Data Centres: Energy

(asked on 20th July 2026) - View Source

Question

To ask His Majesty's Government what assessment they have made of the impact of electricity network connection delays on the delivery of artificial intelligence data centre developments.


Answered by
 Portrait
Baroness Lloyd of Effra
Parliamentary Under-Secretary of State (Department for Digital, Culture, Media and Sport)
This question was answered on 3rd August 2026

The Government recognises that growth in AI and data centres is increasing electricity demand and that grid connection delays are a major barrier to new capacity in the UK.

To address this, the Government is reforming the connections process to better support strategically important demand, including data centres. Working with DESNZ, Ofgem and the National Energy System Operator, reforms will reduce delays, limit speculative applications and prioritise viable projects, helping unlock capacity faster while maintaining security of supply. Through the AI Energy Council, co-chaired by the Secretaries of State for DBIST and DESNZ, DBIST is exploring resilient, sustainable and scalable.