Royal Navy: Type 31e Frigate Debate

Full Debate: Read Full Debate
Department: Ministry of Defence

Royal Navy: Type 31e Frigate

Lord West of Spithead Excerpts
Thursday 6th September 2018

(5 years, 8 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Asked by
Lord West of Spithead Portrait Lord West of Spithead
- Hansard - -

To ask Her Majesty’s Government whether they still plan to have the first Type 31e frigate in Royal Naval service by 2023.

Earl Howe Portrait The Minister of State, Ministry of Defence (Earl Howe) (Con)
- Hansard - - - Excerpts

My Lords, there has been no change in the Government’s plans to procure a first batch of five new Type 31e frigates. We still want the first ship to enter service by the end of 2023, with all five ships delivered by the end of 2028.

Lord West of Spithead Portrait Lord West of Spithead (Lab)
- Hansard - -

I thank the noble Earl for his Answer—in “Yes, Minister” terms, he is very brave to make that statement. Our great maritime nation has 13 ageing frigates, which is a national disgrace. Replacing them is crucially important. The first design contract for the Type 26 frigate, the key replacement, was placed in 2005, and the first one will be delivered in 2024 or 2025, some 14 or 15 years later—a very long time. The Type 31e does not as yet have any contractors, designers or orders, yet we are saying that it will take four years. I hope that the Minister is right—that would be wonderful—but I am concerned. Is it not time to push the Type 26 programme to get these ships delivered more quickly, and to order the remaining five of them, in order to get a steady drum beat of orders that will drive the cost of the Type 26 ships down? A number of people in the Treasury would like to see that happen.

Earl Howe Portrait Earl Howe
- Hansard - - - Excerpts

My Lords, the Type 26 programme is proceeding at pace, on time and on budget so far. The point that the noble Lord makes, about ordering all Type 26 ships in one go, might not be the right way to get value for money. If we had done that in the first instance, it is arguable that we would have overpriced the contract, because Australia has since come in with a firm order for Type 26 frigates. We are sure that this will play very favourably into the price of our next order for the Type 26.