Nuclear Submarines: Decommissioning

(asked on 19th December 2024) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, how much funding he has allocated to the submarine dismantling programme for each of the next five years.


Answered by
Maria Eagle Portrait
Maria Eagle
Minister of State (Ministry of Defence)
This question was answered on 13th January 2025

The Department does not release spending profiles for individual programmes. However, I can confirm the latest Whole Life Cost for the Submarine Dismantling Project, as published in the Department’s 2023 Government Major Projects Portfolio data, is £298 million. This figure includes costs associated with dismantling work in Rosyth and maintenance costs for decommissioned submarines in Devonport.