Question to the Ministry of Defence:
To ask the Secretary of State for Defence, what recent progress he has made on the E7 Wedgetail programme.
The Wedgetail programme has seen the first aircraft complete three test flights, be painted in the markings of 8 Squadron and continues with the installation of mission equipment at STS Aviation at Birmingham Airport, before entering the test and evaluation phase later this year. Aircraft two and three are progressing with integrating their modifications as planned.
The infrastructure programme at RAF Lossiemouth has delivered the combined Poseidon and Wedgetail engineering line facility, as well as 8 Squadron headquarters office accommodation, with the final elements of the technical facility expected to be handed over in March 2025.