of time away from the phase 2 Bill and the process involved in phase 2b. As I have said to my hon. Friend and to other Members, we will try to sort out those exceptions so that people do not suffer inappropriately. I will continue to work with my hon. Friend to try to resolve the situation.

Gareth Snell Portrait Gareth Snell (Stoke-on-Trent Central) (Lab/Co-op)
- Hansard - - - Excerpts

While the Secretary of State is handing out assurances, may I, on behalf of the people of Stoke-on-Trent, ask for an assurance that the existing direct and frequent services from Stoke-on-Trent to London, Birmingham and Manchester on the west coast main line will in no way be diminished or reduced as a result of HS2 taking up some of the capacity through the classic compatible services?

Lord Grayling Portrait Chris Grayling
- Hansard - -

As the hon. Gentleman will know—and I have given this assurance to my hon. Friend the Member for Stoke-on-Trent South (Jack Brereton)— I am acutely aware of the issues in Stoke-on-Trent. I want to ensure not only that the high-quality service that it deserves is protected, but that HS2 trains run through it, which is also what it deserves. I have given that clear commitment to the people of Stoke. I want them to have a first-rate rail service, and HS2 will make it possible for them to have an even better rail service than they have at present.

Let me say more about the affected communities. Last week we announced an additional £5 million for communities and businesses that are disrupted by the construction of phase 2a, which can be spent on public projects, community centres and so forth. That will add to what we have already committed in terms of the mitigation and compensation in place, and we will carry on looking at ways in which we can minimise the impact on local people and the areas affected.

Rebecca Pow Portrait Rebecca Pow (Taunton Deane) (Con)
- Hansard - - - Excerpts

I am totally in favour of the project, as train travel is environmentally friendly because it gets people out of their cars and on to trains. But will the Secretary of State reflect on the potential loss of ancient woodland because of HS2, and whether consideration might be given, where possible, to using tunnels so that we keep these wonderful, magnificent trees? We have only 2% of them left in the whole country. Will we consider doing this? If not, and if there is unavoidable loss, could we consider 30% amelioration, as recommended by Natural England, rather than the figures bandied about today?

Lord Grayling Portrait Chris Grayling
- Hansard - -

I am very well aware of the potential impact on ancient woodland. We have already made changes to the design of the project to try to mitigate that impact, and there is an absolute commitment to look to plant afresh and to develop environmental measures to compensate for any loss of woodland. Also, there are some exciting potential projects on the route that can enhance the natural environment at the same time as we are having to make changes elsewhere. I assure my hon. Friend that we are very sensitive to the issue she mentions, and we will do our best to make this project in as environmentally friendly a way as possible. We cannot build something new like this across the whole country without having some impacts, but we can try to mitigate them and put money into positive alternatives. That is what we are committed to, and that is what we will do.

This is a step on the way towards creating a 21st century new rail network: phase 1 to Birmingham, phase 2a to Crewe, eventually phase 2b to Manchester and Leeds, and then across the top with Northern Powerhouse Rail, and then, through that, the connections to the north-east, which the shadow Secretary of State will hold dear, to Scotland—colleagues on both sides of the House representing Scottish constituencies are keen to see that connection put in place—and into north Wales through the Crewe hub that we are working on at the moment.

This project will provide the capacity our transport system needs in the 21st century. It will deliver better journey times and, particularly importantly, much better connections between our northern cities—Birmingham, Sheffield, Leeds—where there are poor connections at the moment; this will make a huge difference to them. But above all this is about making sure this country has a 21st century transport system. I hope the project commands support across the House. I know that some Members have issues both about the principles of the project and constituency impacts. To those with constituency impacts I simply say again that we will do our best to minimise those and to work as closely as possible with them to make sure that people who are affected are treated as decently as possible.

This Bill is enormously important to this House, to the future of this country, to our nation, to strengthening our Union, and to delivering economic growth across the whole country, and I very much hope that this House will give it its support today.

--- Later in debate ---
Andy McDonald Portrait Andy McDonald
- Hansard - - - Excerpts

I am grateful to the hon. Gentleman for that intervention, and it is key that HS2 integrates. We have just heard words from the Secretary of State about the need to ensure that it does connect with our northern cities, but we are yet to see those plans unfurl. We have heard about Transport for the North’s aspirations, but this cannot be a stand-alone project; it is essential that it links into our great towns and cities throughout the nation.

Linking the great cities of the north and midlands is equally important and will bring much-needed economic benefits to those regions. Labour supports the nearly 30,000 jobs the construction of HS2 will deliver and the huge uplift it will give to apprenticeships and training, particularly outside London. It is not too early to consider how we will retain and develop those skills in the future in other infrastructure projects both at home and abroad. I would be interested in any comments the Secretary of State has on this point, particularly with regard to Northern Powerhouse Rail and Crossrail.

I also make a plea that we must not repeat the catastrophe of the Carillion experience with apprentices. Apprentices in my constituency are being left flapping in the wind, not knowing whether they are going to be paid. We hear today that their employment will come to an end at the end of this month. It is a disgrace that £6.5 million of public money has gone into an apprenticeship programme that leaves our apprentices short of their qualifications and without employment. The Government should intervene now to guarantee that those apprentices will receive that assurance from this Government today.

Lord Grayling Portrait Chris Grayling
- Hansard - -

I am grateful to the shadow Secretary of State for giving way, and he and I share that view. I can assure him that, on the HS2 project, the apprentices who were employed by Carillion are migrating to work for Kier and those employed by Carillion have been moved on to the project with the other two partners. So not only should there be no hiatus in the work taking place, but, more importantly, the people on those projects are moving to different companies involved in them. There are obviously some very difficult circumstances elsewhere as a consequence of the collapse of Carillion, but I have been very keen with this project to make sure we have the seamless transition we contracted for last summer, and I am delighted to see the apprentices move on in a way that enables them to carry on with their apprenticeships.

Andy McDonald Portrait Andy McDonald
- Hansard - - - Excerpts

I am grateful for that reassurance in the context of these projects, but I am particularly concerned about these apprentices in the here-and-now; there are 100 out of the 1,400 who have been prejudiced in my community and we want to see this Government respond by coming to the table and making sure those young people have a future. It is difficult enough to encourage people into these industries in the first instance without leaving them high and dry, as has happened on this occasion.

I welcome the commitments contained in HS2’s environmental principles. It is imperative that environmental standards and air quality are at the forefront of the project. Many of the arguments about why we need HS2, and why we do not, have been well rehearsed in this House over many years: passenger rail numbers have doubled since 1995; rail freight has grown by two thirds over the same period; and the existing network has been operating at full capacity for years. No amount of timetable-tinkering can change this; I trust that all Members are in agreement about that.

Although it is important to maintain our vital road network, there is an urgent need to secure modal shift across transport: we cannot build our way out of congestion on our roads, and we must be watchful about the sustainability of domestic air travel. In addition, we face the prospect of the population of Britain reaching 70 million by the end of the decade. So the question is: how are we going to move our people around our nation? It is no exaggeration to say that the very economic and social livelihood of this country is at stake. Our capacity to move people by rail and bus is therefore crucial.

--- Later in debate ---
Michael Fabricant Portrait Michael Fabricant
- Hansard - - - Excerpts

But the hon. Gentleman is thin, lithe and athletic. I am talking about a harried husband, a wife, squabbling children and loads of luggage. That is what I am talking about.

Lord Grayling Portrait Chris Grayling
- Hansard - -

May I take my hon. Friend slightly closer to home, not perhaps in his own constituency, but alongside? Those people who seek to commute from Rugby, Coventry, Birmingham International and intermediate stations into Birmingham find that their daily journey is delayed by the fact that this line, which is two-track only and which can only be two-track, has express trains, local trains, intermediate trains to Northampton and even some freight trains on it. It is chaotic and jammed all the time. HS2 takes off the express trains and gives those people a better commute into Birmingham. Is that not something that the west midlands should champion?

Michael Fabricant Portrait Michael Fabricant
- Hansard - - - Excerpts

My right hon. Friend is absolutely right about that. I do not think that there is any argument about the capacity problem. It was he, or perhaps it was my right hon. Friend the Member for Derbyshire Dales, who said that the west coast main line is operating at 100% capacity and that it is the busiest line in Europe. In fact, it is a triumph in that people have moved on to those trains in their millions since the time when a Labour Government were in power, and certainly since the time of nationalisation—and we all remember those curling sandwiches. Of course there are advantages, too, but it could have been done in a much better way. It is not a connected service. What do we have now? The genesis of it all was Lord Adonis who, in 2007, came up with the idea of the route. I can tell Members that he was astonished when the Conservative Government accepted that route. Again, let me say very clearly that I am arguing not against HS2 itself, but against the way in which it is being executed. That is what I am criticising. Lord Adonis wanted an ultra-high-speed line. As a consequence, he got rulers on maps, drew straight lines, crashing through countryside, which had previously not been damaged, destroying ancient woodlands, and generally messing up the entire area.