Parliamentary Buildings (Restoration and Renewal) Bill Debate

Full Debate: Read Full Debate
Department: Leader of the House
Baroness Evans of Bowes Park Portrait The Lord Privy Seal (Baroness Evans of Bowes Park) (Con)
- Hansard - - - Excerpts

My Lords, I shall wait while noble Lords depart.

I am delighted to open the Second Reading debate on the Parliamentary Buildings (Restoration and Renewal) Bill. The Bill has been a long time coming and builds on the work of many in this House and the other place. I pay tribute to my predecessor, my noble friend Lady Stowell of Beeston, to the noble Baroness, Lady Smith of Basildon, and to the noble and learned Lord, Lord Wallace of Tankerness, the noble Lord, Lord Laming, my noble friend Lord Deighton and the noble Lord, Lord Carter of Coles, for the work they did on the Joint Committee on the Palace of Westminster, which was vital in paving the way for the Bill. I also thank my noble friends Lady Byford and Lord Brabazon of Tara, the noble Lords, Lord Blunkett and Lord Stunell, and the noble Baronesses, Lady Warwick of Undercliffe and Lady Prashar, for their work on the joint pre-legislative Select Committee that looked at the Bill. All their recommendations were carefully considered and led to a number of changes.

The Bill gives effect to the resolutions passed in Parliament last year putting in place a governance structure that will ensure that the long-term programme of R&R work can be undertaken. It establishes the statutory bodies that will be responsible for addressing the risks and dangers that currently affect this building, as well as its restoration and renewal.

Noble Lords will be well aware of the horrific fire that swept through Notre Dame only a few months ago, which served as a stark reminder of the risks to this historic and iconic building. Here, we have a team of 24 staff employed to carry out fire patrols around the clock, and we have put in place complex fire mitigation measures. Other issues that have affected the Palace in recent months include falling masonry, water leaks, floods, sewage leaks, lighting and power outages, and toilet closures. Whatever individual position Members may take on particular elements of this programme, I think your Lordships would all agree that significant maintenance work cannot be delayed any longer. We must ensure that the Palace of Westminster is restored and protected, so that it may continue to serve as the home of the UK Parliament for generations to come.

In 2012, both commissions considered the option of relocating Parliament outside the Palace of Westminster in a new purpose-built building, they but decided against such a proposal. The Joint Committee on the Palace of Westminster also considered temporarily relocating Parliament outside London during the works, but concluded that it carried an unacceptable burden of cost and inconvenience.

Lord Foulkes of Cumnock Portrait Lord Foulkes of Cumnock (Lab Co-op)
- Hansard - -

Will the Lord Privy Seal confirm that no costings were carried out or estimates taken of the proposal to build a new Parliament elsewhere?

Baroness Evans of Bowes Park Portrait Baroness Evans of Bowes Park
- Hansard - - - Excerpts

Obviously, a number of reports have looked into this issue, which have considered a range of issues. Today, we are putting into legislative effect the Motions that were passed by this House and the other place, which affirmed that the guarantee that both Houses would return to their historic Chambers as soon as possible should be incorporated in primary legislation. That is what we are doing as part of the Bill.

This is an important, technical Bill which facilitates the next crucial stage of the R&R programme. It consists of 15 clauses and 4 schedules. It establishes the parliamentary works sponsor body, which will have overall responsibility for the restoration and renewal of the Palace of Westminster and will act as the client on behalf of both Houses. It also provides for the formation of a delivery authority as a company limited by guarantee. The delivery authority will formulate proposals in relation to the restoration works and ensure their operational delivery. The sponsor body already exists in shadow form, and I thank those Peers who sit on its board: my noble friend Lord Deighton, the noble Lords, Lord Carter of Coles and Lord Geidt, and the noble Baroness, Lady Scott of Needham Market.

Drawing on best practice from the successful delivery of the London 2012 Olympics, the bodies will be independent and able to operate effectively in the commercial sphere, bringing the expertise and capability needed for a project of this scale.

--- Later in debate ---
Lord Haselhurst Portrait Lord Haselhurst (Con)
- Hansard - - - Excerpts

My Lords, my noble friend the Leader of the House began by saying that this was a technical Bill, and strictly it is. It narrows down to setting up the mechanism that we need to go forward with restoration and renewal. However, it is a Second Reading debate and I notice that our colleagues in the other place dilated around the Bill’s central proposition—which is also happening here in your Lordships’ House.

I profoundly disagree with the noble Lord, Lord Adonis, who said that we appear to be in a hurry. That is certainly not the impression of someone who has spent time in the House of Commons dealing with some of the arguments the noble Lord has deployed today and which I thought had been well and truly sorted out. The idea that we should start looking backwards when there is every urgent need to look forward I do not find very helpful.

Lord Foulkes of Cumnock Portrait Lord Foulkes of Cumnock
- Hansard - -

I wonder whether the noble Lord will give way.

Lord Haselhurst Portrait Lord Haselhurst
- Hansard - - - Excerpts

If the noble Lord will forgive me, we have very limited time.

Lord Foulkes of Cumnock Portrait Lord Foulkes of Cumnock
- Hansard - -

No, we do not.

Lord Haselhurst Portrait Lord Haselhurst
- Hansard - - - Excerpts

And we do not have add-on time, as in the other place.

It is true that we are, as a clientele, a difficult body of people to satisfy, because there are many lively ideas as to how we should proceed. If there are concerns, it is right that they should be examined. The extraordinary thing is that the public seem more satisfied than the two Houses of Parliament about what is intended and that, given their affection for this place and understanding of it as an icon of parliamentary representative democracy which the world also admires, they recognise that it needs to be repaired and be the continuing Parliament of this country. Their expectation is clearly that we will do the work and return here, and any other expectations are mistaken.

However, the renewal of the building might prove trickier, as the noble Baroness, Lady Andrews, hinted. After all, projecting perhaps 15 years ahead, we do not know how many Members there will be in each House—their number might have been drastically reduced. The methods of working we will undertake as elected Members of Parliament and as Members of this House may alter considerably, so how can we be absolutely certain that we are equipping the building, both in electric power—whatever power we choose—and the form of office space we need? Will our needs be the same as they are now? Of course, many of us believe that we are still seriously behind on the IT front anyway, despite the best efforts of the Parliamentary Digital Service.

Then there is the question of the new space to be created. I have not seen any full account of what might become available, beyond the fact that some space will be released underground. There will also be the possibility of glazing over some of the courtyards, as has been done in other Parliaments, creating a lot of attractive space to assist Members meeting their constituents—using not necessarily the Royal Gallery but rather more tailor-made accommodation. As for what should be the priorities, I fully agree with the noble Lord, Lord Blunkett, about access, but it is not just about access for the disabled, however important that is, but access for all visitors to this place. At the moment, they are kept outside, in spartan conditions. We encourage them, by the sensible use of public money, to come from all parts of the United Kingdom to visit this Parliament and we put them in a queue, whether it is hot, cold, wet or whatever, with no protection. This is ludicrous.

The other side of that coin is that because we have been spending so much effort on trying to keep unwanted people out of the place, when we actually need to get people out in an emergency, it is very difficult indeed. Anyone who has taken part in the fire drills we have had must scratch their heads in wonderment as to what we are learning from them. It seems to me that any Member in any part of this building has to know, when entertaining visitors in particular, the quickest way to safety. That is by no means clear and our efforts have not helped to make people fully conscious of what they should be doing.

There is a real issue about passage between the two Houses in their new locations. I would like to think that careful research will be done on the possibility of tunnels connecting them. Anyone who knows Capitol Hill in Washington knows that it is possible to move from one building to another in entirely secure circumstances. Two Underground lines go through Parliament Square, so I do not pretend it is easy, but this is a matter of security. I do not believe that the risk of being attacked will lessen in future years; therefore, we should think of this as an opportunity to see whether we can provide totally safe passage. I would also go on to look at Parliament Square. We are unfortunately placed in that respect, but I would like to push the perimeter out. It has been talked about as being too difficult and so on, but what comes first? The safety of this building and the safety of the people who work in it and visit it, quite apart from that of Members themselves. It is a target and we must do everything we can to frustrate any evil directed at it.

I have one or two specific points. It was asked in the other place whether there was any possibility, in the timescale we are contemplating, that the Elizabeth Tower, when the work there is completed, could be reopened to the public. I do not know whether that is practical, but I can see the point of considering it and I would like a definitive answer. Of course, it is very difficult to get people up there in the first place; nevertheless, it will be a further attraction in the future. More important is Westminster Hall. I would like to know, when all the present work has been done in Westminster Hall, whether it can be effectively sealed off for the period of the decant, so that we can have the opportunity to bring people in at St Stephen’s Entrance and take them through on a conducted tour, telling the story of Parliament. There would also be the opportunity of the gift shop and the cafeteria, but also, more seriously, of having Westminster Hall as a place of debate, as used by the other place. I just think we should be sure whether that is possible.

I want to say a word about the Archives. I suspect I am one of the few people who has visited the Archives. It was never necessary to consult them in all my years as an elected Member of Parliament, yet we keep them in the most appalling conditions in the Victoria Tower. I would have them out of there to as far away as the noble Lord, Lord Adonis, might want to take them to counterbalance things. They would be another point of interest about Parliament. That would then release a great deal of space for your Lordships’ House.

If there are any doubters left—and I hope that the noble Lord, Lord Adonis, is not really one of them—Mr Barry’s War has been commended as essential reading. I absolutely agree. Putting a good structure in place to move forward is now imperative.

--- Later in debate ---
Lord Foulkes of Cumnock Portrait Lord Foulkes of Cumnock
- Hansard - -

My Lords, this has been a very interesting debate so far, with a really fascinating speech from the noble Earl, Lord Devon. We learned a lot from it that we did not know about this building. There was also a gentle introduction from my noble friend Lord Carter of Coles, whom I find it difficult to disagree with but I am going to have to do so on this occasion. However, this debate does not represent a consensus as I understand it. Only my noble friend Lord Adonis has expressed some dissent, as I am about to do.

Going around listening to colleagues, I think that more and more people are getting more and more worried about the course we have set out on. Most of the speakers have been involved in some way—on the committees or the boards—in moving this forward, and they know they are moving in this direction, but so did the captain of the “Titanic”. He knew where he was going but he did not see the iceberg ahead. Sometimes we need to step back and think about that.

My really strong objection is that no proper consideration has been given to the alternative of a purpose-built Parliament, preferably in some other part of the United Kingdom. As my noble friend Lord Adonis said, that would provide a great impetus to places such as York, Birmingham or some other part of the United Kingdom. I am surprised at my noble friend Lord Blunkett, the noble Lord, Lord Newby, and others who normally advocate a move in that direction. A purpose-built Parliament would also be better for security, which could be built in from the start, and it would be better for Members. We could have offices for Members so that we could work properly instead of being in little groups packed into this building.

Lord Blunkett Portrait Lord Blunkett
- Hansard - - - Excerpts

I do not normally do this but I cannot resist just pointing out that, in the early part of his speech, my noble friend Lord Adonis said that he would advise any new Member that it was quite unlikely that anything revolutionary would ever happen here. I just point to my noble friend that the idea of moving the whole shebang is an exercise in total futility.

Lord Foulkes of Cumnock Portrait Lord Foulkes of Cumnock
- Hansard - -

You can say that but you cannot prove it. It is not an exercise in futility. It has happened in other countries and has worked well, so you cannot argue that it is futile. What is being proposed is an exercise in total futility. After all, this House will not have the present composition or the current function for ever—at least, I hope that it does not; I hope that it will change.

Even if we do not move to Birmingham, York or somewhere else, we could still have a purpose-built Parliament in London. It would not help in the redistribution of wealth and power in the countries concerned but at least it would provide a purpose-built building fit for the 21st century. The noble and learned Lord, Lord Wallace, spoke about this building providing a Parliament fit for the 21st century, but it does not matter what you do to this building, it will never do that. It will never provide proper disabled access or have proper security.

What are we going to have? I went to a briefing about this with the lady who chairs the shadow committee. We were given an indication that we are going to be decanted for 10 years, moving out in 2025 and moving back in in 2035, so for 10 years we will try to operate as we do at the moment. What will happen to Joint Committees of the two Houses when we are in the QEII centre and the House of Commons is in Richmond House? What will happen to the CPA, the IPU and the all-party groups? What will happen to the informal contacts, which are increasingly essential to the work of this Parliament? What about security when people go between those two buildings? That will not be very easy. I asked about parking but the committee did not know. At the moment there is parking for Members of both Houses but there will not be during those 10 years. I come in on the No. 3 bus, so I am not worried about it, but a lot of my noble friends do not. They drive in and need to find somewhere to park, but that will not be possible. What is going to happen to the Library during the decant period? There is no answer to that. This is an outrageous suggestion. We really have ended up with a dog’s breakfast.

One argument—it was repeated today by the Leader of the House—is that we should look at what happened to Notre Dame. However, the fires at Notre Dame and Windsor happened during restoration and renewal, and the fires at the Glasgow School of Art also happened during restoration and renewal—twice. When people are working in this place we can detect whether there is a danger of fire and we are protected, but fires seem to happen during restoration and renewal, so do not imagine that this will be a solution to that risk. If we are not going to have any new build, why do we have to have this long and cumbersome decant that will cause so many problems? If we are not going to have a new build immediately, let us at least try to make the best of it. Let us make do and mend in this building. It can be done. We could move back to long Summer Recesses. The work could be done in those periods bit by bit. There is no impossibility.

I missed out something earlier when I was talking about building a new Parliament. I do not suggest that in the long term we abandon this building. It could be used more productively, and the work could be done without panic or rush because we wanted to get back into it: it could become a very good museum, a centre for the study of democracy. As my noble friend Lord Maxton has suggested, we could have reconstructions of famous events in political history in each Chamber for people to come in and see. We could have a whole educational opportunity for young people, who we have been talking about, to come in and look at history. As the noble Earl, Lord Devon, said, there is much more to this place than just the Victorian history that Pugin and Barry left us. There is much more to the whole building. I am not sure that as far as Scots are concerned Westminster Hall is the best place to remember our history, but it would still be a very good centre for people to come to.

I urge the people concerned in all seriousness to look at this again. We are heading towards disaster. I am putting my mark here: I predict that whoever becomes Prime Minister, whether Boris Johnson or Jeremy Corbyn—the latter is possible, although whether it is desirable is another matter—when faced with this proposal for billions of pounds to be spent on Parliament when there are so many other priorities, will not approve it. The whole project from now on is doomed.

--- Later in debate ---
Lord Foulkes of Cumnock Portrait Lord Foulkes of Cumnock
- Hansard - -

Why does the noble Lord think that the Treasury will agree to Parliament making this decision without its approval—I see the Leader of the House is not listening—given that I keep getting told that a much more modest proposal that I have been suggesting for a number of years is subject to approval by the Treasury and must be within a particular envelope? Either this Parliament makes decisions about expenditure or it does not. The noble Lord is saying that it will make decisions about billions of pounds, when it cannot make decisions about millions.

Lord Stunell Portrait Lord Stunell
- Hansard - - - Excerpts

The noble Lord exactly anticipates the point I am coming to. If this goes ahead unamended, it is a recipe for the hidden hand to cause delay and wasted effort. Those were the points I was about to make.

The Joint Committee recommended that a Treasury Minister sit on the sponsor body, which will sign off the brief for the delivery authority. That is when the Treasury input is needed, not after a year’s work of design and procurement has been done, and perhaps wasted, when the estimates commission consults the Treasury, in accordance with paragraphs 3, 5 and 8, and is obliged to reject what comes to it. I say “obliged”, because if you must “have regard” to something, that leaves very little room to ignore the advice you receive.

There is a weakness in accountability here, but not a weakness of the designers, contractors, delivery authority or sponsor board. Those accountabilities are in the main clear and transparent, and very welcome for that. The weakness is in the accountability of the Government and the lack of any transparency in their input. I describe it as their “input” into the process but it is much more likely to be their extraction from it, because I do not believe that the Treasury would urge anyone to spend the money faster. However, their participation in the process is not transparent, and that weakness will lead to delay, waste and extra costs. How much better and simpler would it be to have the Treasury at the front end rather than the back end of the process?

It may be said that there is no problem because the Government will accept the point that the noble Lord, Lord Foulkes, is so dubious about them accepting. However, we know that transparency influences the progress of the project, and that endless delays and costs involve money. When there was no transparency, we did not know, for instance, why it was taking so long for previous stages of this process to reach the House and for decisions to be taken. When those delays cannot be attributed and chased, they accumulate. I can well understand that the Government have no wish at all to be fingered by this problem; equally, we have to understand its cost. With costs running at over £500 million a year, I can well see that Ministers will be hesitant. That is five schools-worth a year, and the temptation will be to stop, pull back and slow down. That is bad and expensive news at any stage of a big project, but it is absolutely destructive when it is in full flow. Let us get that interference at the front level, and minimise the delay, the wasted design time, the costs and the aborted procurement. I hope we can come back to that key issue in Committee.

I concur with practically every speaker in this debate in saying that this is a good, sound Bill. It needs to go ahead, and quickly, and we need to make sure that any flaws regarding accountability that may be built into it are dealt with before it leaves your Lordships’ House.

--- Later in debate ---
Earl Howe Portrait The Minister of State, Ministry of Defence (Earl Howe) (Con)
- Hansard - - - Excerpts

My Lords, I thank all noble Lords who contributed to this high-quality and thoughtful debate. As my noble friend the Leader remarked, the Bill has been a long time coming—too long, as I suspect we all agree. Although the Bill is with us at last, many uncertainties remain: how the restoration and renewal works will be undertaken in practice; how they will balance and reconcile the different imperatives that we all care about; and what the works will mean for Members of both Houses and the continued functioning of Parliament. These questions admit different opinions depending on your perspective. Although I will shortly respond to the issues of this kind raised by noble Lords, they are essentially debates for another day.

Meanwhile, we should be in no doubt as to the importance of what the Bill is here to do. It puts in place a governance structure to ensure that a professional programme of work can be undertaken. The urgency of this task cannot be underestimated. I respectfully but firmly disagree with the noble Lord, Lord Foulkes, that this is a case of “make do and mend”. Earlier, we heard about the state of disrepair that this place now finds itself in, with falling masonry, mechanical and electrical faults, asbestos and other issues seriously affecting the day-to-day operation and safety of the building. Anyone who has toured the basement can see that we face a major restoration programme.

As has been said many times, this is a parliamentary project. The powerful contributions to the debate testify to our strong feelings on the issues before us; they certainly underscore how incredibly important it is that we get on with the job. The bottom line is that very significant work must be done to the fabric of this place. We must take the opportunity that the Bill provides to ensure that, pace the noble Lord, Lord Adonis, the Palace of Westminster can remain the seat of the United Kingdom’s Parliament for generations to come.

Let me address some specific points. First, on the amendments passed in the Commons and the others to be tabled in Committee, we heard earlier today from my noble friend the Leader about the Bill’s smooth passage in the other place as a result of the collaborative working between government and parliamentarians. The Bill reflects that, as cannot be said too often, this is a parliamentary project. The Government have listened to, and taken on board, the views and concerns of Members. That is why the amendments on the need for educational facilities, and on the transfer of external members of the shadow sponsor body to the sponsor body, were assisted and supported by the Government, and passed on Report in the Commons.

As it was the clear will of the House of the Commons, the Government also agreed at Commons Report stage to assist the tabling of two amendments in the House of Lords, one relating to heritage and the other to reporting. As a grade 1 listed building and part of a UNESCO world heritage site, the outstanding architectural heritage of the Palace would always have been a consideration for the sponsor body. We therefore did not deem a reference to heritage in the Bill necessary. However, we have heard from a number of noble Lords —notably, the noble Lord, Lord Carter, the noble Earl, Lord Devon, and my noble friends Lord Inglewood and Lord Lingfield—that the Palace’s heritage and its high-quality conservation are of central concern. As the noble Baroness, Lady Andrews, rightly emphasised, parliamentarians and heritage bodies have made their views on the matter clear, and we have recognised the importance of those concerns. An amendment will therefore be tabled in Committee that I hope will command support.

The Government also agreed to assist a robust amendment on the reporting of contracts and the size and locations of the companies concerned. There is already a requirement for the sponsor body to report on the carrying out and progress of the parliamentary buildings work. However, we will also require reporting on the size and location of the companies contracted to.

Report stage in the House of Commons also resulted in a call for amendments on the corporate social responsibility of contracted companies and for the economic benefits of the works to be spread across the UK. The Government opposed these amendments, but since they were passed in the House of Commons we recognise that their spirit should be reflected in the Bill. We will therefore work with parliamentary counsel and Members to ensure the amendments are worded appropriately.

An amendment to spread the economic benefits of the works across the nations and regions of the UK was passed in the Commons, as I mentioned. The noble and learned Lord, Lord Hope, referred to this. The Government fully support the principle that the benefits should be shared across the UK, but we identified some concerns with the wording of this amendment in relation to procurement law. We will therefore work with parliamentary counsel to ensure the amendment is appropriately worded, as we will with the amendment on corporate social responsibility. As with all the amendments I have spoken about, we will ensure that the spirit of the amendment approved by the other place is retained. The role of government is to assist Parliament in the passage of this Bill through both Houses. The project itself is for Parliament.

I turn next to specific questions asked about the provisions of the Bill. My noble friend Lady Stowell asked about responsibility for other estates projects on the Parliamentary Estate. At present, the R&R programme is responsible only for refurbishing the Palace and for the QEII Centre as a decent location for the Lords. It is expected that in due course, following designation by both House commissions, the R&R programme will also include the Northern Estate programme. Provision to allow for this is made in Clause 1 of the Bill. At the moment, no other current parliamentary estates programmes are expected to come under R&R. Again, however, Clause 1 of the Bill allows this to happen if both commissions, the sponsor body and the delivery authority agree.

The noble and learned Lord, Lord Hope, asked about the mechanisms for dispute resolution between any of the proposed bodies. It will be up to the commissions of both Houses to agree workable arrangements for the resolution of otherwise intractable disagreements. Work on this will be taken forward soon, and its importance is clear. I add only that the programme delivery agreement will cover how disputes between the sponsor body and delivery authority during the works are to be resolved.

The noble Lord, Lord Blunkett, my noble friend Lady Byford, the noble Baroness, Lady Smith, and others emphasised the need for proper disabled access to and within the building. Clause 2(4) states:

“In exercising its functions, the Sponsor Body must have regard to … the need to ensure that … any place in which either House of Parliament is located while the Parliamentary building works are carried out, and … the Palace of Westminster (after completion of those works), are accessible to people with disabilities”.


I agree that it is important that the sponsor body and delivery authority appreciate that we expect disabled access to go beyond visitors, staff, Peers and MPs entering the Parliamentary Estate. It is worth mentioning that the sponsor body and delivery authority will need to comply with any legal obligation, such as the Equality Act 2010, when considering the provision of disabled access. I am pleased that the shadow sponsor body, to whose assiduous work I pay tribute, has specified that improving access forms part of its vision and strategic themes for the works. In fact, it has specified that the restored Palace will provide exemplary standards of access for everyone.

The noble Lord, Lord Blunkett, my noble friends Lady Byford and Lord Bethell and others stressed the importance of educational outreach facilities. We all recognise the will of the other place in amending Clause 2(4)(g) in the Bill so that the provision of educational and other facilities in the Palace after completion of the works was a “need” rather than a desirability. We have the opportunity through R&R to create a legacy in educational facilities. As the noble Lord, Lord Newby, pointed out, better educational facilities will allow schoolchildren who visit the Palace to have a more interactive engagement with Parliament and democracy. This could be achieved by using the new Chamber in Richmond House as an educational facility. I was taken with the proposal made by my noble friend Lord Bethell that we should have ambitious targets for increasing the number of visitors to the Palace. Of course, it is for Parliament—not the sponsor body—to promote Parliament through outreach. Parliament has a number of initiatives in this area, including visits to schools, and there is an opportunity to think about those activities also.

This leads into the whole question raised by the noble Lord, Lord Blunkett, about renewal and how we define it. I am sure we each have different views on what renewal means. That is why it is so important that parliamentarians have the opportunity to engage with R&R and the scope of the work. I completely agree with noble Lords who have argued that the programme provides a number of opportunities; for example, improvements to the Palace should enable an increase in the number of visitors and an even better experience for visitors. I am sure we also all want to see improvements to the accessibility of the Palace as part of the work. That includes not just lifts and ramps but acoustics, the increased use of technology and, as I have just mentioned, better educational facilities. I would also like to see proper consideration be given to how space is used and whether the sponsor body can come up with innovative solutions to increase the available space, without impacting on the heritage of the Palace.

The noble Lord, Lord Berkeley, referred to the importance of fire safety. I agree that this is of paramount importance, and indeed it is one of the strongest arguments for getting on with R&R. As he will know, until the Palace is handed over to the sponsor body, the House authorities are responsible for fire safety. I am aware that the noble Lord raised his concerns in the Chamber on 25 April in the aftermath of the Notre Dame fire. At that time, the chair of the Services Committee, the noble Lord, Lord Laming, went into some detail to explain what precautions the House authorities have put in place to protect the roofs. The noble Lord will no doubt remember what the noble Lord, Lord Laming, said on that occasion.

My noble friend Lord Haselhurst advocated for better access to Westminster Hall and the Elizabeth Tower during the works. Analysis in 2017 found that any continued use of Westminster Hall or its surrounding areas by Members and/or the public would be highly disruptive and costly for no additional quantifiable benefit. The costs would be connected to maintaining a secure perimeter in close proximity to construction works and the additional cost to construction from managing a complex, partially occupied site. However, the feasibility study conducted by the R&R programme in 2017 found that the additional cost of maintaining access to the Elizabeth Tower during the R&R programme for Members’ pre-booked tour groups would be minimal, since the site boundary could be established to the south of the tower, allowing access through Portcullis House. However, that remains a matter for the sponsor body and Parliament.

The noble Lord, Lord Newby, advocated for the opportunity for SMEs to be part of the restoration and renewal works. Smaller businesses will have the opportunity to bid to be part of the works. As the noble Lord will know, that is already happening with the encaustic tile conservation project and work on the Elizabeth Tower. Again, it is ultimately a matter for the sponsor body to determine how best to engage SMEs in the forthcoming work, and we have encouraged the programme to give thought to that.

The noble and learned Lord, Lord Wallace of Tankerness, spoke about the opportunity to promote apprenticeships, an issue also cogently argued by my noble friend Lord Lingfield. Our response to the pre-legislative Joint Committee noted that we very much encourage the sponsor body to consider how it can share the employment and apprenticeship benefits of R&R across the UK. The R&R programme has taken steps to learn from other programmes about how to plan for successful apprenticeship and skills development programmes, and the shadow sponsor body has committed for the programme to provide for the development of national construction and craft skills.

Let me turn briefly, if I may, to the decant, which I completely understand is of huge importance to many noble Lords. The noble Lord, Lord Berkeley, asked about the choice of the QEII conference centre as the location for the temporary decant of the House of Lords. The QEII Centre is the preferred location for the Lords decant, in line with the recommendation by the Joint Committee on the Palace of Westminster in 2016. That recommendation was agreed by the House of Lords Commission in September 2018, subject to further feasibility work being undertaken.

Underlying that decision was a lot of preparatory effort. The restoration and renewal programme team carried out work with the government property unit to assess the suitability of sites on the government estate. One option involved use of the courtyard of the Foreign and Commonwealth Office in King Charles Street. However, it was considered to be a suboptimal solution that would require further decant accommodation to be delivered over multiple locations and had space constraints around the Chamber.

The QEII Centre has a number of advantages as a decant option for the House of Lords. It would provide the best accommodation solution because it would reduce the need for accommodation across multiple sites. It is not a listed building and can be adapted to meet security requirements. As a government-owned space, it has fewer risks when compared to a commercially owned property. Last but not least, it presents opportunities for greater accessibility than we enjoy currently.

I acknowledge that the noble Lords, Lord Adonis and Lord Foulkes, and some other noble Lords, strongly believe that Parliament should be permanently relocated from Westminster and that we should, in consequence, turn the Palace into a museum. The first thing to do is remind noble Lords that the Motion passed by this House early last year was clear that both Houses will return to their historic Chambers as soon as possible after the restoration and renewal of the Palace. In accordance with the will of both Houses, that guarantee is incorporated into the Bill. By way of background, in 2012, Parliament commissioned a pre-feasibility study into the preliminary business case for R&R. The study considered that whole question and concluded that because,

“the geographical proximity of Parliament to Government is of significance … substantial additional costs would be incurred”.

Lord Foulkes of Cumnock Portrait Lord Foulkes of Cumnock
- Hansard - -

The noble Earl has been very helpful but he moved over the issue of the decant before I was able to ask him a question. I asked earlier about the position of the Library and of car parking during those 10 years, and he has not answered either question.

Earl Howe Portrait Earl Howe
- Hansard - - - Excerpts

All I can say is that those issues will be considered as part of the plan. I do not have a ready-made answer for the noble Lord on either question, but I would be the first to concede that they are of importance.

Lord Foulkes of Cumnock Portrait Lord Foulkes of Cumnock
- Hansard - -

When I went to the briefing meeting, the lady in charge of the shadow sponsor body did not have an answer either, and nor did she have an answer on security. There are a lot of unanswered questions.

Perhaps the noble Earl can help me with another question about relocation elsewhere. Earlier, the Leader of the House admitted that there was no costing of that alternative. Why was there no costing, at an early stage, of what is an obvious alternative proposal?

Earl Howe Portrait Earl Howe
- Hansard - - - Excerpts

The matters raised by the noble Lord will be part of the outline business case, so it is impossible to be specific. However, on costing, in October 2012, the House of Commons Commission, and at that time the House Committee in the Lords, considered the pre-feasibility study and decided:

“The report is a useful first analysis of the issues. However, the Commission has ruled out the option of constructing a brand new building away from Westminster and no further analysis will be undertaken of this option”.

Lord Foulkes of Cumnock Portrait Lord Foulkes of Cumnock
- Hansard - -

Why did it rule it out? I should have asked earlier. My noble friend Lady Smith chastised me earlier for being late to the issue. Why was it not considered? Why was it ruled out at such an early stage, without any costing, as the alternative?