Great Western Line: Electrification Debate
Full Debate: Read Full DebatePhilip Hollobone
Main Page: Philip Hollobone (Conservative - Kettering)Department Debates - View all Philip Hollobone's debates with the Department for Transport
(8 years ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
I thank my hon. Friend for raising that extremely good point.
I know that many other Members would like the chance to speak. My final concern, which has been raised locally, is about rolling stock. The effect of the deferral of the electrification of the Thames valley branches on the planned cascade of the Thames turbo class 165 and 166 rolling stock to the west of England is vital to the MetroWest phases 1 and 2 projects. I have been very public about what seems to me, and to many others in the region, an appalling missed opportunity on the part of local decision makers—their failure to prioritise the Henbury loop line in the MetroWest scheme. I have been clear that I do not think that such schemes are ambitious enough to meet the exponentially growing branch line demand in our region; however, they are a start. If the MetroWest scheme, as it is, were to suffer even further detriment, that would be catastrophic for our city and our region. I cannot impress that upon the Minister enough. Can he give assurances today that the rolling stock cascade—the Thames turbo class 165 and 166—will not be affected by the deferral?
I turn briefly to the Bristol East junction and to Temple Meads, issues that the hon. Member for Bristol East (Kerry McCarthy) will probably want to raise in more detail than I will. I have been pleased to be able to work, in many ways cross-party, on rail for our city. Can we get assurances regarding the concerns about the future of the remodelling of that junction and about plans for transforming Bristol Temple Meads to accommodate new trains at platforms zero and one? I know that the hon. Lady will want to speak about that, but I would like some replies from the Minister.
This is an important debate for so many MPs and so many of their constituents. It is not, as I fear it might be seen by some, people fussing over whether we have wire in the sky. It is about the south-west being sick of being the poor relation in our nation’s transport projects while other high-speed projects go roaring on. It is about a real concern that this is somehow the thin end of a wedge that will see all the progress we have made over the past six years, of which I have been so proud, melt away. It is about all of us here, regardless of party, asking serious questions about whether the mechanisms and bodies that this or any Government have at their disposal to plan and build rail infrastructure are any longer fit for purpose. Given what we have seen of projects soaring over budget and over time and then getting paused, deferred, cancelled or any other word anyone would like to use, under an array of Governments, it is hard to believe that Network Rail is fit for purpose. If it is not, and assuming Britain wants to be a global competitor, can the Minister provide some thoughts on what on earth we are going to do about it?
Several hon. Members rose—
Order. The debate is due to finish at 5.45 pm. It is an hour-long debate. It is very difficult to chair because I have an array of parliamentary talent before me and just over 20 minutes of Back-Bench time before I have to call the Front-Bench spokespeople. Unfortunately, I am going to have to impose a time limit of three minutes. If Members intervene on each other, some of you will not get called, but if you stick to three minutes, everyone will get in, and there may be time at the end to intervene on the Front-Bench spokespeople.
It is a pleasure to serve under your chairmanship, Mr Hollobone, and I congratulate the hon. Member for Bristol North West (Charlotte Leslie) on securing the debate. I will curtail my comments.
I speak for my Bristol South constituents, who also use Bedminster and Parson Street stations, when I say that the so-called deferral of this project has confused and outraged passengers in my constituency. We are confused because, despite the promises that we received and the significant disruption that we have tolerated, we have a half-finished project. We are outraged because the rail connections are such an important part of our economic development and our success. Bristol is key to the entire regional economy and that is why this is such a critical decision.
In 1835, an Act of Parliament created the Great Western Railway. In just six years, Brunel managed to build the entire thing from Paddington to Bristol—but in the last six years we have seen a complete lack of progress. Decisions have been delayed and deferred and now progress has been halted. At the Public Accounts Committee next month, we will consider the National Audit Office report and I would be grateful for comments from all Members. I suspect the hon. Member for Torbay (Kevin Foster) will also join that discussion. The report is very clear. Who is accountable now for the decision? Who is in charge of the plan to deliver benefits to passengers? Who lined up the key components of the new trains with the infrastructure and the operator? Who is managing the critical path alongside things such as the signalling works?
I have three asks of the Minister. If he does not have time to answer my questions, I would appreciate an answer in writing. First, is there still a case for electrification? What is now the Department’s analysis of the benefits for passengers in terms of journey times, frequency and capacity—dare I mention having a seat?—of bimodal trains versus electrification? We do not seem to know.
Secondly, Mr Brunel built the entire railway via an Act of Parliament, so why did the Department for Transport not at any point place an order under the Transport and Works Act 1992 for all the works? It might have taken longer to get to this point, but Network Rail would not have had to go through the myriad processes that it has had to, across the whole line.
Thirdly, what is the role of the regulator, the Office of Rail and Road? The Government have chosen to make it an arm’s-length body, but what is its responsibility in all of this? There is a political choice between enhancements and renewals or maintenance. The regulator has a clear role on renewal and maintenance, in light of its safety responsibility, but enhancement such as electrification is different. I am interested to know what the Minister thinks about that.
The core of the matter is passengers and our constituents. Whatever processes were undertaken to deliver the decision, it is true to say that as a result Bristol people feel we are being short-changed, and as we are the gateway to the region, the entire south-west region is being short-changed. Who is making these decisions on behalf of Bristol colleagues? Consider the make-up of the Government, the Cabinet and the Tory Front Bench. Apart from the Secretary of State for International Trade, the right hon. Member for North Somerset (Dr Fox), the south-west has no representation at the top table of Government. There are 51 Tory MPs in the south-west, out of 55. I congratulate them on their victory, but they have a small smattering of Ministers from their number to be able to deliver top decisions at the top table—
It is a pleasure to serve under your chairmanship, Mr Hollobone.
I congratulate my hon. Friend the Member for Bristol North West (Charlotte Leslie) on securing the debate. She made many of the points that I wished to make, but much more eloquently than I might ever have done. I join her in expressing disappointment at the decision to defer the four electrification projects along the great western route.
I will reiterate a couple of the points made by my hon. Friend, because that decision will have a direct impact on a number of my constituents in south Gloucestershire who travel from Yate, specifically, to Bristol Parkway and on to London. More passengers will continue to use the Bristol Parkway service as a result of the worsening congestion for many residents of south Gloucestershire.
I will also express some concerns about the knock-on effects of the plans to delay investment. I first seek reassurances from the Minister, as others have done, that the deferral of electrification of the Thames valley lines will not affect the cascading out of the Thames Turbo trains, the 165 and 166, to the west of England. They are essential to replace the trains that Great Western Railway has to return at the end of their leases. Failure to do so will result in a reduction of services and an increase in passenger overcrowding.
The chairman of our local West of England LEP called those trains
“essential to deliver the £100m MetroWest Phase 1 and 2 rail schemes”.
Phase 2 of the MetroWest scheme includes the plan to increase the frequency of services between Bristol and Yate from hourly to half-hourly, which will be hugely important to people in Yate, Coalpit Heath and surrounding areas. It has overwhelming support from people who want to see a reduction in overcrowding on the service, and would without doubt take more cars off already congested roads around Yate and Coalpit Heath. I will be grateful if the Minister clarifies that in his closing remarks.
I will also be grateful if the Minister clarifies the impact of the decision to delay on the local four-tracking project at Filton, which, too, is essential to deliver MetroWest phase 2. South Gloucestershire Council has already started some of the clearing work, so an early indication of any effect from the Minister will be extremely welcome.
Lastly, I call for reassurance that there are no plans to change the proposed four inter-city express services an hour between Bristol Temple Meads and London, two of which will pass through Bristol Parkway and connect directly with Yate services.
I thank my hon. Friend the Member for Bristol North West for securing the debate, and I will welcome the Minister’s reassurances.
We now come to the Front Benchers’ speeches. I want to call Charlotte Leslie again to sum up the debate no later than 5.43 pm, which means that the Front-Bench speakers have nine minutes each. Were the Opposition spokesman to take less than nine minutes, there will be more time for the Minister to speak and, potentially, for interventions, but we are in her hands. I call Pat Glass.
Thank you, Mr Hollobone. I will endeavour to be as quick as I can.
The recent decision by the Department for Transport to delay the electrification of the great western route is just the latest in a series of announcements of delays and pauses made by the Government on electrification of our railways. We have had one announcement after another by the Government, who still state that they are planning electrification, but while the Government have promised much, they have delivered little.
I sympathise with the Minister. Like me, he is new to the role and just happens to be holding the parcel when the music stops. However, I have a criticism about his recent announcement, because he appeared to sneak it out just hours before the November recess and on the day of the American election when, presumably, he was hoping we would all be looking the other way.
I therefore congratulate the hon. Member for Bristol North West (Charlotte Leslie) on securing this important debate. She and I served together on the Select Committee on Education when we were new Members in this House, and I understand her dedication to the city of Bristol. I also want to acknowledge all the MPs from Bristol: they are four strong women, who are here together fighting for a better future for rail in their city.
The case for the electrification of the route was set out in October 2009. The Department for Transport projected then that it would take eight years to complete and cost up to £1 billion. According to the original timetable, we should have been looking at a fully electrified line from London to Swansea by the end of next year. Since then, however, the project has had a very unhappy journey.
Two weeks ago today, we were told by the Rail Minister that the project will be paused, with no detail of when it might be unpaused or restarted, or, indeed, if it will ever be completed at all. Over the past six and a half years we have had delay after delay to the original timetable, and the cost to the taxpayer has skyrocketed as a result. As the Minister knows, the National Audit Office, in its recently published report, laid the blame squarely on the Department for Transport, stating that it did not
“plan and manage all projects…in a sufficiently joined up way.”
I have worked in government at local and national levels. At the national level, I found that the lack of planning and joined-upness makes local government look like a smoothly operating machine, and that is saying something. Even within that, the Department for Transport has its very own place.
The cost of the project was reassessed in September 2014, when the Department estimated it at £1.5 billion, up 50% on the original costings. Although the cost-benefit ratio expected by the Department for Transport in March 2015 was within the Department’s high value-for-money range, at 2.4:1, by the end of last year that had dropped to 1.6:1, which meant that it had fallen to within the medium value-for-money range. That is because the Department was forced to announce that the cost of the project had been revised yet again and was now estimated to be more than twice the original projection, at £2.1 billion. The latest announcement is in another league altogether, however, with the estimated costs to the taxpayer reaching £5.58 billion. The Government have managed this infrastructure project so badly that the cost-benefit ratio has now fallen through the floor.
The issue is not isolated to the great western route alone. Rather, the Government’s handling of the electrification of UK railways is being felt right across the country. First, we had the delays to the electrification of the trans-Pennine railway. Originally planned to be completed by the end of 2018, that is now looking distinctly unlikely—to put it politely. The electrification of the midland main line was paused in June last year. The wires will now not reach Kettering and Corby until 2019—that is today’s estimate—whereas the original plan had been for electrification to stretch far beyond Corby to Derby, Leicester and Nottingham by 2018. When the Government finally announced that both plans had been revived, it was only to say they would be four years behind schedule.
In 2013, 30% of the most crowded train services in England and Wales were Great Western services into Paddington, and the Department for Transport forecast tells us that passenger demand on that route is to grow by 81% between 2013 and 2019. Electrification is therefore essential if we are to see any improvement for passengers. It will lead to further economic benefits, in particular driven by freight trains running on electrified lines, and it is vital if we are to reduce our carbon footprint and will help to build a greener transport network, with the increase of freight on rail being central to that aim. It is therefore really disappointing to see that a significant part of the estimated £330 million that will be added to the bill for the electrification of the great western route will come about because of the revisions that are needed to the new all-electric trains that the Government ordered.
Thanks to the delays, those trains, which were set to cost the taxpayer £4.1 billion, will now need to be fitted with diesel engines so they can run on sections of the great western route that the Government have now decided will not be electrified. Adding those diesel engines will make the trains heavier, less energy efficient, more polluting and more damaging to the track. So this Government will spend £5.58 billion on upgrades to the great western route that will in fact cause a reduction in capacity, a slower service and an increase in carbon emissions and mean that rail lines will require even more regular maintenance work. That is quite an achievement.
My right hon. Friend the Member for Slough (Fiona Mactaggart) said that this issue impacts on the earlier debate about pollution in the Thames valley and the decision about a third Heathrow runway. Further, passengers in the north of England and Scotland will have to wait up to two years longer for improvements to their services, because the revised plans and delays to infrastructure works mean that old Great Western Railway stock will not be passed on to other areas that were depending upon getting that old stock to make such improvements.
The budgeting for this project has been shambolic, and clearly no one can confidently rely on any figures produced by the Department for Transport. The Government cannot be allowed to get away with continually claiming to be investing in infrastructure when we see Ministers once again with their tails between their legs trying to sneak out announcements about further delays to their plans.
Will the Minister tell us exactly when the Government intend to follow through on the great western line? When can we expect the pause to cease and the project to restart, if it restarts? In what shape will it be if it ever restarts? At the beginning of the debate, the hon. Member for Bristol North West talked about passengers. She is absolutely right: neither passengers nor taxpayers are getting a good deal, and quite frankly, they deserve better.
Order. Will the Minister bring his remarks to a conclusion no later than 5.43 pm to allow the mover of the motion to sum up the debate?
May I press the Minister on when he thinks the Cardiff-to-Swansea section of the project will be completed? What is his latest estimate?
Order. Before the Minister replies, may I say that he must allow time for Charlotte Leslie to sum up?
I do beg your pardon, Mr Hollobone. I was looking at the clock showing the time left for my speech. If I may, to save time, I will write to the hon. Gentleman. I will end it there and write to any further Members who asked questions to leave time for my hon. Friend the Member for Bristol North West to finish the debate. I thank hon. Members for listening.