To ask the Secretary of State for Defence, what his planned timetable is for his Department to complete a review into the Morpheus programme.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 20th May 2022

Delivery of the first element of the MORPHEUS project is late and the MOD is considering the optimum route to achieve delivery of the full MORPHEUS capability. The MOD will continue to meet all our operational requirements. MOD are actively considering how best to deliver on the Morpheus project including working with General Dynamics Mission Systems UK on potential strategies to mitigate delays to delivery. This will determine the revised Initial Operating Capability date. This work is being led by a dedicated Director Level Senior Responsible Officer.