To ask the Secretary of State for Transport if he will make a statement on the proposals from Buckinghamshire County Council requesting that all enabling work for HS2 in Buckinghamshire is paused until notice to proceed to the main works contractors has been approved.

John Bercow Portrait Mr Speaker
- Hansard - -

Order. I gently point out at this stage that the question is narrowly about Buckinghamshire; it is not the occasion for a general debate about HS2. I will consider the Minister’s reply in making a judgment about whether it has been broadened, but at this point it is narrow.

Nusrat Ghani Portrait The Parliamentary Under-Secretary of State for Transport (Ms Nusrat Ghani)
- Hansard - - - Excerpts

Completing HS2 is Government policy and is crucial to unlocking economic growth and improved productivity in the midlands and north. It is supported by Members on both sides of this House. I therefore have no intention of halting work on HS2 in Buckinghamshire or elsewhere. There are already 7,000 people and 2,000 businesses working to deliver the HS2 project, and early works are well under way. Once HS2 Ltd has reached agreement with its suppliers and the Government are satisfied about both affordability and value for money, we will make a full business case for phase 1. This will inform notice to proceed, which is the formal contractual process that enables each phase 1 supplier to move from design and development to construction. Notice to proceed is scheduled to take place later this year. The works that are now taking place are necessary to enable the construction of HS2 to move forward in accordance with the programme, following notice to proceed.

We are aiming for HS2 to be one of the most environmentally responsible infrastructure projects ever delivered in the UK, and managing its impact on the environment during construction is a high priority. HS2 will deliver a new green corridor made up of more than 650 hectares of new woodland, wetland and wildlife habitats alongside the line. More than 7 million new native trees and shrubs will be planted, to help blend the line into the landscape and leave a lasting legacy of high-quality green spaces all along the route. It will include more than 33 sq km of new and existing wildlife habitat—an increase of around 30%, compared with what is there now. Many of the early works that are now taking place on HS2 are activities aimed precisely at creating this environmental legacy. They are being done now to ensure that they become fully established as early as possible, alongside construction of the railway.

Cheryl Gillan Portrait Dame Cheryl Gillan
- Hansard - - - Excerpts

The notice to proceed for HS2 has again been delayed, I believe until December. In the meantime, enabling works continue to blight large parts of the county, and this error-ridden project is costing our local authorities more and more. The situation is critical, with the area of outstanding natural beauty suffering irreparable environmental damage from preparatory works, rather than the “legacy” the Minister just referred to, and the costs spiralling out of control, when this project could well be cancelled. Indeed, millions are being spent on consultants to try to reduce the costs, which will in all likelihood result in failure to deliver on environmental protections and promises.

Already hedgerows have been netted or removed, machinery has been brought in to remove mature oak trees, country road verges have been destroyed by HGVs, massive ugly earthworks have appeared at our prime tourist sites, construction worker camps are surrounded by prison-like barriers, and there is the horror of the depopulated areas where homeowners were forced to sell to HS2.

It is almost impossible to hold this monster to account. Written questions are answered so poorly that I have to submit freedom of information requests to elicit basic information. I want some straight answers today. Why is only a junior Minister with other responsibilities in charge of the largest infrastructure project in Europe, which costs more than Brexit? Surely it should have its own Minister, if not its own Department. In her written answer today and in her statement just now, the Minister gives the impression that the entire decision on the go-ahead of this project comes from her. Will she be the sole Minister responsible for issuing the notice to proceed?

Why has the cost of HS2 not been updated since 2015, and what are the actual costs at today’s prices? What is the latest evaluation of the cost-benefit analysis, and why has that not been done already? When will the Treasury review be completed, and will a full report be published? Is the delivery of HS2 still being flagged with an amber-red warning, and how regularly is Cabinet updated on this project? Has HS2 applied for and received all the environmental licences and permissions required to carry out this environmental vandalism in Buckinghamshire?

What level of control and monitoring does the Secretary of State exercise over the awarding of contracts and the finances, and if he does have a level of control, why has £1.7 million that was paid out in unauthorised redundancy payments not been recovered or any director held to account? What would it cost to cancel the project now? Why, with so many doubts and unanswered questions, will the Government not agree to a perfectly reasonable request from Bucks County Council to have a six-month pause to do a total re-evaluation of this project, which has already blown its timetable and its budget before it even has the go-ahead?

John Bercow Portrait Mr Speaker
- Hansard - -

The Minister’s use of the words “along the route” in her initial reply has somewhat widened the scope, which is no doubt music to the ears of the hon. Member for Stone (Sir William Cash), the hon. Member for North West Leicestershire (Andrew Bridgen) and, to judge by his grinning countenance, the hon. Member for South Dorset (Richard Drax).

Nusrat Ghani Portrait Ms Ghani
- Hansard - - - Excerpts

My right hon. Friend has posed a number of questions, which I will do my best to get through. She has expressed her disappointment that I am not the Secretary of State, but I am indeed the Minister responsible for this project. Not only is the project this Government’s policy, but it was in the Conservative party’s manifesto as well as in the Labour party’s manifesto. It is absolutely right that the Minister responsible for the project continues to undertake to ensure that it stays on track.

This is a good opportunity to remind the House why HS2 is so important. It is indeed a national project, and it is the largest infrastructure project in Europe. It will connect eight of our 10 biggest cities, connecting half of our country’s population, so every Member of Parliament in this place will have constituents who are positively impacted by HS2. It will create thousands of jobs directly and over 100,000 jobs indirectly, and the net positive for our economy will be well beyond £94 billion over its lifetime.

We always talk about investment in our rail network and why we need to have extra capacity when it comes to HS2, but demand on the west coast line has increased by 190% since 1995 and we are close to being unable to add any more seats or trains. People often stand the whole way on long-distance journeys, and while delays are less frequent than in the past, we need a solution, and HS2 provides that solution. It is supported by a number of leaders up and down the country, but particularly in the midlands and the north, who often comment not only to the media but to me that they are quite fed up about people in the south commenting on what is needed in the north.

My right hon. Friend wanted to know about the notice to proceed. The notice to proceed is the point when HS2 Ltd instructs its main works civil contractors to begin construction of the phase 1 railway, as set out in the HS2 development agreement, which was in the Bill that went through in 2017.

My right hon. Friend talked about the impacts on Buckinghamshire, and she has been a very passionate campaigner for her constituency. I understand that her constituents will be feeling some of the impacts of HS2’s construction, but the enabling works are absolutely crucial, especially when it comes to the environment. The early works are necessary to enable the construction of HS2 to proceed in accordance with the programme once notice to proceed is given. The existing programme of enabling works includes habitat creation, tree planting, ground investigation, the construction of work compounds, road improvements and utility diversions. This existing programme of enabling works has not changed, and it is the backbone of ensuring that further environmental mitigation can take place, which is why enabling works are so crucial. My right hon. Friend will know, because we have often talked about this, that HS2 is seeking to achieve no net loss in biodiversity across the route of the new railway.

My right hon. Friend also talked about the particular impacts in her constituency, and she has been a staunch campaigner on behalf of Buckinghamshire, which we know will be impacted by the line. A large section of the subsurface route, in the form of the 24 km Chilterns tunnel, has already been put through the hybrid Select Committee process. Furthermore, £3 million has been provided for the Chilterns area of outstanding natural beauty, and there are the £5 million woodland fund, the £30 million road safety fund and the £40 million community and environment and business and local economy funds. Buckinghamshire has already received over 30% of all the awards it could be afforded.

HS2 is a large infrastructure project—there is no denying that—but it is absolutely vital if we are to focus on smashing the north-south divide and provide opportunities for people who live beyond London and the south-east. It is and will be the most important economic regeneration project for a generation, and it is absolutely right that parliamentarians commit to long-term infrastructure projects that reflect the needs of our country.