Question to the Ministry of Defence:
To ask the Secretary of State for Defence, pursuant to the Answer of 4 December 2024 to Question 16468 on LE TacCIS programme, what the cost is of the Morpheus communications programme as of 5 December 2024.
As of 5 December 2024, total expenditure for the MORPHEUS project is c£828 million.