Commons ChamberI do not want to detain the House for too long. However, I want to say a few words as the Member of Parliament for Maldon, which contains Bradwell-on-Sea.
Bradwell had been the home of a nuclear power station since the early 1960s, and it safely generated power for nearly 40 years before being successfully decommissioned. I remain a strong supporter of nuclear power, and I agree with my hon. Friend the Member for Isle of Wight (Bob Seely) that it is not a question of choosing between renewables and nuclear. We will need both if we are to achieve our ambitions, particularly our ambition to reduce carbon emissions.
The fact Bradwell has been the site of a nuclear power station for so long is probably the reason why it was chosen as one of the designated sites for new nuclear development. Of course, an agreement was reached between EDF and China General Nuclear Power Corporation whereby Hinkley Point and Sizewell would be majority owned and financed by EDF with some Chinese contribution, but Bradwell would be the site of a Chinese-designed and majority Chinese-financed reactor.
I visited China General Nuclear in Shenzhen when I was Secretary of State for Culture, Media and Sport, when the attitude of the British Government was perhaps a little more friendly towards China than it is today. At that time the Government were keen to encourage investment in Bradwell, partly because it appeared to be the only way that we would be able to finance new nuclear, as the Chinese were the people who had the resources and the willingness to do so.
My hon. Friend the Member for Isle of Wight referred to the concerns about Chinese technology, and my concern is not about the safety of Chinese technology. The Chinese reactor is now well advanced in the generic design assessment process, and it appears to be proceeding smoothly. I suspect it will be found to be safe, but there may be other reasons why the British Government are perhaps less keen on the idea of a Chinese-owned and designed nuclear power station in this country than they were five years ago. I fully appreciate and understand the reasons for that.
Bradwell is one of the few locations to be designated as appropriate for new nuclear, and the site is owned by CGN. If the Government decide it is not appropriate to build a Chinese reactor, I would still like to think Bradwell is a possible site for an alternative nuclear power station development. Whether or not the Government reach that decision on China, it is too early to say, and I am sure the Minister will not be in a position to say definitively this afternoon, but I would like to put it on record that Bradwell successfully hosted a nuclear power station for 40 years—Bradwell A—and I saw the benefits it brought to the local community. I would therefore still be positive about the possibility of Bradwell B, whoever designs and owns it.
I rise to speak to the amendments tabled on Report. You will be interested to know, Mr Deputy Speaker, that I would also like to talk about the Bill and its contents.
Order. Dr Whitehead, do you intend to keep your mask on?
Sorry, no—I have a general habit of wearing a mask whenever possible.
The Bill essentially falls into three parts. Part 1 concerns the designation of a company for the receipt of regulated asset base payments. Part 2 concerns the collection and disbursement of funds through the regulated asset base arrangements. Part 3 sets out a special administration regime, should a nuclear power plant be unable to carry out its obligations arising from the institution of the regulated asset base arrangement.
The Bill, essentially, is trying to produce a method for funding and getting over the line one particular nuclear power plant: Sizewell C. That is the only plant that is developed enough to be able to generate by 2030. A substantial part of the Bill is not about the general future of nuclear, or the relationship with nuclear renewables; it is about how one plant is to be financed over the next period so that it can actually start producing energy, hopefully by the end of this decade or shortly thereafter.
The Labour party supports nuclear power for the future and is particularly concerned that, for example, the Climate Change Committee has indicated that some 8 GW of nuclear power might be put in the mix for low-carbon renewable power for the future. Sizewell C is an important part of that process—indeed, getting it going is long overdue. Perhaps I can put the record straight, because the previous Labour Government, as the 2007 nuclear White Paper and the strategic planning documents of 2009-10 show, laid the basis for the present number of sites to be considered and, therefore, for nuclear power going forward.
The hon. Gentleman is absolutely right, but unfortunately we lost a decade, from 1997 to 2007, when nuclear was taken off the table. Because of the timescales, which he is well aware of, will he just accept—this is not necessarily party political—that losing that decade put us back and is costing us now?
The hon. Member is quite right that prior to 2007 the Labour Government did not consider the development of nuclear power by state means to be an appropriate way forward, although they never suggested that the development of nuclear power by private means could not be countenanced. However, we have since had more than 10 years of Conservative-led Government, which has produced precisely no nuclear power plants. Indeed, there is one nuclear power plant in the pipeline, and we hope a nuclear power plant that can be financed by reasonable means. One of the problems with the previous plant, Hinkley Point C, which the present Government got off the ground, was the funding arrangements, with EDF supplying most of the capital for the plant and then a CfD for the plant at the end, which looks like it will be quite disastrous, with future electricity prices being completely uneconomic.
It is therefore important that we get a method for funding those nuclear plants, and particularly Sizewell C, that does not fall into those traps and is also secure for the future. That is the concern of our amendments 1 and 2. To put the record straight, anyone who looks at those amendments reasonably closely will see that amendment 1 defines what is stated in amendment 2, and that it is defined as
“means owned by a company controlled by a foreign state and operating for investment purposes.”
That does not include EDF. Let us be clear from the outset that EDF is not
“a company controlled by a foreign state.”
Although it is substantially owned by a foreign state, it is not operating for investment purposes, but for production purposes. Let us be clear about what the particular concern is for the future.
Please correct me if I am wrong, but my understanding is that EDF is majority owned by the state. If the state required it to do certain things, I do not see how the company could say no. Could the hon. Gentleman confirm if that is his understanding?
It is correct that EDF is owned by the French state, but it is not controlled by the French state and, as I say, it does not operate for investment purposes. The amendment specifically excludes that kind of company from its provisions, but, importantly, it includes companies such as the China General Nuclear Power Corporation, which is clearly owned and controlled by a foreign state and operates for investment purposes.
This is incredibly important. The amendment states
“the nuclear company is not wholly or in part owned by a foreign power”.
Factually, that is the situation with EDF. I do not have a problem with it, but I am trying to explain to the hon. Gentleman that his amendment does not say what he has just said it does, and it is therefore inaccurate, even by what he is trying to achieve.
I am afraid we will have to differ on that. Amendment 1 has been written on good advice, in terms of what EDF does and does not do in its operation, and, on the contrary, what a company such as the China General Nuclear Power Corporation does. There is a clear distinction between those two particular companies and organisations.
The amendments wish to draw attention to the fact that this is not an academic issue. As the right hon. Member for Maldon (Mr Whittingdale) mentioned earlier, we have an agreement in place at the moment whereby the Chinese state nuclear corporation has a 35% stake in Hinkley Point C, a 20% stake in Sizewell C, should it go ahead, and complete control of Bradwell, should that go ahead, with ownership of the site and operations, and with the installation of a Chinese reactor. That agreement has already been reached, so the issue in this Bill is that if the regulated asset base is going to be put in place to finance and bring about the control of a nuclear power plant by the Chinese Government over the next period, we think that that would be a retrograde step for the future of nuclear power in this country, for obvious reasons.
In Committee, we asked the Government whether they wished to make any statement about the future of the agreement that is currently in place, which was agreed between 2013 and 2016 and includes the Secretary of State’s investment agreement, and about future arrangements for nuclear power. We asked if they could they confirm that RAB would not be used as an instrument to extend those arrangements, as far as the Chinese Government are concerned. They have not said anything about that at all; I regret that. Hence we have brought these amendments to try to clarify what RAB will be used for, what the position is concerning the 20% of Sizewell C that looks to be owned by the Chinese Government in the future, and how that relates to RAB overall. Although it is not central to the RAB debate, it is an important element in that debate and needs clarification for the future.
We did not particularly want to table these amendments. If we had had a statement from the Government that they were not proceeding with Bradwell and were going to bring an end to the arrangements that are in place for Sizewell C at the moment, perhaps things might have been different, but we urgently need some clarification about their intentions in relation to RAB and Chinese involvement in UK civil nuclear power in future. That is what amendments 1 and 2 would achieve.
I welcome these amendments because one of the concerns about RAB is that there are no safeguards, so the developer could run up costs and there would be nothing to stop them doing so. Therefore, if the Government do not accept the amendments, would it not be irresponsible to support the Bill on Third Reading?
It would not be irresponsible to support the Bill on Third Reading, but it would be responsible of the Government to take a little more notice of these particular problems with the RAB process and possibly, as we move forward with its development, bring in mechanisms that can protect the bill-paying public in a rather better way than is suggested at the moment. That is essentially what the amendments do.
The arrangement for the RAB to be put into place is that a series of considerations are entered into to give an agreed expenditure cap for what is considered to be the proper use of the collection fund that will provide assistance to the company producing the new nuclear power plant. It can properly draw on that, up to a certain ceiling, from the general public. That is if everything goes well with the nuclear power plant, but of course that may not necessarily be the case. Of 176 nuclear power plants across the world, 175 went substantially over time and over budget, so we need to be very clear that we should not commit the general public to fund these proposals completely open-endedly. We are saying in these amendments that should there be a cost overrun or a time overrun, the Secretary of State should seek an increase in the agreed revenue ceiling without further recourse to customer funds. That may be by producing bonds or it may be by further state funding if that is the choice the Government wish to make, but they should not increase the ceiling for customers to pay exponentially at the same time.
These are very simple and straightforward amendments saying that, should there be such cost overruns or time overruns and there is a suggested further call on customer bills through RAB, the Secretary of State will have to think of something else to fund the system. Let us be clear that, with the RAB arrangements at the moment, it is suggested, I think very optimistically, there will be an increase of about £10 to £20 in customer bills. That is a really current topic at the moment, but a cost overrun would substantially increase such a levy on customer bills, and we just think that should not be part of the RAB arrangements for the future.
The third set of changes we wish to put in place are to part 3 of the Bill, which sets out what should happen and what arrangements should be in place if a company, despite all the investment from the public in the construction of a nuclear power plant, essentially goes bust. In this part, the Government have in effect lifted the provision in the Energy Act 2011 for a special administration regime. Again, that is rather current because it is precisely such a special administration regime that was used to rescue Bulb Energy when it went bust a little way ago. It was placed in such a regime under the 2011 Act—the wording is identical to that in this Bill—to allow it to continue trading for the time being, subject to the company being disposed of.
However, I would suggest that a nuclear power plant the size of Sizewell C, for example, is not remotely the same as an energy company the size of Bulb. It would be quite possible to dispose of Bulb or disperse its customers according to the special administration regime, but that would not be the case for a large nuclear power station. We are saying in amendment 5 that there should be an additional backstop so that, in the circumstances of a special administration regime, it would not be possible to pass the company on—to sell it on or to reintroduce it as a going concern through allocation to a subsidiary—and that the Government should have a plan to introduce a public company to take it over, provided it is working as a nuclear power station. That would not be the case—some Members may think the amendment means this—if the power station could not continue because the reactor head had exploded or the power plant was otherwise non-operational. If it is an operational power plant, we think that such a backstop should be available.
Hon. Members have mentioned what I think is the salutary case of the North Carolina energy plant that was conceived under RAB arrangements, or something very similar. Some $9 billion of customer money went into that plant, but the plant went bust, not because it was not operational, but because it was unfinanceable. Customers lost $9 billion of money, and there is no power station at the moment.
Is it not the case that, if the Government in power are faced with a big financial disaster from a very large project going horribly wrong and the company going bust, they will need flexibility to make the best decisions they can in the interests of the taxpayers and customers at the time, and it is quite difficult for us to pre-think that and embed it clearly in law?
That is precisely why we wish to put in the Bill that there should be a direction in which the Government should go. Of course they should have flexibility in how they work, but we think this is an important backstop that will ensure customers do not lose their shirts in a company that goes bust after they have invested large amounts of money in its operation.
We will seek to divide the House on amendments 2 and 3 in the absence of any clear further Government commitments today in relation to. We may well be minded to support amendment 9, tabled by the SNP, should that also be put to a Division. However, I emphasise that we are happy to support the Bill overall. We want it to go through Third Reading, but we would like it to be strengthened as much as it can be by the addition of the amendments we have put forward today.
First, may I minute my condolences on the death of Jack Dromey? I shared his 12 years here and he made an enviable contribution to the House. Particular condolences to the right hon. and learned Member for Camberwell and Peckham (Ms Harman).
I am thankful for the excellent contributions we have heard today, and over the past few weeks during the passage of the Bill through the House, from Members throughout the House. I will attempt to address all Members’ comments and explain why the Government do not believe that today’s amendments should be accepted.
I turn first to new clause 1, tabled by the hon. Member for Kilmarnock and Loudoun (Alan Brown) for the SNP, regarding the special administration regime, but before I deal with his amendments, let me reflect a little bit on the contribution by my hon. Friend the Member for Gloucester (Richard Graham). The SNP, as we know, is talking today about transparency, but its real agenda is a hardcore anti-civil nuclear power agenda. This comes, ironically, just a few days after the closure of the Hunterston power station, which had its life extended by two decades beyond what was predicted and provided 31 years—31 years—of zero-carbon electricity to every home in Scotland. The Bill would make things cheaper, but I do not think that the SNP has got Scotland’s best interests at heart here for Scottish electricity or Scottish consumers.
Nuclear power has been a massive success story in Scotland, which is what I hope the Bill will also enable. New clause 1, tabled by the hon. Member for Kilmarnock and Loudoun, would severely risk the effectiveness of the special administration regime by delaying the speed at which an administrator could access funding to continue a nuclear RAB project construction or a plant’s generation of electricity. That could result in significant sunk costs for consumers and is not in the public interest.
I will turn now to Labour amendments 1 and 2, tabled by the hon. Member for Southampton, Test (Dr Whitehead), while responding to some of the points made in the debate. The hon. Member and I are aligned in our concern that foreign investment in our critical infrastructure should not come at the cost of national security. However, I want to be clear that the Bill is not about decisions on individual future projects; it is about widening the pool of potential investors and financing while reducing our reliance on state-owned developers to build new nuclear power stations. As the House is aware, we have committed to taking at least one project to final investment decision in this Parliament, subject to value for money and all relevant approvals. We are in active negotiations on the proposed project at Sizewell C. The hon. Member argued that the approval of Hinkley Point C would inexorably lead to the approval of other projects. That is simply not the case. Decisions on nuclear projects in this country are made on a case-by-case basis, and subject to a number of robust approvals from both Government and independent regulators.
The Bill, as its title suggests, is about how to finance nuclear power. We know that the Climate Change Committee has indicated that some nuclear power is needed in the future as part of an overwhelmingly renewable energy mix. The Bill is therefore important in ensuring that we get at least the next, and only, nuclear power plant that can generate power by the early 2030s in place and developing, as the prospects of a new plant elsewhere seem bleak.
We welcome the arrangements that the Bill will make for financing nuclear power. We need to remember that there has been a 10-year hiatus, during a time of Conservative Government, in bringing forward any nuclear power, so the Bill is welcome, but overdue. We hope that with the RAB model in place, Sizewell C will be able to reach financial closure and go ahead.
We ought to understand both the advantages and possible problems of a RAB model, in the context of the people who will fund it from their bills. Although RAB has been used for other projects, a RAB model of the size and scale needed for Sizewell C has never been attempted. We urge the Government to be very careful about how they deploy the RAB model in terms of the customer interest, to not just regard customers as a milch cow for overruns or time delays in nuclear power for the future, and to ensure that the customer contribution is properly regarded as far as nuclear power development is concerned. We think the Government should pay closer attention to customer involvement in RAB, particularly because, on this occasion, the customer is funding the nuclear plant before, and not after, it develops. Careful stewardship and close custody of how that RAB model is used is vital.
The question of ownership of plant is important for UK national security. Although the Government have rejected our amendments about foreign influenced or owned investment in nuclear power in the future, we all know what that is actually about—the role of China and the Chinese state nuclear corporation, the China General Nuclear Power Corporation, in Sizewell C, and the possibility of them owning the nuclear power plant at Bradwell in the future. Despite the Government’s bluster, we know the arrangement is now in place for that development to succeed. Is that a wise way to go with nuclear power in the future, we ask?
We consider it imperative that the Government are clear about what they think about Chinese involvement in the very near future, and that they plot a clear course whereby this RAB investment is not the vehicle for the realisation of China’s developing and owning a nuclear plant in the UK, with all the security implications that has. I urge the Government to come forward at an early stage with clarity on what they consider to be the future for that arrangement. As the Secretary of State knows, that was not arranged on his watch, but in 2013 to 2016, before he was a Minister. I hope he will be able to cast an eye over the arrangement, with a view to the future that he has set out today.
With my party being in favour of nuclear power, I repeat the question asked by the hon. Member for Kilmarnock and Loudoun (Alan Brown) about the £1.7 billion in the Red Book at the last Budget for the completion of the project. Is it about buying off China? Is it about developing this project? Is it about funding further nuclear power for the future? We have no clarity at all, as we have only one line on that investment, which is not good enough. We need much more clarity for the future.
The health and welfare of Springfields is vital to this development, as it could be and should be supplying nuclear fuel rods to the new plant, and we hope the Government will look carefully and sympathetically at the future of that company, because the delivery of British fuel rods to a British nuclear reactor is very important for the future. It is vital that the Government do not allow the company to slip away under their watch when its contribution could be so important to the future of nuclear power in the UK.
Overall, we see much to support in this Bill and believe that, properly executed, its provisions will be able to establish a viable way forward for UK nuclear power. We therefore wish to support its Third Reading.