Sir John Armitt: I would argue that local planning committees are not really professionally equipped to deal with NSIPs. As I said at the beginning, these are very significant projects. They are likely to be in the interests of a much broader area than that which any single planning committee is going to be taking an opinion from. The planning committee inevitably finishes up looking at things through a local lens, and I would argue that that is not really appropriate for projects of national significance. Clearly, their views can be taken, but one should recognise that local interest when doing so, and that should be set alongside the much broader considerations, recommendations and advice that could sometimes be received from much larger statutory bodies that clearly have a much more national interest.
Robbie Owen: Certainly, I do not see local planning committees as being particularly problematic so far as responding to proposals for national infrastructure projects is concerned. That is a segue into a broader point: improved guidance could be given by Ministers, not just to applicants about how they should go about their pre-application consultation and engagement, but to local authorities and other public bodies about how they should respond to proposals for national infrastructure.
Response performances, if I can put it that way, from local authorities differ markedly across the country. More uniform guidance would be really helpful there. The changes that the Government heralded yesterday in terms of pre-application consultation pave the way for a new set of guidance dealing with the pre-application period, because that is where most of the delay rests at the moment. As the Government said, and I agree with them, yesterday’s changes should really help to about halve the pre-application period, and that would be very welcome.
Q
Sir John Armitt: There are two things there: what should the target be, and will the Bill deliver it? I think the target clearly should be to try to get back to what we were handling and seeing back in 2010 to 2012. That was just over a two-year period. These projects are getting more complex and getting a lot larger—there are some very big ones coming down the line in the next 10 years—but if we could get back to that sort of level, clearly that would be welcome. Would the Bill deliver that degree of improvement? Frankly, I would be surprised.
Robbie Owen: We should not forget the role of national policy statements. They became rapidly yellowed at the edges in the late 2010s, which led to a dramatic increase in judicial review of decisions. The Bill does include a number of valuable proposals to improve how national policy statements are kept up to date. It is really important that they are, because they are the basis for decisions that are then taken on individual projects.
As a rule of thumb, we should really, at the very least, be aiming to be getting back to the performance levels in about 2015, which were approximately 12 to 18 months for pre-application and then around 15 to 18 months from application to decision. Obviously, if we could improve on that a little bit, that would be ideal, but if we could get back to that, that would be my rule of thumb.
Q
Beatrice Filkin: One of the purposes of the queue reform is to make sure that the projects that we need and are ready earliest get earlier access to the network. At the moment, we have a lot of projects in the queue that are at an early stage of development, and are not so critically needed by the strategic plans that we are setting out. Projects such as connections for demand or for factories are already in the queue and are deemed as needed. They will therefore be prioritised for the queue, and we expect their connection dates to improve as a result of the connections reform process.
Q
Dhara Vyas: I think that the Bill is going to be crucial. It was as true for the previous Government as it is for this Government that clean energy and investment in clean power is seen as the safest and surest way to ensure the UK’s energy security. There is a programme of work for investing in clean power, but there is absolutely nothing to be gained from all of that net investment unless we can move it around the country. That is why this part of the energy industry is so crucial.
In terms of the impact on bills, the reality is that, at one point, energy bills were four times what they were in 2019. We are now seeing bill debt of £3.8 billion and growing. It is also important to note, generally speaking, that households are under more pressure now than they have been for well over a decade. I think more than half of households who go to Citizens Advice have a negative budget. Households are really feeling the pressure, and the conversation about energy bills has not really been off the front pages for the last four years.
As for being able to expedite the investments in clean power and make sure we are reducing the amount we are spending on curtailment costs, that should mean that in the future, if we experience an energy shock again, we will not spend the £40 billion that was spent in 2022-23 to support people. That is why this is so important.
Q
Dhara Vyas: I think it links neatly to the last question around demand. The reality is that we need to decarbonise business in a significant way. Right now, what businesses in this country are paying is among the highest of OECD countries, if not the first or second highest in that group. This is a big part of the discussion with the Department for Business and Trade around the industrial strategy.
Energy and the price of energy is hugely significant to business users, as well as to households. So while we need to be having conversations about linkage with Europe, we also need to be having significant conversations here about how we can speed up demand and connections for demand—and have that conversation for both homes and businesses. More broadly, we also need to be having a conversation about how we support businesses to consider how they can move off their dependence on gas.
Q
Beatrice Filkin: What has happened to date is that NESO has done some preparatory work assessing options. We have made a decision about how they should go about reordering the queue based on need and readiness —that is the decision we made last week. NESO now needs to implement that decision, which is what they will be doing rapidly over this year to make those choices.
For the reordering of the queue, it will prioritise the projects that were due to connect in the next year or two, first of all, and then the completion of all the projects that are needed for clean power by the beginning of 2026. That is the process. We are not walking away from that. We are regulating NESO, but also working with them on this process. We see this as a very critical enabler of clean power. Working through this year of that process, we will be a partner alongside them. That is also why we very much welcome the provisions in the Bill to provide the legislative security of what they are looking to do.