Question to the Department for Transport:
To ask the Secretary of State for Transport, whether she plans to provide support to local businesses potentially impacted by delays to the completion of M25 junction 10 works.
The project has been delayed due to a number of factors. Severe weather, with unexpected heavy rainfall since October 2023 caused poor ground conditions. This postponed planned winter work and required a redesign of embankments and drainage. Additionally, the discovery of unexpected underground utilities along the A3 have further complicated progress, leading to extended relocation and design adjustments. Works on the M25 at junction 10 are expected to complete by late summer 2025, helping to alleviate traffic queues. The scheme is due to complete in Spring 2026. National Highways is working with its supplier to assess the full impact of delays and to minimise costs. Given the project's scale and complexity, the final cost will only be determined upon completion.
In terms of the support available for local businesses, National Highways provides compensation as established in legislation across all its projects, ensuring appropriate use of taxpayers’ money. National Highways can only consider compensation in line with legislation, for example where it takes land during scheme delivery, but not for loss of earnings during temporary road works.