Question to the Ministry of Defence:
To ask the Secretary of State for Defence, what his timeframe is for completing the construction of the PEGASUS facility.
The original and current approved costs and the current in-service dates for Project Mensa and Project Pegasus are as follows:
Project | Original Cost Approved in 2011 | Current Approved Cost | Approved In-service Date |
MENSA | £734 million | £1996 million | 2024 |
PEGASUS | £634 million | £634 million | Material Handling Store - 2025 Manufacture Capability – 2030 |