Great Western Line: Electrification Debate
Full Debate: Read Full DebatePaul Maynard
Main Page: Paul Maynard (Conservative - Blackpool North and Cleveleys)Department Debates - View all Paul Maynard's debates with the Department for Transport
(8 years, 1 month ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
It is a pleasure to serve under your chairmanship, Mr Hollobone. I congratulate my hon. Friend the Member for Bristol North West (Charlotte Leslie) on securing this debate. Contrary to what we have just heard, I actually welcome the debate and the opportunity to discuss a complex project. Whether I can do it justice in nine minutes is another matter, but I will do my best. If I fail to address anyone’s points, I shall be more than happy to write to colleagues, and I thank all those who have participated in the debate.
My hon. Friend started by suggesting that the south-west was perhaps not first in the queue. My diary shows that I started today at the publication of the report of the all-party Peninsula Rail Task Force. Immediately afterwards, I had a meeting about the Exeter to Barnstaple railway line, and I have spent the rest of the day addressing this issue, which is a priority for the Government—and not just today. This is the first major rail electrification project for many, many years, and there has been an awful lot to learn. I am not someone who tries to go for cheap partisan points, but there is one that cannot be avoided in this discussion: the Labour party electrified fewer than 20 miles of track in its 13 years in office. We are having to overcome a backlog of delayed investment.
As we have heard, the NAO report on the electrification of the Great Western Railway states that £330 million has been wasted so far. Does the Minister believe that that huge waste of money endangers the final delivery of the Cardiff to Swansea section of the project?
We certainly recognise a lot of what the National Audit Office report says, and I will set out what the Department is doing in response to that. As the hon. Member for Bristol East (Kerry McCarthy) pointed out, the Secretary of State was critical of progress on the project so far at Transport questions last week. I share those concerns; the project clearly has not gone well.
However, it is worth stressing that we are having to defer four elements. I have heard many words pass around the Chamber—“cancellation”, “pause” and all sorts of others—but “deferral” is quite a precise term. No work is being paused; if one considers the various elements that make up the scheme around Bristol, work is continually ongoing. We are raising bridges, improving line speeds and resignalling. That is all preparatory work before decisions can be taken on proceeding with further electrification. The only work that has been suspended in the greater Bristol area is the erection of the overhead line equipment. That is what has been deferred until a future control period. I cannot make precise statements about what control period 6 will contain, because that has to be part of a wider national package, but I want to make it clear that we are not stopping work on the electrification programme in the Bristol area. That work continues.
If that is the case, why do the Government continue to spend money doing something that they cannot at any point say when we will need? Is that not potentially wasting more taxpayers’ money? What is the purpose of electrification if it does not deliver benefits and we are going to spend more money at some unknown time in the future?
I have just said that we will be making announcements about what—[Interruption.] Is the hon. Lady going to listen to my reply or just mutter at me? I am happy to respond to her point if she wants to listen. We will take decisions about what control period 6 comprises and announce the whole of that control period at the appropriate time. As a member of the Public Accounts Committee, she will be more than aware that Sir Peter Hendy has already reprogrammed other projects across the country. As Rail Minister, I am not prepared to part-announce elements of control period 6 depending on what debate I happen to be in at any moment in time. That would not be a prudent way to go forward—nor, were I in her position on that Committee, would I think it a particularly prudent position for any Minister facing her queries to take.
Can the Minister reassure us that as a result of the deferral that he has just described, the cost-benefit ratio of the elements of the programme that have been paused will not be substantially changed? Can he also provide us with information about how those cost-benefit ratios compare with both the decision not to go ahead at all with the electrification of the suburban Bristol railway lines and things that are going ahead, such as High Speed 2?
There will always be ongoing recalculations of the cost-benefit ratios of any wider projects, as well as the elements within them. I do not see this as a matter of HS2 or the great western main line. There are investment backlogs that we have to catch up on in all parts of the country, and each investment has to respond to a specific rail need in that region. Here, we are trying to respond to a specific rail need by ensuring that all the passenger benefits that can be accrued by electrification can be delivered as soon as possible for the use of the new bi-mode intercity express programme trains.
If the hon. Gentleman wants to intervene, it will have to be the final occasion.
That is very reassuring. I would be very happy if the Minister would provide the specific numbers that I asked for, perhaps in a letter.
I will happily write to the hon. Gentleman with that information at a later point. That is more than fine.
Hon. Members have noted the extra seats and the 15-minute journey time saving from London Paddington to Bristol Temple Meads via Bristol Parkway that the new trains will provide, and I hope that they will also note that those trains should stimulate economic growth across the region as a whole. Bristol is one of the few cities that is a net contributor to the UK Treasury, and that has to be recognised. We need to do more to work with Bristol to ensure that all those in the commuter belt around Bristol are properly able to access the city. That entirely makes sense. But we need to go back to the fundamental point that modernising this line has been an ambitious and challenging undertaking, and it has not been straightforward. Even closing the Severn tunnel for six weeks this autumn has caused immense disruption to journeys and people’s lives, but it has been worth while, because had we not closed it for those six weeks, there would have been five years of weekend work and disruption.
As a result of that challenge and the complexity of the work, with ageing assets, heritage sites and a very busy line that Network Rail has to work around, difficulties have occurred. As was mentioned, the National Audit Office report was highly critical of what had occurred. However, what is often not pointed out in these debates is the recognition the NAO has given to the changes that the Department has made since 2015. In particular, we now have a programme board for each route upgrade across the country, chaired by a senior responsible owner from the DFT, to provide effective oversight of delivery.
We are working closely with Network Rail, train operators and other partners to ensure that major construction works and the introduction of new train services occur in a pragmatic, sequenced and timely manner and that all elements of those complex processes interact sensibly with each other. There is no point in delivering a piece of rolling stock that cannot operate on a particular track because the infrastructure work has not been done. That requires work to be sequenced. Much of the criticism in the NAO’s report was of the failure to sequence early on in the process and understand the true scope of the project.
My hon. Friend the Member for Bristol North West was concerned that the decision represents a waste of money. I would say that it does not at all. The preparatory work will enable future decisions to be taken, which is also a point that she made. If one takes some of the work around Bristol East junction, for example, the savings made through the deferrals are specifically targeted at bringing forward the work to enable the capacity improvements that will allow full advantage to be taken of the new bi-modes. If that did not occur, there would be less benefit from having the bi-modes because there would not be the capacity at Bristol East junction. That underlines the point about sequencing work and, in a project of this complexity, the overall need to have a degree of flexibility in the system so that, as technology moves on, options change and new pieces of locomotive and rolling stock come on stream, we have the capacity in our projects to make those pragmatic decisions and seek to deliver the benefits to passengers as soon as is possible.
As I mentioned earlier, this decision underscores a wider approach to rail investment across the country as a whole. Passenger outcomes must be delivered while achieving the best value for every pound spent. On that point, the Government have been clear about the rationale for electrification. We are not against using electrification as part of a wider strategy for delivering improved services. Electrification does bring benefits. It enables, for instance, the use of electric trains, which over time reduce the cost of running the railway as well as bringing environmental benefits—but we have to make improvements in the way that makes most sense and gives most value to the taxpayer. Therefore, in some cases, where a train can run on both electric and diesel power, it is right to look at how that can be factored into any decision about how we sequence the different elements of any electrification process.
In the end, electrification is not an objective. It is a means to an end. It is an input. It is about putting wires up. It is about traction and power. It is an engineering solution to a defined problem. Yes, it is an enabler of new trains, but that new capacity is needed by passengers as soon as possible. Therefore, if we have access to these new trains, I think it right that we go down that path.
May I press the Minister on when he thinks the Cardiff-to-Swansea section of the project will be completed? What is his latest estimate?
Order. Before the Minister replies, may I say that he must allow time for Charlotte Leslie to sum up?
I do beg your pardon, Mr Hollobone. I was looking at the clock showing the time left for my speech. If I may, to save time, I will write to the hon. Gentleman. I will end it there and write to any further Members who asked questions to leave time for my hon. Friend the Member for Bristol North West to finish the debate. I thank hon. Members for listening.