To ask the Secretary of State for Defence, what the average length of time is between his Department sending an Invitation To Negotiate and a procurement contract coming into effect.


Answered by
James Cartlidge Portrait
James Cartlidge
Minister of State (Ministry of Defence)
This question was answered on 30th April 2024

The average days between 'Awarding Date' and 'Publication Date' for Invitation to Tender (ITT) /Invitation to Negotiate (ITN) on the Defence Sourcing Portal (DSP) is 149 Days.