Ruth Cadbury
Main Page: Ruth Cadbury (Labour - Brentford and Isleworth)(3 years, 3 months ago)
Public Bill CommitteesQ
Martin Boyd: Unfortunately, my view is that the residents’ voice section of the Bill and the HSE’s current work is the weakest element of the whole process. The Government have not dealt with the issue of the residents’ voice particularly well for a very long time. There is no system at all in either the social or the private sector for the proper representation of everyone’s interests.
As we said, the landlord is obviously sitting in conflict. Under the Bill, I get to sit in conflict with my leaseholders because I have become the accountable person. Under me, I have a responsible person—one of Nigel’s managing agents—who will employ the building safety manager. With my landlord’s hat on, I am liable if things go wrong, but I have no responsibility for any of the costs. All the residents have full responsibility for the costs, but no control. It is only because I am a landlord and a leaseholder that we get that common interest. In both the social and private sector, we have had landlords who have undermined effective resident engagement for decades.
Early in the Bill’s passage, we set out a proposal for a formalised system to create a residents’ group on every site, and the view at the time was that that sat outside the Bill’s purview, but there is no point in setting up a system for cosy little decisions to be made that filter down to the residents, where you hand them a nice little infographic saying, “Please don’t store petrol in your flat.” That is what has been done. The social sector best practice group has produced an infographic, and one of the diagrams says, “Don’t keep petrol in your flats.” Well, if that is our view of the intelligence of people who live in flats, we have a very, very long way to go.
We need to take a very different approach to resident engagement, and what I have said to officials is that, rather than take a top-down approach—assuming that we call the landlord the top of the system—it should start at the bottom with people who actually live in the buildings. Give them the facility to organise themselves and represent their common interests.
Dr Glen: As a managing agent, I would much rather deal with a representative committee of residents than each resident individually, because obviously time is involved in that. It would be nice to think that those residents will represent everybody—that would be nirvana—although it will not always be the case.
This is a really difficult issue. It is always a surprise that people do not realise that managing agents often do not know who the resident is. Somebody will hide the fact that they are sub-letting, for a variety of reasons. They might not want the taxman to know that they are receiving rental income. They might not want to pay a sub-letting fee, or they might not bother to get around to it.
It is difficult to engage with residents when you do not know who they are, but capturing their voice means we have to do that. We also have to filter it. I will give you an unfortunate example that I read about on LinkedIn over the weekend. A firm that specialises in out-of-hours said that they had had a complaint from a gentleman. It was about an issue that did not need instant attention, because that would cost four times as much and he could wait until Monday. The firm received 155 phone calls from that person over two days, most of which were abusive.
Something I put in my paper was that we need somehow to figure out how to filter this. The example I gave was someone saying, “It’s a bit dark in this corridor.” Is that a complaint? Is it just ruefully saying, “My eyes are getting old,” or do I, as a managing agent, have to log that, report it to the regulator, track it and bring in somebody to install new lighting at the cost of £2,000 that weekend? I do not know.
This is a difficult area to get into, but the more we, as managing agents, can get a collective response, the less admin you are doing trying to deal with absolutely everybody.
Q
Martin Boyd: The answer on whether it is fully clear—I think we would fully agree on this—is that when you get into complex sites with mixed private, social sector and commercial, you are going to have a number of accountable people, a number of responsible people and, potentially, a number of building safety managers. The potential for conflict there is enormous.
The issue I have with the Bill is this: I can accept that you want to make me accountable if I get something wrong, but the Bill, if we use the analogy of cars, is trying to make me responsible for the fact that Mercedes produced a diesel engine that broke the rules. I did not design the building. I did not build the building. I am responsible, and fully accept I should be responsible, if we do something wrong with the management, but we, effectively, are non-exec directors. At any large site, that is how it will be.
Residents do not run their own building unless it is very small; they will contract and employ a professional managing agent. In turn, there is no such thing as a building safety manager at the moment. I do not see why they are needed at all in the occupation phase, because what a professional property manager does is contract a relevant expert when they are needed. If the air conditioning system, the lift system, various plant and machinery or the fire alarms need to be updated, they will go out to a relevant expert.
The idea that we are somehow going to put that expertise in one individual and that they will make the decisions is just going to cause conflict. The property manager will be trying to budget for how they plan to look after the building for the next five years, and the building safety manager will have a different set of priorities. As far as I understand it, the building safety manager wins—so what happens if the building safety manager spends all the money and there is nothing left for the property manager to spend? The answer is that they will just have to put up their bills, so we will have one set of building safety charge bills getting bigger and bigger, and another set of normal service charges getting bigger. It will cause problems.
Dr Glen: A big worry for me about the impact of having an accountable person, particularly where there are lay boards, is, to put it succinctly: who in their right mind would agree to be a director with that level of accountability? What are we going to do in those circumstances?
We have talked about potentially bringing in professional directors—that is one possible route, if the lease allows it, and that would be a cost, again. That is going to be an issue, I believe, for anybody in their right mind taking on that level of responsibility. What this might mean is that there are no leaseholder-led boards—they might appoint a professional who then appoints and instructs the managing agent accordingly, but you might see residents’ management companies and right-to-manage companies disappearing.
Martin Boyd: I think there is a risk, because if you want to make me responsible for Mercedes, you need to put me in charge of Mercedes. I am not going to do that, so I am stuck. People who sit on the boards of RMCs usually consider the matter quite carefully. You are taking on a serious responsibility, helping to look after the lives of other people. But you are doing it as a non-exec.
I make it clear to the rest of my board on regular occasions: “You do not interfere in operational matters.” We employ professional managing agents to do that. I think that the legislation needs to be structured to allow that non-exec position to continue because if you want to say, “I am suddenly going to make you criminally liable for matters you don’t control,” Nigel is right: who is going to be stupid enough to take that role? More importantly, a representative of the Association of British Insurers will be speaking to you in a while and I think you are going to struggle to find anyone who will insure that role or those of the building safety manager and the responsible person.
If there are no further questions, I thank the witnesses and we will move on to the next panel.
Examination of Witnesses
James Dalton, Steve Wood and Dr Sarah Colwell gave evidence.
Q
James Dalton: The significantly increased cost of fire is obviously passed on to all premium payers through increased premiums. For leaseholders in the post-Grenfell world, there have been very significant increases in the cost of insurance for some of the buildings that have been identified as most at risk.
I and the insurance industry particularly empathise with all leaseholders who have been affected, and we have worked hard to ensure that where buildings have not been able to access insurance, we have tried to facilitate insurance. The sad reality is that, in the absence of a quicker remediation programme, those leaseholders will continue to face increased insurance premiums.
Q
James Dalton: I would say that it is not just residential; it is in a number of buildings. If you think about the significant increase in online shopping, for example, which has driven the development of very large non-compartmentalised warehouses: those are very significant fire risks because they lack the structures internally. It is a problem that the insurance industry is cognisant of both here in the UK and internationally.
Q
James Dalton: I am not aware of issues in other jurisdictions. It is not fair to talk about the UK as a whole, because Scotland has a different regulatory framework, but I am aware that in the UK there are policy issues that we as an industry have long been calling for—for example, the mandatory installation of sprinklers in all new buildings, but particularly those that house and protect the vulnerable such as schools or care homes. Frankly, it is beyond belief that it is not mandatory to include sprinklers in those buildings when they are newly constructed. I am conscious that I am probably not answering the question, but I do not have any information and I would not want to mislead you. I can follow up in writing with research done by colleagues, if that would be useful.
Q
James Dalton: I thought you might be sick of hearing from me!
Let us start with what is good about the Bill. I think there is a lot in the Bill to welcome in the context of Dame Judith Hackitt’s golden thread of information. The devil will be in the detail, so we await with interest the secondary legislation that will underpin the Act. A lot of the technical detail is going to be there, and our industry along with many others will want to analyse and scrutinise that legislation.
What is missing from the Bill? If I am honest, we do not understand why the framework does not apply to buildings under 18 metres. Fire does not affect just those in buildings over 18 metres—it affects all buildings. Some of the most egregious examples of buildings that have been covered in cladding, with woeful fire protection mechanisms, are under 18 metres. We certainly think that the Committee should carefully consider applying the provisions of the legislation to buildings under 18 metres.
Steve Wood: I would support what James said. There is a lot that is good in the Bill and the NHBC supports the principles of the Bill. In terms of what is missing, it places a single Building Safety Regulator across the whole sector, private and public, and we suggest it is important that the regulator appoints to building control bodies on the basis of competence—not whether they are from the public or private sector. That is an area we are concerned about.
We welcome the single regulator, but please appoint to building control on the basis of competence; otherwise, there could be real issues in terms of capacity and confidence in the sector, which might slow down new home building and potentially lead to less safe buildings. From the previous session, and reinforcing what James said, there is still quite a lot of detail to work through in the secondary legislation. That includes details around accountable persons. Given all the people involved in the design and construction phases of developments, particularly complex developments, we should work harder to get accountabilities clear where we can. There is more to work through on product certification as well, but someone on the panel will be more of an expert on that than I am, I suspect.
We welcome the Bill, but there are a few areas that need to be worked through to get it right. The principle should be to build right first time to avoid these issues. There are big structural challenges in the industry to do that, and that is where the focus should be.
Dr Colwell: I would agree with the previous panellists: it is a welcome Bill with a lot of good frameworks and overarching challenges within it. We would all agree that, as practitioners, the devil will be in the detail as to how that actually comes into place. Going forward, we welcome the introduction of the competency roles, and the understanding of building materials and the role they play within the structure.
Throughout this process, one of the things that has been commented on frequently is the golden thread. The one thing that we are seeing and hearing throughout these sessions is that the thread is more complex, and is potentially a network or a web. As such, the legislation that supports this—the secondary and the line part—needs to be clear that it does not end up conflicting, but rather carries the whole process through and leads us to safe buildings.
Q
Alison Hills: Yes, I have to say that I think that would be helpful. When we found out about all the defects in our building, it was in the middle of lockdown, so we were stuck for 24 hours a day in a flat that was potentially unsafe. All these videos started coming out on Twitter about Grenfell, the fires and Kingspan. It was absolutely horrific, from a leaseholder’s perspective: people were genuinely frightened to send their children to sleep at night.
I cannot reiterate enough just how difficult that period was. That was one of the reasons that I made the decision to move out; I am lucky that I had that choice, but many others do not have it. Many are still putting their children to sleep at night in a building where they do not feel safe. Leaseholders absolutely need more support with that. They also need more mental health support, because we are just relying on each other at the moment. There is a very good cladding community, and the leaseholders have been a brilliant support—my MP Daisy, who is on the Committee, has been a brilliant support as well—but I think that the Government need to take more responsibility to support their constituents with the mental health impact. I cannot reiterate enough how difficult it has been.
Steve Day: I think that leaseholders supporting each other is one thing, but you have to remember that the building safety fund has asked us to create all these reports showing all the defects. Unless someone comes and fixes those defects, the horse has bolted. The building safety fund reports show all these missing fire barriers, cavity barriers and internal fire stopping. If you check approved document B, getting the fixings wrong has a material impact on the fire rating of the external wall system.
Unfortunately, you have turned millions of people into fire experts. We now know what ADB says, and we now know that a small difference in the render thickness of our external wall systems can have a material impact on the fire rating. We know, when we look at the safety certificate from the British Board of Agrément for 100 products across the UK, that not meeting the exact specifications contravenes the certificate; the head of the BBA confirmed that, and I am grateful to him.
We know all that and we have all that information, yet not only have we been left to pay for it all, potentially, but we have all the worry of it. You cannot put that back in the box unless this is remediated. Unfortunately, in the leasehold community, we have been exposed to an awful lot of fire safety evidence that would lead us to believe that we are not in safe homes. Until the remediation is done, I just do not think that we can put it back in the box.
Alison Hills: I have not specifically been asked a question about this, but another problem is that the building safety fund process has been very difficult. The fund only covers some defects in some buildings. We have been told that we are eligible, but we still cannot get any of the fund because there are a number of onerous contract terms. MHCLG and our managing agent have been at loggerheads over the contract terms for almost the past year, and we are in limbo with a huge potential bill of £200,000 hanging over our heads. That is just not an acceptable position to be in—we simply should not be in that position.
Q
Alison Hills: First of all, I do not think that there should be any height restrictions to the building safety fund. We have seen videos in which the 18-metre figure came up because the people making the decision did not have time to come up with a better figure. There does not seem to be any reason behind the 18-metre rule. The materials are still flammable in buildings under 18 metres; they can still catch fire, as we have seen.
In my view, the building safety fund needs to cover all heights of building and all defects, not just cladding. I have spoken to a shared owner in the London Olympic park who does not have any cladding on his building, but who is facing an £80,000 bill just for missing fire breaks and insulation. That is just an unacceptable position to be in. There are a number of fire safety defects that do not relate to cladding, and they should absolutely be covered.
Steve Day: I would say, “Have a look at the materials.” We all accept that ACM cladding, linked to Grenfell of course, is dangerous, but you may not have realised that the Victorian Building Authority conducted a test last year and concluded that expanded polystyrene, because of very rapid vertical fire spread, ultimately creating fire pools that go down as well as up—not the pools, but the fire—was as dangerous as ACM. Why do we have this categorisation that ACM is the only dangerous cladding when EPS has been proved by the VBA to be as dangerous? That has implications on the 8414 tests because everyone knows that the grate is at the bottom of the rig. How do you test downward fire spread if the grate is there? It will just test upward, so there are issues there.
This is why I am always talking about trust. We need to get back to trusting our materials. We need to get back to having a large stick if the cladding manufacturers mis-sell products. In the aftermath of the Grenfell fire,181 samples failed combustibility tests. We need a big stick. The building industry and the construction industry are showing that they cannot be trusted, unfortunately. That is why we need full redress.
Q
Alison Hills: Again, I think there needs to be clear definition in the Bill of how often access will be granted and for what reasons, how much notice will be given, and who will come into the property. There are so many unanswered questions in leaseholders’ minds at the moment, and it needs clear definition in the Bill, in my view. Otherwise, it potentially brings up privacy issues.
Steve Day: Get rid of the gas boilers as quickly as we can. They are not great on high rises.
Q
I want to touch on residents’ engagement. It is hugely important. We saw that with Grenfell, and what was missing. Earlier witnesses said that the residents’ engagement section of the Bill is potentially one of the weakest parts. How do we strengthen residents’ voices, and the imbalance of power that exists? How would you reflect what residents need within the Bill to ensure that their voices are heard?
Steve Day: We need to have very good transparency from our managing agents. Often we cannot see the reports that are about the safety of where we live. We cannot see the accounts to see that they are spending the money correctly. We are given a very high-level aggregate view that often does not check out to what we are paying, so that side of things needs to be transparent. There needs to be a lot of thought towards how residents are engaged as well. Not all residents have the inclination to get together and form a committee. How do you handle that? Do the managing agents pick on one person and say, “You’re responsible for it”? I think that could all be strengthened.
Alison Hills: Luckily, in our block, our managing agent has been very forthcoming. We have regular meetings with them every two weeks. That position is quite lucky, but it took a lot of work to get to that point. A lot of leaseholders across the country have managing agents who do not share information, fire risk assessments and even evacuation plans. We have seen, particularly for disabled leaseholders, that some blocks do not have any evacuation plans at all. I think that is completely unacceptable.
Information sharing is the key point. Residents do have a right to see this information. It affects their lives; it affects their health and safety; and it affects their mental health. They need to know what to do in the event of a fire; they need to know what the defects are; and they need to know what the next steps are. As I said, my managing agents have been good with that, but many others have not.