Shivani Raja
No, that is fine. Do you have anything to add, Mr Palmer?
Matt Palmer: I think it is beyond my scope—National Highways is here as an operator and a constructor. I think Will has probably answered the question properly.
Mike Reader (Northampton South) (Lab)
Q
Matt Palmer: I think all of us recognise that annualised costs on major projects, especially mega-projects, are very difficult to deal with. They drive perverse cost behaviours, where you are trying to fit into a 12-month window, and the Government are currently moving, with the mega-projects piece, towards more of an envelope-type conversation. This is just another extension of that. You end up with a cost envelope that you are working within, with a driven timeframe that you have to deliver to, which then allows the flexibility to execute at the right time—depending on the weather and so on. It is that flex that you need in order to execute efficiently. If you are constraining yourself on cost to a budget every year, which is common, it does drive cost. This model gives you the flex that allows you to drive an efficient construction project.
Mike Reader
Q
Matt Palmer: The base cost of the scheme—the cost without inflation—has been fixed since 2020. The great thing about a development consent order is that the scope is fixed. We are still building 52 bridges, 22 km of road and 4.3 km of tunnel. The cost difference between now and previously is essentially driven by inflation. You have got great cost control sat there inside the direct consent order. Our contracts with our contractors then drive to that same scope and control, and there is a pain/gain share: they get into pain if they exceed and they get incentivised to deliver below, which is normal with any project of this scale.
Mike Reader
Q
Will Godfrey: I hope my earlier answers go to some of that. If your question is specifically about the scope of what you were just asking Matt, it is important for us that the arrangements around what will be LTC Co. and its relationship with its contractors, and in turn what it is allowed to charge to end customers, is not a simple pass-through-type arrangement. That is really important.
You need to make sure that there are the right liability caps in relation to the pain/gain sharing. Are those at the right level? Has LTC Co. or any company licensed under these arrangements—let us concentrate on the LTC example—got the right incentives to be able to control the relationship with the contractors? Through the licence and the price control arrangements we need to create arrangements in which there remains that discipline to control those costs, so it is not a set of arrangements in which, beyond a certain threshold, end users are ultimately on the hook for cost pass-through.
The importance that the Bill places on efficiency in the economy and that being at the heart of our duties is something that we would take really seriously and very much welcome. It gives us the authority to be able to act on getting to those kind of price control licence arrangements. Of course, as I said earlier, the first price control arrangement would be set by the Department through that first competition for the first licence. In terms of how we operate on it thereafter, we would look to make sure there is not just a simple mechanistic pass-through in the event that costs overrun, whether for inflation or other cost shocks.
Douglas Lumsden
Q
Justin Madders: I do not think that this is covered by the Bill anyway, but I will certainly take it away to see if there is anything to reflect on. I assure you that this would not be proceeding if there were no interest in investment.
Mike Reader
Q
Justin Madders: I think it will. Obviously the Treasury decision on how this is going to be funded is driving us in a direction where we have to secure private investment. I think the model gives us the opportunity to give the investor certainty over a long period. Clearly, guardrails in there will protect users as well, but as I say, the indications I have had so far are that the long-term nature of the project and the way in which it has been de-risked make it an attractive proposition.
Mike Reader
Q
Justin Madders: As I probably made clear, the Bill is scheme agnostic, so an amendment to require a certain type of fuel would not really help us at all. Look, we have had quite a lot of evidence and, as a Committee, we should take confidence in the measures that are in place to ensure that the costs are kept under control.
Mike Reader
Q
Justin Madders: I suppose, to pick up from one of the witnesses, I will reference the fact that the road investment strategy—which was started by the previous Government —has set us up with a very sustainable model to develop these large projects over a longer term, giving confidence to the supply chain to keep control of costs and to deliver on time and within scope. I think that National Highways is now very well skilled at doing that, which should give us all confidence.
Mike Reader
Q
Justin Madders: The tolls will ultimately be part of part of the licence, which is covered by the Bill—
Mike Reader
Q
Justin Madders: That will be part of the licence conditions, and probably a little too specific for the Bill. Obviously, there are safeguards in the Bill about the things that will need to be considered by the operator.
Mike Reader
Q
Justin Madders: Yes, we are happy to do that.
The Chair
As there are no further questions from Members, I thank the Minister for his evidence. That brings us to the end of the sitting. The Committee will meet again at 9.25 am on Tuesday 3 November to begin line-by-line consideration of the Bill.