Nuclear Energy (Financing) Bill

Mark Jenkinson Excerpts
2nd reading
Wednesday 3rd November 2021

(2 years, 5 months ago)

Commons Chamber
Read Full debate Nuclear Energy (Financing) Act 2022 View all Nuclear Energy (Financing) Act 2022 Debates Read Hansard Text Read Debate Ministerial Extracts
Greg Hands Portrait Greg Hands
- Hansard - - - Excerpts

The right hon. Gentleman said he was first elected in 2001, but my guess is that he was a supporter of the 1997 manifesto. What says supports what the Government have been doing here for some time, which has been to increase our nuclear capacity and make sure the financing models are in place to support the funds. I am surprised he voted against the Budget last week, with its £1.7 billion made available for new nuclear. Perhaps he might explain to his constituents why he was against that Budget.

Mark Jenkinson Portrait Mark Jenkinson (Workington) (Con)
- Hansard - -

Just to carry on the point about Labour’s involvement in this, I should point out that at his final party conference Tony Blair said:

“10 years ago I parked the issue of nuclear power. Today, I believe without it, we are going to face an energy crisis and we can’t let that happen.”

For the first time in my life, I am going to say that Tony Blair was right. The French are reaping the rewards of Messmer’s nuclear legacy. Will my right hon. Friend commit today to his Messmer-style nuclear legacy for the UK?

Greg Hands Portrait Greg Hands
- Hansard - - - Excerpts

I, too, do not often agree with Tony Blair, but it was good to see his conversion in the end, albeit that it took him 10 years. I have always been a passionate supporter of nuclear power, right since I was first elected in 2005, which was round about the time of that Labour volte-face. I was a strong supporter of Labour’s changing its view at that time; it is just such a pity that there was a lost decade before it came to that view.

Let me move on—

--- Later in debate ---
Alan Brown Portrait Alan Brown
- Hansard - - - Excerpts

It will be no surprise to hear that I have no confidence that the true costs of nuclear waste disposal are actually included. We hear that this is rolled up in the strike rate for Hinkley, but if something happens and EDF goes out of operation, who will pick up the additional costs? It will clearly be the bill payers or the taxpayer. We hear about the fact that nuclear is supposed to be clean energy, but how can it be classed as clean energy when we are burying radioactive waste and having to store it for up to 1,000 years? That, to me, does not mean clean energy.

Taishan in China was held up as an exemplar EPR project when it was commissioned, but it has been offline since June this year due to safety concerns and rod damage. It is clear that the design and construction of EPR nuclear stations has still not been bottomed out properly. As the shadow Minister, the hon. Member for Southampton, Test (Dr Whitehead), said, a reliance on French state-owned EDF and the Chinese state company China General Nuclear kind of undermines the argument about having sovereign energy security. It makes no sense.

Despite the cost and programme issues at Hinkley, we are told that Sizewell C will somehow be different. There will be cost savings from learning on Hinkley. The design will be replicated, saving more money, but the reality is that the site at Sizewell C is bound to have different ground conditions, different environmental considerations and different logistics and site constraints, which affects methods of working, and that means that we cannot build an exact duplicate station the same way.

Even if savings are realised on Sizewell C compared with Hinkley, what does that mean cost-wise? If Sizewell C saves 25% compared with Hinkley, that is still a capital cost outlay of £18 billion. Surely there are better ways to spend £18 billion. We heard from the right hon. Member for Kingswood (Chris Skidmore) about the number of jobs being created. If I was given £18 billion to £20 billion, I am sure that I could create 30,000 jobs —by the way, that is £730,000-odd a job in capital costs alone. That is not a good return.

On costs, we are told that a new deal signed under the proposed new funding model in the Bill will cost consumers only £1 a month during construction, but if we look at a 10-year construction period for Sizewell C, we see that that means that bill payers in 28 million households will pay £3.4 billion before it is operational. That is a further £3.4 billion in expenditure when that money could be better invested elsewhere.

We still do not know with this Bill what the long-term pay-back options will be. Will there be a further agreement on the strike rate or a minimum floor price on the sale of energy? What length of contract will bill payers be tied into once a RAB model for an agreement is signed off?

What else could we do with that amount of money? We could upgrade all homes to energy performance certificate band C. We could have wave and tidal generation. The UK Government are willing to introduce the Bill and commit hundreds of millions of pounds to nuclear—the Budget has £1.7 billion just for developing nuclear to a negotiation stage—but they will not even ringfence £24 million for wave and tidal in pot 2 of the forthcoming contracts for difference auction. The disparity is clear.

It is time the Government took their blinkers off. It will be a real disgrace if they do not provide a pathway for wave and tidal projects to scale up. Scotland is currently leading the world on the issue; the O2 tidal generator is operational and grid-connected in Orkney. I hope that the Minister will reconsider the request to ringfence a small amount of money in pot 2 of the forthcoming contracts for difference auction.

Mark Jenkinson Portrait Mark Jenkinson
- Hansard - -

I am a huge supporter of tidal energy, but is it not the case that nuclear, given its energy density, is the most environmentally friendly and low-carbon technology that we have, while tidal has the potential to significantly damage marine ecosystems? I am a big supporter of tidal energy, but we have to be really careful about where we deploy such things. We have a ready-built, proven technology here—the most environmentally friendly and low-carbon technology that there is.

Alan Brown Portrait Alan Brown
- Hansard - - - Excerpts

I completely agree with the hon. Gentleman about nuclear being clean—oh, wait, apart from the radioactive waste that we still do not know what to do with. We will ignore that point, but he has a valid point about the need for clear environmental considerations with respect to where we site any marine project. That should be part of a robust, up-front planning process, working with the likes of Marine Scotland. There are regulatory bodies that have oversight of these projects, so it is important that they be involved in the planning process. I agree with the hon. Gentleman that there is still a huge future for wave and tidal.

Alan Brown Portrait Alan Brown
- Parliament Live - Hansard - - - Excerpts

I completely agree. I was happy to co-sign the cross-party letter from the all-party parliamentary group on marine energy, which I fully support. I hope that the Minister is listening, because this is a matter that we agree on across parties.

Looking at other technologies that we should be spending money on, I compliment the UK Government on seeing the opportunities that floating offshore wind can bring, but let us start deploying it much more quickly and investing more money, because that is where the real future is. Clearly, the further out to sea the turbines are, the greater the reliability of wind and subsequent generation.

There needs to be much greater investment in carbon capture and storage. The Government need to reverse their disgraceful decision not to have a Scottish cluster as part of their track 1 CCS projects. A Scottish cluster would also deliver hydrogen production, which is vital on the pathway to net zero.

We heard earlier, as we always do, the argument that nuclear is required for when the sun does not shine and the wind does not blow, but as I have tried to point out to the Minister, there is an existing technology that can address that issue: pumped storage hydro, a renewable energy source that utilises surplus grid energy to fill the reservoirs and can then dispatch electricity when required. Pumped storage hydro is the perfect foil for intermittent renewables, rather than big, inflexible nuclear power stations that invariably pump energy to the grid when it is not required. An Imperial College report suggests that there could be system savings of £700 million a year from using pumped storage hydro technology instead of nuclear.

SSE has all the necessary permissions in place, right now, to progress a new pumped storage hydro scheme at Coire Glas in the Highlands. It is progressing the design at its financial risk, and all that it needs is agreement with the Government and a minimum floor price for electricity—not a strike rate and not direct funding, just a minimum guarantee on the sale price of electricity. Then the development can reach the construction stage, and can be commissioned in the same timeframe as Hinkley. I ask the Government to reconsider, and to get round the table with SSE and other developers.

Mark Jenkinson Portrait Mark Jenkinson
- Hansard - -

I thank the hon. Gentleman for allowing me to intervene again. I am a big supporter of pumped hydro, which is great for storage, but we cannot neglect the fact that we require a surplus of electricity to pump the water in the first place, up to the point of that storage. It is great to be in control of when we release the water and use the energy, but we have to think about how we get it up there in the first place.

Alan Brown Portrait Alan Brown
- Hansard - - - Excerpts

Absolutely. That is my point. This is about utilising spare energy and then filling the reservoirs. That is much more productive than, with nuclear, putting additional electricity into the grid and then making constraint payments to wind farm developers to turn the turbines off. Those turbines could be used to much greater effect for the likes of pumped storage hydro, or generating green hydrogen.

It is clear that there are alternatives to nuclear. The Government have rightly pointed out that the existing nuclear fleet is coming to an end, but they have wrongly concluded that that means we need new nuclear. Dungeness went offline earlier this year, seven years early, because of safety concerns. Hunterston B is about to go offline, and Hinkley Point B will close next summer. Hartlepool and Heysham will follow in 2024. That means that Hinkley Point C will not even replace the lost capacity, and by 2024, 5.3 GW of nuclear capacity will have been lost to the grid.

If the grid can operate successfully without that 5.3 GW of nuclear for three or four years until Hinkley’s 3.3 GW comes on line, that in itself confirms that new nuclear power is not required. In all likelihood, Torness and Heysham 2 will not last until 2030, so all but one of the existing stations will be offline before Hinkley comes online. By not replacing the existing nuclear fleet as it comes to the end of its life, the UK Government are themselves proving that we do not need a nuclear baseload, because the grid can operate without it, unless an energy security crisis arises when all the other stations go offline. The Minister can address that later if he wants.

Although here in the Chamber it is just me saying that we do not need new nuclear, plenty of experts agree. Back in 2015, the then chief executive officer of National Grid, Steve Holliday, said:

“The idea of large power stations for baseload is outdated”.

In the 2019 World Nuclear Industry Status Report, Mycle Schneider, who was the lead author of the report, said that nuclear power

“meets no technical or operational need that low-carbon competitors cannot meet better, cheaper and faster.”

A recent study by Good Energy and the Energy System Catapult demonstrated that carbon emissions from the power sector could be eliminated as early as 2030 without the need to develop new nuclear power. Sarah Darby, associate professor of the energy programme at Oxford University’s Environmental Change Institute, has said:

“Nuclear stations are particularly unsuited to meeting peak demand: they are so expensive to build that it makes no sense to use them only for short periods of time. Even if it were easy to adjust their output flexibly—which it isn’t—there doesn’t appear to be any business case for nuclear, whether large, small, ‘advanced’ or otherwise.”

It is clear that there is not a case for new nuclear—and, as my hon. Friend the Member for Edinburgh North and Leith (Deidre Brock) pointed out earlier, we have yet to address the nuclear waste issue. It will cost £132 billion to deal with the existing nuclear waste legacy. Why do we want to create another waste legacy for future generations to deal with?

So we do not need nuclear, and we do not need this Bill. Even if we consider what it aims to achieve, the fact remains that there is market failure, given that Hitachi has walked away from Wylfa and Oldbury and Toshiba has walked away from Moorside. So there is no competition to drive down cost, and EDF and China General Nuclear are still the only show in town. As the hon. Member for Southampton, Test (Dr Whitehead) asked, while the RAB model may might bring down costs, what protections are there in the event of project overruns?

Clause 2 puts all the powers of negotiation and contract award into the hands of the Secretary of State, and allows the Secretary of State to determine what is value for money. We all know how good the Government are at direct negotiations, so how can they guarantee value for money in a transparent manner?

As I touched on earlier, we have been told for five years that Hinkley is good value for money, but now the Government have come back to the House to say that actually that is not the case and they have a new plan for how to deliver nuclear. I therefore cannot possibly support this Bill, especially as the electorate of Scotland have consistently voted to elect a Government on a “no new nuclear” manifesto. Why should Scottish bill payers be forced to pay for nuclear energy that they do not want or require? This is another democratic deficit for Scotland, especially when so much of our renewable energy is not being supported at the moment and we are stuck with the highest grid charges in Europe. It really is time that Scotland had control of its own energy decisions, but in the meantime I will be proud and pleased to vote against this Bill.

--- Later in debate ---
Sarah Olney Portrait Sarah Olney (Richmond Park) (LD)
- Parliament Live - Hansard - - - Excerpts

Thank you, Mr Deputy Speaker, for the opportunity to speak in this debate.

If we did not already know that decarbonising our energy supply is one of the most urgent challenges facing not just this country but the whole world, the ongoing discussions in Glasgow at the COP26 summit have certainly informed us. There is now worldwide consensus on the need to phase out the use of coal and other fossil fuels in energy production, transport, heating and industry, and it is encouraging to hear some of the commitments made by delegates towards that goal. We have quite a good story to tell already on that in this country. In the UK, energy production accounts for approximately 15% of all carbon emissions. One significant challenge we face is how to replace the role of coal and fossil fuels in energy production with carbon-free alternatives, but we have already made great progress in decarbonising our energy supply. Carbon dioxide emissions from power stations were 75% lower in 2020 than in 1990, and this change has come about largely from the introduction of new energy sources, particularly renewables, such as wind and solar. The use of coal in our power supply fell sharply from the mid-2010s onwards, after which the use of renewables expanded rapidly. Wind power is now the cheapest form of electricity generation, and it was Government policy that made the substantial difference to this change, notably the decision of the then Secretary of State for Energy and Climate Change to introduce contracts for difference to incentivise private sector investment into the renewables sector. That Secretary of State was my right hon. Friend the Member for Kingston and Surbiton (Ed Davey), whom, I gather, went on to more exalted roles.

The legislation has strong precedents. Unlocking the barriers to private sector investment into carbon-free alternatives in our energy market has catalysed the changes we need to see. We need to go further to make sure that we can completely decarbonise our energy sector, supporting renewables and household and community energy.

Mark Jenkinson Portrait Mark Jenkinson
- Parliament Live - Hansard - -

Does the hon. Lady not prefer France’s decarbonised electricity model to Germany’s model of ever-increasing emissions and air pollution because of its decisions to close down nuclear power stations and go back to burning lignite, the dirtiest form of coal there is?

Sarah Olney Portrait Sarah Olney
- Hansard - - - Excerpts

My remarks are about the UK power sector, but I take the hon. Gentleman’s point about Germany. Clearly, as I think I have clearly stated, we want to move towards carbon-free alternatives to coal. I also want to make it clear that it is not our position that we should be closing down nuclear power stations; we support the ones that are currently operational and where contracts have been signed to open new ones. As I want to go on to make clear, our position is very much that there should not be new nuclear power stations. We need to go further to make sure that we can completely decarbonise our energy sector. We want to support renewables and household and community energy. It will create jobs. To pick up on the point made by the hon. Member for Morecambe and Lunesdale (David Morris) about jobs in the nuclear sector, let me say that the advantage of jobs in the renewables sector and in other alternative energy supplies is that they can be spread over a much larger area of the country. I believe he said that there are probably 18 viable sites for new nuclear power stations, many of which are concentrated in his part of the world. I am interested in job creation right across the country, and renewables offer much better opportunities for us on that.

Of course, we want to cut fossil fuel imports. On that basis, I strongly back the Government in what they are trying to achieve here, but not for nuclear. I wish to reiterate the Liberal Democrat position: there is currently no economic or environmental case for the construction of any further nuclear stations in the UK. The hon. Member for Kilmarnock and Loudoun (Alan Brown) set out, in his extensive and detailed speech, very much what we believe: there really is not a case for such construction.

A further point I wish to make is that it will take 20 years to build a new nuclear power station, however it is funded. We have very ambitious net zero targets. As the Minister said, we want to be net zero in our power sector by 2030, which is much sooner than in 20 years. We need to move considerably faster than that, and we already have the tools and technology to cut carbon significantly in our power sector in a much shorter period, so we need to accelerate the deployment of renewable power. We need to remove restrictions on solar and wind. We need to build more interconnectors to guarantee the security of supply. If we did that, we could reach at least 80% renewable electricity by 2030, which would be consistent with the Government’s aims to achieve net zero.

Notwithstanding the points made by other Members about the growth in demand for electricity from electric cars, we can do much more to reduce demand for electricity from existing sources.

--- Later in debate ---
Chris Green Portrait Chris Green
- Hansard - - - Excerpts

I am concerned about the strategic national interest, but I think that most people at home would need to have reassurance on this: the security risk of the technical aspects, to which people might be more sensitive, is different from the financial aspects, which is what the Chinese involvement is at the moment. Those are two very different things. However, I do acknowledge the hon. Gentleman’s concerns.

Mark Jenkinson Portrait Mark Jenkinson
- Hansard - -

On security, the Office for Nuclear Regulation is considered to be one of the best nuclear regulators in the world. I certainly have faith in its being able to do its job, but is not the reason why state-backed companies are involved in nuclear construction that they have the money to put in up front? Is not this legislation exactly what we need to remove the need for them to be involved?

Chris Green Portrait Chris Green
- Hansard - - - Excerpts

I agree entirely that there are huge challenges for the private sector to come up with the cash for the nuclear sector, because of providing the money up front; it takes such a long time to build a power station before energy or electricity can be produced, and people can get returns for their money. That is why the regulated asset-based model is key. It has been used in other areas successfully, so it is now seen as a reliable way of financing large projects.

Now is the time to make progress in this area. We have the skills base, the national need and the national security questions. All these things come together at the same time to make a compelling argument, so I am pleased that the Government are bringing this legislation forward, whether it is for the larger-scale nuclear reactors or the smaller-scale nuclear reactors. Let me finally say to my hon. Friend the Minister—I know that he has an interest in this—that, in the slightly longer term, if we do develop the fusion reactors, perhaps this funding model could be used there.