Planning and Infrastructure Bill (First sitting) Debate
Full Debate: Read Full DebateLewis Cocking
Main Page: Lewis Cocking (Conservative - Broxbourne)Department Debates - View all Lewis Cocking's debates with the Department for Energy Security & Net Zero
(1 day, 15 hours ago)
Public Bill CommitteesWe are now sitting in public again and the proceedings are being broadcast. Before we start hearing from the witnesses, do any Members wish to make a declaration of interest in connection with the Bill?
I was a planning consultant until the general election, but not any more. I am a chartered town planner member of the Royal Town Planning Institute and a chartered architect member of the Royal Institute of British Architects. I am a vice president of the Town and Country Planning Association, but that is an honorary position, so I have no pecuniary interest.
Q
Dhara Vyas: I think it links neatly to the last question around demand. The reality is that we need to decarbonise business in a significant way. Right now, what businesses in this country are paying is among the highest of OECD countries, if not the first or second highest in that group. This is a big part of the discussion with the Department for Business and Trade around the industrial strategy.
Energy and the price of energy is hugely significant to business users, as well as to households. So while we need to be having conversations about linkage with Europe, we also need to be having significant conversations here about how we can speed up demand and connections for demand—and have that conversation for both homes and businesses. More broadly, we also need to be having a conversation about how we support businesses to consider how they can move off their dependence on gas.
Q
Beatrice Filkin: What has happened to date is that NESO has done some preparatory work assessing options. We have made a decision about how they should go about reordering the queue based on need and readiness —that is the decision we made last week. NESO now needs to implement that decision, which is what they will be doing rapidly over this year to make those choices.
For the reordering of the queue, it will prioritise the projects that were due to connect in the next year or two, first of all, and then the completion of all the projects that are needed for clean power by the beginning of 2026. That is the process. We are not walking away from that. We are regulating NESO, but also working with them on this process. We see this as a very critical enabler of clean power. Working through this year of that process, we will be a partner alongside them. That is also why we very much welcome the provisions in the Bill to provide the legislative security of what they are looking to do.
Q
Beatrice Filkin: We have made a decision about the way in which NESO now prioritises the queue. They are doing that going forward. Our decision-making process was finished last week. That is the process by which they make those decisions. They are now going to implement that decision and do that re-ordering decision—individual decisions—over the year.
Q
Beatrice Filkin: We have set out in our decision the way in which NESO should assess the queue. They will use the information that we set out last week—that guidance—to implement and take each individual project, weigh it up against the criteria, decide whether they meet the need and the readiness requirements and use that to sort through the queue. That is a process. They will operationalise our decision of last week.
Christianna Logan: On the practicalities of how that will be approached, NESO’s proposal is that the customers with connections contracts will provide evidence of their readiness to meet the criteria, in terms of things like submission of planning consents and land rights—ways that they can evidence they are progressing their projects at the pace necessary to achieve the 2030 goals and, as Beatrice said, against the strategic alignment of different technology types with the needs of the clean power plan. Customers will put forward their evidence that their projects are best placed. NESO will use that to assess which ones should go forward. Within that, there is some protection for projects that are already well progressed, so that we do not impact investments that are ready to be deployed to hit those targets.
Q
Beatrice Filkin: What we set out in the decision last week sets off the piece of work that NESO are doing over this year. That helps projects, because as we have talked about, there are a number of projects in the queue that are either nowhere near ready or are not deemed needed for the overall strategic plan. So the process of sorting through the queue will speed up that very constrained access to the network to enable those projects that are needed and ready to join and connect to the network earlier.
Q
Beatrice Filkin: Are you asking whether it provides an opportunity to local communities?