Type 26 Frigates: Procurement

(asked on 25th February 2025) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what the latest estimated IOC date is for the last of class of the Type 26 frigates for the Royal Navy.


Answered by
Maria Eagle Portrait
Maria Eagle
Minister of State (Ministry of Defence)
This question was answered on 4th March 2025

On current plans the construction of all eight Type 26 frigates is expected to be complete by the mid-2030s. HMS Glasgow's Initial Operating Capability date remains October 2028.