Early Warning Systems

(asked on 25th February 2025) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what his planned timetable is for when the Crowsnest airbone early warning system will achieve Full Operating Capability.


Answered by
Maria Eagle Portrait
Maria Eagle
Minister of State (Ministry of Defence)
This question was answered on 4th March 2025

The Royal Navy’s Merlin Mk2 Airborne Surveillance and Control helicopter, as delivered by the CROWSNEST programme, has been in service since March 2021. The Programme is in the final stages of delivery for Full Operating Capability - expected by 28 March 2025, which is within its approved date.