Trident Submarines

(asked on 17th March 2023) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what estimate he has made of how much and what proportion of the £10 billion contingency provided by HM Treasury for the Dreadnought programme will have been spent by 31 December 2023.


Answered by
Alex Chalk Portrait
Alex Chalk
Lord Chancellor and Secretary of State for Justice
This question was answered on 22nd March 2023

Up to March 2023, the Ministry of Defence has drawn-down £2 billion, 20 per cent, of the HM Treasury-held Dreadnought contingency. Contingency drawdown for financial year 2023-24 has not yet been agreed.