Question to the Ministry of Defence:
To ask the Secretary of State for Defence, what recent progress his Department has made on the Type 26 Global Combat Ship Programme.
The Ministry of Defence continues to work closely with BAE Systems (BAES) to ensure the Type 26 programme remains on track to meet all user requirements and deliver world-class Anti-Submarine Warfare (ASW) frigates to replace the Type 23.
Following the steel-cut ceremony for HMS Sheffield on 28 November 2024, five of the eight Type 26 frigates are now under construction on the Clyde. HMS Cardiff is structurally complete and has joined HMS Glasgow in the dry dock at Scotstoun for the outfitting phase. Unit and block assembly on HMS Belfast and HMS Birmingham continues.
HMS Glasgow is forecast to achieve Initial Operating Capability in 2028, with construction of all eight frigates expected to be complete by the mid-2030s.