To ask the Secretary of State for Transport, pursuant to the Answer of 18 June 2025 to Question 59834 on South West Main Line: Dawlish, if she will set out a timescale for when a decision on whether Stage Five of the rail resilience programme for Dawlish will receive funding will be reached.


Answered by
Lilian Greenwood Portrait
Lilian Greenwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 27th June 2025

We are currently working to determine which rail enhancement projects will be taken forward following the conclusion of the Spending Review on 11 June. More information will be made public shortly.