Question to the Ministry of Defence:
To ask the Secretary of State for Defence, whether his Department has imposed (a) financial penalties and (b) adjustments to contract terms with General Dynamics in relation to the delay of the MORPHEUS project within the Land Environment Tactical Communication and Information Systems programme.
The MORPHEUS Evolve to Open Transition Partner (EvO TP) contract with General Dynamics Missions Systems (UK) (GDMS(UK)), which was focused on evolving the proprietary Bowman system, was concluded in December 2023. Commercial confidentiality precludes providing the specific details of the arrangements made, however the Department can provide assurance that these arrangements have been verified by both HM Treasury and Cabinet Office as representing the best value for money approach for the taxpayer.