Commons ChamberWith the leave of the House, I will make a few remarks in response to the debate.
The fundamental point of the debate is to allow petitions to be submitted to the hybrid Bill Committee, so, while many of the points are perfectly reasonable ones to make, they should be directed to the Committee for it to consider and then, if necessary, make recommendations on. That said, the hon. Member for Nottingham South (Lilian Greenwood) made some points I need to address, particularly about how Euston station can be developed. We are all in awe of the development of King’s Cross and St Pancras stations and the regeneration of the surrounding area. People used to go to King’s Cross for all the wrong reasons; now they go for the right reasons. It is a great place to be.
We need such regeneration around Euston, although I recognise the points about there not being quite so much spare land around there. It is important that we work with Network Rail and Transport for London to co-ordinate the approach. Our Euston proposal is fully compatible with the redevelopment of the remaining Network Rail station and has been developed with Network Rail and TFL. The improvements to the underground station at Euston will be transformational. When the new Victoria development opens, we will get a taste of how a new state-of-the-art underground station can help commuters and particularly of how the tidal flows of people need not conflict in the way they often do in other areas. On project delivery, Sir Peter Hendy and his team are looking at how Network Rail can work more effectively.
The hon. Lady mentioned excavated material being removed by rail. Extended construction at Euston station will allow more excavated material to be removed by rail, as there is capacity to do so. We will work to maximise what can be taken out by rail. The fewer trucks the better for noise and congestion and for the safety of pedestrians and cyclists. I am a London cyclist myself. We know that, sadly, heavy construction vehicles are often involved in accidents. Despite the prowess and training of drivers and the modification of vehicles, accidents still occasionally happen. I can also confirm that there are no changes to the compensation schemes. The scheme in urban areas, compared with country areas, recognises the character of those areas and the effect that construction and development can have, particularly on property prices and people.
The hon. Lady asked about the net cost of the changes. I can confirm that the net cost is zero. The overall cost of phase 1 remains £21.4 billion at second quarter 2011 prices. Any changes that add costs simply draw down the contingency not set aside for that purpose. We always knew we would need to draw down the contingency—for example, to meet the cost of the Chiltern tunnel extension, the cost of which was more than £40 million, at second quarter 2011 prices, excluding the contingency. I hope I have reassured the House that the project is deliverable within budget.
The hon. Lady also asked whether we would return to the House to provide clarity on phase 2 and legislative plans. I can confirm that the Government will outline the way forward for phase 2 before the end of the year, including confirmation of the plans for legislation.
The Minister says that the Government will announce the way forward. Is that the same as confirming the line of route?
On phase 1, the line of route is certainly becoming much closer to being confirmed, but on phase 2 there is obviously a lot more work to be done with local authorities and leaders of the great cities of the north, as we call them, to ensure that we get that right. Some criticism has been voiced today that we keep coming back with new changed proposals, but it is important that we react to the points that people make, as the Committee reacts to petitions, for example. We have reacted to ensure that we can deliver a state-of-the-art station at Euston and minimise the impact on local people during the construction phase.
My right hon. Friend the Member for Chesham and Amersham (Mrs Gillan) mentioned the supplementary environmental statement. Let me repeat that for Camden it will be available from tomorrow for consultation until 6 November, while the consultation period on the AP4 area will commence in mid-October—I cannot give an exact date—and will run for six weeks.
The hon. and learned Member for Holborn and St Pancras (Keir Starmer) talked about the phased approach and how that would certainly mean disruption for a longer period, but we need to consider disruption not only to the residents affected by vehicles, noise, dust and so forth, but to the commuters who use the station. Delivering the project in the way we have outlined today will mean having more capacity through that station. I am pleased to reassure Members that some of the coverage at the weekend about reductions in platform space is not correct. There will be an opportunity to make sure that we keep the passengers going through.
As I mentioned in an intervention, Old Oak Common will become one of this country’s most important stations—it will be as well known as King’s Cross, Victoria and Waterloo. Indeed, at least 30% of the passengers will alight there to get on to Crossrail and then to a number of locations around London. As for other areas where it might be quicker to go through Euston when the line is complete, passengers will be able to use Old Oak Common as a connection. To come to Westminster, for example, it will take only three minutes longer via Old Oak Common than it would be via Euston. Many people may get used to Crossrail and like to use the new facilities.
The hon. and learned Member for Holborn and St Pancras, and indeed the hon. Member for Hampstead and Kilburn (Tulip Siddiq), mentioned the provision of social housing. It is important, particularly in the more deprived areas of our capital, to have good social housing provision. We have already committed to replacing lost social housing at Euston. We have purchased the Netley development and we are funding the construction of more social housing in the area—all with the aim of ensuring that social tenants are required to move only once.
The hon. and learned Member for Holborn and St Pancras also asked why the whole station would not be ready by 2026. If we look at the project—phase 1 to Birmingham and phase 2, the Y section—we find that capacity will not be needed until later for additional trains coming from Leeds and Manchester, and many other trains will start their journey further north in Scotland.
I think I have covered a number of the points raised. The ability to divert into Crossrail will be maintained, as my hon. Friend the Member for Milton Keynes South (Iain Stewart) made clear. As for the environmental statement, there will be an ability to prioritise local needs. The hybrid Bill does not take powers for over-site development, which will all be subject to the normal local planning process, so it will need to conform to the local planning strategy. I am sure that there will be tremendous opportunities at Euston for other development in the area, which will capitalise on the new station.
Finally, I come to the Euston arch. I can tell Members that the Secretary of State is very keen to see the resurrection of the Euston arch. We think we know where the bits are. The Euston Arch Trust aims to re-form the arch, and it is for that trust to bring it forward through a local planning application. We have a location for the new Euston Square gardens for the arch to come forward. Personally, I wonder whether a holograph might be even better, but I can certainly confirm that the Secretary of State is very keen to see the arch resurrected.
(9 years, 5 months ago)
Commons ChamberI will take your direction, Mr Deputy Speaker, but there are undoubtedly issues to be tackled at Euston. Three times now the residents of Camden have been presented with different plans for Euston station, with all the uncertainty that brings. Their treatment has clearly been inadequate, and I urge the Minister to shed a little light on when we can expect those additional provisions—I hope that I am still in order, Mr Deputy Speaker.
Does the Minister agree that it is unacceptable that a number of my hon. Friends have not been informed of the fact that the additional provisions would affect their constituencies? I know from discussions with a number of Members that they have had no communication from HS2 Ltd, or indeed from the Department, and consequently have had only one day’s notice that the changes are being debated. I know that the changes are a cause of concern to a number of hon. Friends. That situation is unacceptable, so I hope that the Minister will take it up with officials. The situation must not be repeated when further additional provisions are brought before the House.
We are not debating the provisions; we are debating the fact that the Select Committee can receive petitions and consider the changes. We are not debating the provisions at this point.
I thank the Minister for his intervention, but this is clearly an opportunity for right hon. and hon. Members who wish to make comments on behalf of their constituents to do so. It is only right that people are aware of the provisions that are being introduced and debated in this House. They will question what the value of these exchanges is if we do not raise concerns on behalf of our constituents.
I seek an assurance from the Minister that, when the Committee has issued an instruction regarding a particular section of the route, it will be acted on accordingly. This is a matter of particular concern in the constituency of my right hon. Friend the Member for Birmingham, Hodge Hill (Liam Byrne). I would welcome a commitment that today’s additional provision does not represent an end to the question of land-take at the Washwood Heath site, and that a mutually agreed solution will still be sought with the site’s owners.
Residents face a plethora of compensation schemes, some of which have been withdrawn, while awareness of others appears to be low. As the HS2 residents commissioner has said:
“It is vital that those who are eligible for the Government’s property compensation and assistance schemes get clear information and know what they are entitled to.”
Will the Minister take steps to clarify what support is available to residents, including those who live outside the rural support zone? This applies particularly to the concerns raised by my hon. Friend the Member for Ealing Central and Acton (Dr Huq).
I absolutely understand that this scheme should neither confound some of our other rail plans on western access, nor confound plans for highways improvement. I am therefore more than happy to meet my right hon. and learned Friend to get my head around these issues in particular.
The motion introduces changes to address issues that have been raised. It will put these proposals under the scrutiny of the Committee, and I am sure the House will be delighted to approve it.
Before the Minister finishes, will he clarify when he expects to introduce the additional provisions relating to Euston and when the Government expect to confirm the line of route for phase 2?
We expect to bring forward provisions for Euston later this year. I am working actively with officials from HS2 to ensure that we are in a position to introduce a proposal that will address some of the problems, particularly the issues about continuing to use that station for the west coast main line at the same time as construction is taking place. I will certainly give the hon. Lady some more information on the other point she raises when appropriate.
I commend the motion to the House and I hope the House will approve it.
Question put and agreed to.
Ordered,
That it be a further Instruction to the Select Committee to which the High Speed Rail (London - West Midlands) Bill is committed–
(1) that the Select Committee have power to consider–
(a) amendments relating to the vertical and horizontal alignment of the proposed railway in the vicinity of the A38 and Trent and Mersey Canal in the parishes of Fradley and Streethay, King’s Bromley and Whittington in the County of Staffordshire;
(b) amendments conferring additional power to carry out works in the Borough of Slough and in the parish of Iver in the County of Buckinghamshire for the purpose of providing a new Heathrow Express depot in the Borough of Slough (to the north east of Langley railway station), in consequence of the displacement of the existing depot because of the exercise of powers conferred by the Bill;
(c) amendments conferring additional power to provide sidings for Crossrail services at Old Oak Common in the London Boroughs of Ealing and Hammersmith and Fulham that could be extended in the future to create a connection between the West Coast Main Line Railway and the Great Western Main Line;
(d) amendments to accommodate the requirements of landowners and occupiers in
i. the London Boroughs of Brent and Ealing;
ii. the parishes of Barton Hartshorn, Calvert Green, Chetwode, Great Missenden, Grendon Underwood, Little Missenden, Preston Bissett, The Lee and Twyford in the County of Buckinghamshire;
iii. the parishes of Godington and Mixbury in the County of Oxfordshire;
iv. the parishes of Aston-le-Walls, Boddington, Chipping Warden and Edgcote, Greatworth, Radstone, Thorpe Mandeville and Whitfield in the County of Northamptonshire;
v. the parishes of Burton Green, Coleshill, Curdworth, Kenilworth, Ladbroke, Lea Marston, Middleton, Offchurch, Southam, Stoneleigh, Stoneton, Wishaw and Moxhull and Wormleighton in the County of Warwickshire;
vi. the parishes of Armitage with Handsacre, Drayton Bassett, Hints with Canwell, King’s Bromley, Swinfen and Packington and Whittington in the County of Staffordshire;
vii. the parishes of Balsall, Berkswell, Chelmsley Wood and Hampton-in Arden in the Metropolitan Borough of Solihull; and
viii. the City of Birmingham;
(e) amendments to accommodate changes to the design of the works authorised by the Bill in:
i. the London Boroughs of Ealing, Hammersmith and Fulham and Hillingdon and the Royal Borough of Kensington & Chelsea;
ii. the District of Three Rivers in the County of Hertfordshire;
iii. the parishes of Chetwode, Denham, Ellesborough, Great Missenden, Grendon Underwood, Little Missenden, Preston Bissett, Quainton, Steeple Claydon, Stoke Mandeville, Turweston, Twyford and Wendover in the County of Buckinghamshire;
iv. the parishes of Godington and Mixbury in the County of Oxfordshire;
v. the parishes of Aston-le-Walls, Boddington, Greatworth, Marston St Lawrence, Radstone and Thorpe Mandeville in the County of Northamptonshire;
vi. the parishes of Coleshill, Curdworth, Kingsbury, Lea Marston, Middleton, Offchurch, Radbourne and Stoneleigh in the County of Warwickshire;
vii. the parishes of Colwich, Drayton Bassett, Fradley and Streethay, Hints with Canwell, King’s Bromley, Swinfen and Packington and Weeford in the County of Staffordshire;
viii. the parishes of Berkswell and Bickenhill in the Metropolitan Borough of Solihull;
ix. the City of Birmingham;
(f) amendments to the definition of “deposited statement” in clause 63(1) of the Bill to refer to supplementary environmental information provided in relation to matters which do not require an extension of the powers of the Bill to construct works or acquire land;
(g) amendments for purposes connected with any of the matters mentioned in subparagraphs (a) to (f);
(2) that any petition against amendments to the Bill which the Select Committee is empowered to make shall be referred to the Select Committee if–
(a) the petition is presented by being deposited in the Private Bill Office not later than the end of the period of four weeks beginning with the day on which the first newspaper notice of the amendments was published, and
(b) the petition is one in which the petitioners pray to be heard by themselves or through counsel or agents.
That these Orders be Standing Orders of the House.