Southeastern Railway Timetable Changes Debate
Full Debate: Read Full DebateVicky Foxcroft
Main Page: Vicky Foxcroft (Labour - Lewisham North)Department Debates - View all Vicky Foxcroft's debates with the Department for Transport
(2 years ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
It is an absolute pleasure to serve under your chairpersonship for the first time, Ms Harris. I congratulate my hon. Friend the Member for Eltham (Clive Efford) on securing this important debate and on his speech. He has made many key points with which I wholeheartedly agree.
Like many colleagues, I have worked closely with local transport users during my time as an MP, and I am here today to share the concerns of constituents who have contacted me following the publication of the amended timetable. As we have heard from many Members, it is fair to say that there has been widespread anger with the Department for Transport for allowing Southeastern to press ahead with the changes without consulting its passengers.
Although I can appreciate the removal of the requirement during the pandemic so that operators could bring in changes more quickly, most Members would agree that we are now at a point at which passenger numbers have restabilised. In response to a written question from my hon. Friend the Member for Sheffield, Heeley (Louise Haigh), the Department stated:
“There will be less than 1% fewer typical weekday passenger services across the…network compared to the current timetable.”
Well, I can tell the Chamber that users of St Johns station in my constituency are expecting to lose 19 services per day thanks to the rerouting of the Hayes line’s trains to Charing Cross.
I have received representations from two very active local organisations: St John’s Society and Brookmill Road Conservation Area Society, as well as from individual constituents. St Johns has had its services reduced in recent years, and the walk to nearby stations—New Cross and Lewisham—is long and uphill for many, causing difficulties for disabled people and those with young children.
Lewisham in particular suffers, as has been mentioned by many colleagues, with overcrowding at peak times and a woefully inaccessible station. The situation will only get worse as further large residential developments are completed in Lewisham, as Members have referenced in relation to their own constituencies. When the remaining peak-time trains reach St Johns—the next stop on the line—they might be too full for passengers to be able to join them. There are environmental considerations, too, if people are forced to use their car when previously they would have opted to travel by train.
Similarly, users at Blackheath station in the constituency of my hon. Friend the Member for Lewisham East (Janet Daby), just over the border from my constituency, have been hit with the news that there will be no direct services to London Charing Cross during off-peak hours, and many peak trains will also be cut.
I will conclude my comments. While the overall number of services might not be significantly reduced, that 1% figure in no way reflects the impact that the changes will have on individual stations and communities.
My right hon. Friend makes a good point. This is the challenging balance for Government and train operators. The cloth has to be cut accordingly. If I look at my Southeastern service, I am now down to an hourly service, without the benefit of going up to Cannon Street but having to change at London Bridge, in the same way that Members are about to experience with their constituents.
I recognise the danger that, in order to grow the railway, it is necessary to demonstrate a positive experience. We do not want to get to a situation where the railway service looks like the bus service. At the same time, there has been time taken post pandemic to assess how passenger numbers have been performing and they have not performed with the level of uptick that we need to give us an indication that people will not change their work habits—they are not going to return to the office five days a week. That is why difficult decisions have had to be made, but my right hon. Friend makes a very good point and it will be taken into account.
On consultation, there has been a need to recast the Southeastern timetable for many years. The last recast was over a decade ago, when Southeastern’s highspeed services were introduced. Even before the pandemic, the timetable no longer matched demands and had inherent efficiency and structural performance issues. As has been pointed out, Southeastern has changed its timetable 15 times since March 2020. Coming out of the pandemic, the industry has had to continue to work at pace to provide rail timetables that meet the new travel patterns and carefully balance cost, capacity and performance.
Operators have had to move at speed to address changes in demand and deliver cost-efficient timetables. That means that traditional public consultation has not always been possible. It takes many months to design and consult on a timetable, and it would have been challenging for Southeastern to conduct a meaningful consultation without time to change the timetable based on the feedback it received. That ultimately means money spent on running an inefficient timetable for longer, costing the taxpayer money. Ministers at the time thought that this was unacceptable, and, as a result, agreed to allow operators to implement demand-led timetables through 2020 without consulting formally.
Going forward, fiscal pressures may mean that other relatively short-notice timetable changes need to happen. However, there are lessons to be learnt from this timetable change on engagement and information sharing with stakeholders, even if timescales are compressed. I say to all right hon. and hon. Members present that I will ensure that if changes need to be made there will be transparency and engagement with Members of Parliament and other stakeholders at the earliest opportunity. It may not be possible to do a full 16-week consultation, but I will ensure that the starting point is with Members in this place. That is what I would expect, and I give them that assurance.
While I am giving assurances, I was also asked by my hon. Friend the Member for Old Bexley and Sidcup (Mr French) for an assurance that there are no plans in place to close Albany Park station: there are no plans in place to close Albany Park station.
There has been quite a lot of talk about Lewisham station, which is in my constituency. I can assure the Minister that Lewisham station is absolutely rammed at times, and there have been humungous safety concerns around it and the rerouting of passengers. We have had many new developments going up in the area. In the spirit of the Minister wanting to do consultations, would he like to come and meet me and Lewisham station’s user group—who are very expert in the rail network and Lewisham station—to hear their views on what might happen as we proceed?
I have always enjoyed spending time with the hon. Member—if that does not damage her electoral chances—so I would be very happy to meet her and the user group. I will put out another offer at the end of my speech.
Since the publication of the timetable in September there has been a mixed reaction from stakeholders. Many are pleased by the delivery of long-held ambitions on their routes, but others, such as those on the Bexleyheath and Sidcup line, are concerned about the loss of direct services to either Cannon Street or Charing Cross stations at off-peak times. All passengers affected by losing direct services can change at London Bridge to access high-frequency services to either station at no extra cost, and without having to use the tube. I see the hon. Member for Eltham shaking his head—that is a change I do on a regular basis, and I know what it takes. I will explain why it is not the poor experience that some may think it to be.
London Bridge is a modern station that has been designed for high volumes of interchanging passengers. I understand that some Members have concerns about changing there, but I can assure them that, as someone who does the change often, the station is well designed for that purpose. We believe it is one of the best in the country. The station is well lit, is sheltered and has full CCTV coverage. Southeastern has completed an equalities impact assessment and has made further improvements, which include the increased provision of dedicated mobile assistance staff, on-site lift engineers to ensure that all platforms remain accessible and on-site paramedics for any emergencies.
I turn to some of the benefits that Members who are not here might receive from the timetable change.