Question to the Department for Transport:
To ask the Secretary of State for Transport, further to the Answer of 1 September 2025 to Question 69372 on Midland Main Line: Electrification, what is her Department's estimate of the cost of completing electrification of the Midland Main Line to Nottingham and Sheffield.
The Department’s most recent estimate to electrify the Midland Main Line to Nottingham and Sheffield was c. £1.5 billion, however, before the decision to pause the programme was confirmed, work was being undertaken by Network Rail to update their cost estimate.
Since July, Network Rail have been making plans for their current activities in a way that enables work to be subsequently utilised. The design work that will be completed will enable a more robust and up to date cost estimate to be produced, as and when funding becomes available to complete electrification of the route.