New Pylons: East Anglia

Jerome Mayhew Excerpts
Tuesday 19th July 2022

(1 year, 9 months ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Jerome Mayhew Portrait Jerome Mayhew (Broadland) (Con)
- Hansard - -

I am glad to lend my support to the arguments of many MPs whose constituencies are directly affected by the proposed pylon route of East Anglia GREEN. I represent the constituency of Broadland in Norfolk, which is not directly affected. The run starts at Dunston in south Norfolk, just south of Norwich, heads through Suffolk and into Essex. The reason I wanted to join the debate is to question the rationale for reinforcing the transmission network from Norwich south in the first place.

The consultation, which has already been much criticised and will be by other contributors, starts with the assumption that there is a problem that needs to be solved. That problem is additional power being applied to the network at Dunston, at Norwich south. The power comes from offshore wind farms, both those connected in the past five years, since the previous review by Ofgem in 2015, and the huge number of additional wind farms anticipated between now and 2030, and thereafter.

We know from last year’s National Grid ESO report of an anticipated 17 GW of offshore wind constructed in the southern North sea alone—part of the 50 GW by 2030 ambition—but there is a problem. Although we won the argument for a holistic network design leading to an offshore transmission network, with the Secretary of State making that announcement on the Floor of the House, we appear to have lost the battle when it comes to East Anglia. The holistic network design comes into force from 2030 onwards, we are told, yet the connections for East Anglia affect our counties between now and 2030. It is between now and 2030 that the 17 GW will be constructed and connected.

We have here the most classic example of putting the cart before the horse. Much better would be to look again at the design for East Anglian connection, follow the advice of the National Grid ESO report, which was referred to by my hon. Friend the Member for South Norfolk (Mr Bacon), and create an offshore transmission network. Accelerate it; do not accept the argument that it can be put in place only by 2030 and push for 2025. If we do that, on its own estimates, there are £6 billion of savings to be made: £3 billion in reduced capital expenditure, because it is much easier for a wind farm to connect to a grid that is already offshore, and £3 billion of further operating savings between now and 2050.

Richard Bacon Portrait Mr Bacon
- Hansard - - - Excerpts

Does my hon. Friend share my concern that, with this enormous extra offshore capacity that is coming, if we do not follow his suggestion of an offshore grid as soon as possible, which is Government policy, we could be faced with the current nightmare being duplicated or triplicated? In a few years it could be said, “Well, actually the pylons we installed a few years ago are not efficient, so we need even more pylons.” How lunatic would that be?

Jerome Mayhew Portrait Jerome Mayhew
- Hansard - -

Of course, Ofgem would say, “Well, we’ve done the calculations. We know that there isn’t going to be any more offshore wind, and we think this is going to be enough.” But in 2015, when it last looked at this subject and was asked to assess whether an offshore transition network would provide value for the money to the consumer, its advice to the Government was, “No, it would not, because we will never have enough offshore wind to justify it.” Well, how wrong it was. Just seven years later, here we are bitterly ruing that short-sighted failure to make anticipatory infrastructure decisions. We could have avoided all these arguments and be leading Europe in the development of this innovative design, which now is absolutely technically possible. In fact, I have spoken, with others, to the managing director of Hitachi, who told us that this is off-the-shelf technology now.

We come back to the consultation, which has just been closed, and the position of the regulators and National Grid. Their argument is essentially that it is too late to change the decision about connection points. We already have radial connections coming into Norfolk. Given that the power is being delivered to south Norfolk, the network has to be reinforced to draw the electricity south, hence East Anglia GREEN and 112 miles of pylons. However, I invite the Minister to take a step back and look at the rationale behind the decision to write contracts to allow the offshore wind farms to connect to Norwich south. All those offers must have been subject to planning permission, because the regulator knew, or ought to have known, that the connection point did not have sufficient capacity to deal with the anticipated measures.

James Cartlidge Portrait James Cartlidge
- Hansard - - - Excerpts

My hon. Friend is making an excellent, highly technical and very important speech. Is it not true that in our recent discussions with Ofgem, National Grid and others that officials from the Department for Business, Energy and Industrial Strategy confirmed on the call that none of the current contracts could in any way predetermine the planning application? Therefore, the question of how the electricity is ultimately shifted through the onshore grid is still open.

Jerome Mayhew Portrait Jerome Mayhew
- Hansard - -

My hon. Friend is absolutely right. As a question of law, it must be open because it is subject to planning.

The Minister has a great opportunity not to make the errors that we made in 2015 and to be bold about the anticipatory infrastructure that is required, which is being implemented for the holistic network design elsewhere in the country. It is ironic that the only part of the country that is not part of the holistic network design is East Anglia, given that East Anglian MPs pushed the Government into adopting the policy.

We have an opportunity to create the infrastructure that will allow us to connect without more devastating impacts on our environment and communities; to save money in the medium term, as pointed out by the National Grid ESO position paper; and to accelerate the early adoption of additional wind farms, because once the offshore transmission network in place, the connection process will actually be quicker and easier. Additionally, if we take the offshore route via “Sea Link 2” down to the Isle of Grain, there will potentially be additional benefits in relation to international interconnectors.

I question the rationale behind the assumptions that went into the consultation paper, and I make this one further request. In the very constructive call that a number of us had with National Grid Electricity Transmission Operator yesterday, it committed to generating a like-for-like offshore replacement for East Anglia GREEN, but I have one concern about that. If we literally have a like-for-like replacement, we would be taking energy from Norwich South to Tilbury. That is not the question that should be asked. The question that should be asked is what is the cost of taking advantage of an offshore route to deliver electricity to the Greater London area? It is not an exact like-for-like comparison with Dunstan in south Norfolk to Tilbury. How do we take advantage of the benefits that National Grid ESO identified in its position paper to maximise the dynamism of our electricity provision while minimising the cost to the taxpayer and to the constituents of our three counties?