Question to the Ministry of Defence:
To ask the Secretary of State for Defence, what the estimated minimum deployable capability date is for the Boxer (a) 120mm self-propelled mortar system and (b) 155mm self-propelled artillery system.
The Mechanised Infantry (BOXER) programme uses the terms Initial Operating Capability (IOC) and Full Operating Capability. The Armoured Mortar Vehicle is a project within this programme and therefore uses those terms. The Mobile Fires Platform project is a part of the Close Support Fires Programme, which uses the term Minimum Deployable Capability instead.
Whilst the Mechanised Infantry (BOXER) programme has an IOC, the definition of the IOC for the Armoured Mortar Vehicle project within the programme is yet to be confirmed. The Mobile Fires Platform project does not have a confirmed definition for Minimum Deployable Capability (MDC). Therefore, an estimated IOC or MDC for either variant cannot be projected at this time.