Commons ChamberI beg to move,
That this House takes note of and approves the National Policy Statement for Waste Water, which was laid before this House on 9 February.
The waste water national policy statement sets out Government policy for the provision of waste water infrastructure of national significance in England. It will be used from this April by the Planning Inspectorate, as the examining body, and by the Secretary of State, as the decision maker, as the primary basis for making decisions on development consent for nationally significant infrastructure projects.
Consultation on the waste water national policy statement took place between November 2010 and February 2011. At the same time, it was subject to parliamentary scrutiny. The Select Committee on Environment, Food and Rural Affairs undertook scrutiny for the House by holding oral hearings and taking written evidence. It published a report of its findings in April 2011, with 19 recommendations and conclusions, to which the Government responded in February 2012.
I would like to take this opportunity to thank the Select Committee, nobly and expertly chaired by my hon. Friend the Member for Thirsk and Malton (Miss McIntosh), for its hard work and for its determination to get to grips with a subject area that was new to some Committee members and, at the time when I gave evidence, relatively new to me. I am grateful to the Committee for scrutinising the national policy statement in a relatively short period. I hope that it can see that its contribution has helped to refine and improve the document before the House.
The Minister is being his usual modest self in saying that he was not au fait with the subject. He is now up to his knees, if not his waist, in the subject, having dealt with the Water Industry (Financial Assistance) Bill last week and in introducing this debate. I believe that the Select Committee had some doubt about major projects being included in the NPS. For the avoidance of doubt, are the Government unshaken in their view that projects such as the Thames tunnel and Deephams sewage works should be included in the NPS? Whatever the final decision on the route and the detail, it is important to be clear—[Interruption.]
Order. I will make the judgments about the length of interventions, thank you. We want short interventions. I presume that the hon. Gentleman has got to the end of his.
I think I got the gist of it. I will come on to cover the key points that were made by the Environment, Food and Rural Affairs Committee and to explain what the waste water national policy statement is. I think that I will address the hon. Gentleman’s points, but I am happy to let him intervene again.
In laying the waste water national policy statement before the House for approval and in having this debate, we are meeting a Government commitment to mirror the new requirements of the Planning Act 2008 that will be brought into effect next month under the Localism Act 2011. Those procedures are intended to make national policy statements more democratically accountable to Parliament.
The Government are committed to making the planning system more open, transparent and fast, and to ensuring that all those who want to get involved in the process can do so, whether it relates to an application to extend a property or to a project of national significance, such as the Thames tunnel. The abolition of the Infrastructure Planning Commission brings democratic accountability back into the determination of nationally significant infrastructure projects by giving decision-making powers back to Ministers, who are answerable to Parliament. Ministers will also have regard to recommendations made by the Planning Inspectorate.
National policy statements are a key component of a more open and accountable planning system. They will set out Government policy clearly on particular types of infrastructure of national significance, having been subject in draft form to both formal consultation and parliamentary scrutiny. National policy statements provide a framework for preparing, considering and deciding development consent applications. This national policy statement is therefore primarily for planning purposes and does not claim to be a complete statement of Government policy on waste water.
Effective waste water infrastructure is vital, because without suitable treatment, the waste water we produce every day would damage the water environment and create problems for public health, water resources and wildlife. The proper collection, treatment and discharge of waste water, and the correct disposal of the resulting sludge, helps to protect, maintain and improve water quality in the UK.
The criterion that we have used in the national policy statement for the demonstration of the need for nationally significant infrastructure projects is that the projects have been included in the Environment Agency’s national environment programme. The Environment, Food and Rural Affairs Committee recommended that that issue needed to be clarified and I believe that our approach now addresses its concerns.
In addition to establishing the need for waste water infrastructure, our national policy statement sets out impacts that will be relevant for any waste water infrastructure, including details on mitigating adverse impacts. Those are issues that the Planning Inspectorate and Ministers will have to have regard to when examining and determining applications.
The national policy statement does not describe how any waste water projects of national significance should be developed. I think that this addresses in part the point made by the hon. Member for Hammersmith (Mr Slaughter). How such projects are developed is up to the project promoter before they place an application for development consent, which from April this year will go to the Planning Inspectorate.
The waste water national policy statement details two proposed projects of national significance: the sewage treatment works scheme at Deephams in north-east London and the Thames tunnel. The justification for both developments and the consideration of alternatives to the Thames tunnel are fully explained in the document.
Currently, only the proposed upgrade of the Deephams sewage treatment works can be considered a potential nationally significant infrastructure project, as it meets the criteria in the Planning Act 2008 for waste water treatment facilities serving a population equivalent of 500,000 people. We will shortly lay a draft order before Parliament for its approval, to amend section 14 of that Act to enable a waste water transfer and storage project such as the Thames tunnel to be classed as a nationally significant infrastructure project.
London’s sewerage is under considerable pressure, due to a system that is close to capacity, changing land use in London and population expansion. That leads to frequent spills of untreated waste water containing sewage into the tidal reaches of the Thames, which has a negative impact on its water quality. Resolving that problem has been the subject of extensive and comprehensive studies, including the consideration of a wide range of alternative solutions, for more than a decade. As a result, the Government are satisfied that the development of the Thames tunnel, when compared with the alternatives, is the most cost-effective and timely solution to the problem of untreated sewage discharging into the River Thames. That is demonstrated in the waste water national policy statement.
One of the arguments that the Minister has just made is that the proposed tunnel is the most cost-effective way of dealing with the problems in the Thames. Can he point me to any cost-benefit analysis that has happened in the last couple of years, since the initial study was made in 2006 and since the cost of the project has risen from £1.7 billion or thereabouts to £4.1 billion?
Like my right hon. Friend, I am concerned about the cost of the project. That is why my Department has instructed Ernst and Young to advise it in detail on the cost-benefit analyses that have been carried out to date, recognising, of course, that not far off a quarter of the estimated price is a contingency. It is important that throughout the process we are open about the figures that are arrived at. These matters concern not just his constituents and those of other London Members but 144 Members whose constituents pay Thames Water bills, of whom I am one.
I can assure my right hon. Friend that, as I said in last week’s debate, Ministers remain healthily sceptical about the cost of the project. We want to ensure that it provides value for money, and I am happy to tell him that cost-benefit analysis will be an ongoing process. I assure him that the alternatives that we have examined, which may be more attractive on the face of it, such as retrofitting sustainable urban drainage systems across London or separating clean water from dirty, cannot compare favourably with the cost of the tunnel. Indeed, one of the options that I have seen would come in at somewhere between three and four times the cost of the Thames tunnel scheme. I take the matter very seriously and will be happy to keep him informed of our progress.
One concern about both the development at Deephams and the Thames tunnel is the role of Ofwat. There is concern that Ofwat’s attention may be somewhat too concentrated on the Thames tunnel, for all the good reasons that we have discussed, and that it may not give sufficient priority to Deephams. Can the Minister reassure us that that will not be allowed to happen?
I can assure the hon. Gentleman that that is a matter of great importance to Ofwat. It has agreed funding to progress the Deephams upgrade, which will increase treatment capacity to accommodate the expected growth. I am convinced that Ofwat is taking the project seriously, but I am happy to write to him with more details. I think it would strenuously deny that it is looking myopically at the Thames tunnel, to the exclusion of Deephams. Of course, it is perfectly in order for him to contact Ofwat, because it is the independent economic regulator of these matters.
We made statements to the House about the Thames tunnel in November 2011, accompanied by documents setting out what we believe is the irrefutable case that it is the correct scheme for our capital city. To address the hon. Gentleman’s concern, I point out that although improvements to the Deephams sewage treatment works may have received less public attention over the years, they are on a large scale. The current site covers about 30 hectares and is the ninth largest sewage treatment works in England.
The improvements are essential to ensure that environmental quality standards in the waterways into which the treatment works discharge meet European and national standards. As the developer, Thames Water, is still evaluating the site and treatment options prior to selecting a preferred option for development, the waste water national policy statement does not consider alternative options. It will be for Thames Water to justify its preferred option in its development consent application.
The national policy statement, as with planning policy documents in general, does not prescribe the use of specific technologies. That is to ensure that developers are not fettered by the Government from taking account of future technological advancements. It is up to the developer to justify in its application its preferred treatment option, including any options it has considered and ruled out.
Although the national policy statement details two potential nationally significant infrastructure projects, may I stress that we are not here to debate how those schemes may be delivered? Our purpose is to discuss whether the national policy statement fulfils its requirements under the 2008 Act, and therefore whether it is fit for purpose. Designation of this national policy statement is not the last opportunity for people to have their say on development consent applications for waste water infrastructure of national importance. Developers must consult local communities before submitting an application to the Planning Inspectorate, and people will have the chance to have their say during the examination by registering and making representations to the Planning Inspectorate.
The waste water national policy statement is critical in helping to deliver important infrastructure developments and in ensuring that the right framework is used in the consideration of development consent applications. I strongly believe that the waste water national policy statement provides robust justification for the new infrastructure proposed. I welcome the debate and look forward to responding, with the leave of the House, to the points raised in it.
With the leave of the House, I will respond to the points raised in the debate. I apologise if my response is hurried and does not deal with points in the order in which they were raised.
Important points have been raised in this debate. I concede that this is a serious matter, particularly the Thames tunnel element of it. I share many of the concerns expressed by my right hon. Friend the Member for Bermondsey and Old Southwark (Simon Hughes) and my hon. Friend the Member for Cities of London and Westminster (Mark Field). I repeat my earlier assurance to them: I do not enter this matter with blind disregard to the impact that it will have on their constituents and mine, including in the construction phase. Many hon. Members who have spoken on previous occasions are rightly concerned about the impact of the project and its construction. I assure hon. Members that I remain willing to be engaged. Let us not pretend that this is the last occasion on which this scheme or other such schemes will be debated in the House. There will be opportunities to raise these issues in the House and I remain willing to be held accountable.
Essentially, those of us in government are all laymen, unless we are lucky enough to have a specific engineering skill. I do not have banking experience or engineering experience of large projects, so I seek to get it. I am gifted with a good team supporting me in the Department, but I can assure Members that these schemes, particularly the Thames tideway, are rightly matters of concern not just to my Department but right across Government, and to agencies such as the Environment Agency and Ofwat.
Recommendation 9 in the Environment, Food and Rural Affairs Committee’s report was very important. It suggested a serious look at how Ofwat saw the Thames tunnel. The Government’s response, which I will not repeat, set out clearly that Ofwat accepted without reservation the Committee’s recommendation that it must make full use of its regulatory powers
“to scrutinise the economic case for the Thames Tunnel project and be rigorous in determining which costs should be passed on to Thames Water customers.”
I know that Ofwat would want me to continue to provide assurances about that.
My hon. Friend the Member for Cities of London and Westminster commented on the risk of infraction of the urban waste water treatment directive. I remind the House that the UK is already in the European Court of Justice with respect to the combined sewer outflows into the Thames, so far from there being a risk of gold-plating, there is a risk that the Court will find that we are doing too little. We await its judgment later this year, but I would be surprised if it came to the conclusion that the Thames tunnel was not required.
My right hon. Friend the Member for Bermondsey and Old Southwark mentioned cost-benefit analysis. There was an analysis in December 2011 to support the ministerial statement, and it took account of the increased costs of the project. As I said earlier, I assure him that we are examining the matter rigorously with advice from Ernst and Young and others, and will continue to do so. We will reassure the House of our assessment from time to time. As I said, Ministers will remain sceptical about the cost of the project, and we will drill down to ensure that we deal with it as well as possible.
The hon. Member for Luton South (Gavin Shuker) spoke in support of what the Government are seeking to do, and he made a number of points. He mentioned the definition of sustainable development. On page 9 of the Government’s framework document, in paragraph 2.2.3, the Government’s key policy objectives are set out, and a definition is given of sustainable development in relation to the national policy statement. We will also shortly publish the national planning policy framework, which my hon. Friend the Member for Thirsk and Malton (Miss McIntosh) mentioned. That, too, will set out the Government’s definition, moving forward from that of the Brundtland commission. The Environmental Audit Committee has done some work on the development of that definition, and I hope that there is general agreement about it throughout the House.
The hon. Member for Luton South mentioned the green deal, which of course has a blue element—hot water. I entirely share his ambition that the Government should examine the success that I am sure there will be in the green deal and see whether we can retrofit water-saving measures into households. There is a whole range of ways to do that. I refer him to our green infrastructure partnership, which is overseeing the retrofitting of large sustainable drainage systems into developments and which we hope will be a real success. He also made a point about energy recovery, and my noble Friend Lord Taylor is liaising with the Department of Energy and Climate Change on that important matter.
My hon. Friend the Member for Thirsk and Malton, the Chairman of the Environment, Food and Rural Affairs Committee, mentioned the cost of the Thames tunnel and also talked about the consultation on the national policy statement. It lasted 14 weeks and was considered to be within the scope of the Planning Act 2008, and stakeholders were contacted. I am sure the House will continue to consider better ways of consulting people. When consultations have passed, we always discover that some stakeholders and groups feel that they have not been involved. We must seek to do better, and I know that the House will continue to work on that, including through the Select Committee process.
My hon. Friend and other hon. Members asked why we are not establishing a red line on costs for the Thames tunnel project. As I have said, we are working across Government, with Ofwat, Infrastructure UK and Thames Water, to ensure that the Thames tunnel represents proper value for money, that the engineering costs of the tunnel are minimised, and that the project is delivered efficiently, with a structure and financing mechanism that delivers value for money for those who will pay for it.
My hon. Friend also raised the question of SUDS, which was no surprise to me or any other hon. Member—it is an important point. The Government’s intention is to implement the SUDS measures as soon as possible. Implementation dates are being explored in the consultation. Our initial proposal is to commence in October 2012, and during consultation we are seeking feedback on the feasibility of that date for those affected, including developers and local authorities. During the consultation period, officials have been working on a series of additional consultation events, including workshops around the country for local authorities on their capacity to deliver the SUDS requirements.
The hon. Member for Edmonton (Mr Love) raises, with his usual vigour, his concerns for his constituents. There is not time to go into them in detail, but I assure him that I will meet him and his constituents to ensure that we address the points he raises. Thames Water recognises that the odour at Deephams is a key issue for local stakeholders and is working with the Environment Agency, the Department for Environment, Food and Rural Affairs, Ofwat and local authorities. It can mitigate the problem to a degree. Options include covering and controlling odorous air from primary treatment plants.
The national policy statement requires all waste water treatment infrastructure projects of national significance examined by the Planning Inspectorate to include an appropriate odour impact assessment as part of the environmental statement. The applicant should assess that potential, so I hope the hon. Gentleman’s constituents will be living in a slightly more favourable environment in future.
My hon. Friend the Member for Cities of London and Westminster asked how much pollution is in our river at the moment. We must produce more evidence to satisfy him, but the fact is that there are 50 to 60 overflows from combined sewage overflows every year. That is set to increase. An element of that is being dealt with by the Lee Valley project, but another 18 million tonnes is flowing through our river, in one of the most important cities in the world. Yes, we require caution on cost, but we also require a resolute approach to deal with that.
Discharge events are increasing, and we know that only 2 mm of rain results in a combined sewage overflow. My hon. Friend is absolutely right that that will not change the colour of our river. Londoners and any visitor to this great city will stand on our bridges and see no demonstrable change in the colour of the river, but most people recognise that a bubbler system, which has worked well in Cardiff harbour, which is of course a lagoon rather than a tidal river, will not resolve the problem. Professor Binnie, who has been prayed in aid on all sides of the argument, seems to have come down on the same side that the Government reluctantly came down on, and concluded that the scheme should go ahead. He was right to do so.
I apologise to hon. Members if I have not been able to answer all their points, but this important debate is ongoing, and I commend the statement to the House.
Question put and agreed to.
Resolved,
That this House takes note of and approves the National Policy Statement for Waste Water, which was laid before this House on 9 February.