(6 years, 4 months ago)
Commons ChamberUrgent Questions are proposed each morning by backbench MPs, and up to two may be selected each day by the Speaker. Chosen Urgent Questions are announced 30 minutes before Parliament sits each day.
Each Urgent Question requires a Government Minister to give a response on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
My hon. and gallant Friend strikes the nail on the head. He is absolutely right that this decision will be damaging for the capabilities of the whole of Europe. In view of the Prime Minister’s statement on our willingness to co-operate on security issues, the situation that we are now facing is genuinely disappointing. Again, he highlights the fact that we have the capability, skills and expertise to develop our own system if that is what we have to do.
I declare an interest as a trustee of the Royal Observatory in Edinburgh. The Government have said in response to a written question:
“In the long term, we believe that”
a British global navigation satellite
“system could be operated for around the same annual cost as the UK’s current contribution to the EU’s Galileo programme.”
Could the Minister tell us: what are the short-term costs?
The written answer highlights the fact that our current contribution is about £200 million a year. The total billed cost would be estimated at about £4 billion. So in the short term we still want to ensure that we have an involvement with Galileo: that is still our aim. The Prime Minister will take this issue up, and it is clearly important that she does so. It should be noted that, thus far, every single satellite utilised within the Galileo system has been built in the UK, so I wonder whether this urgent question should be taken in every other Parliament in Europe as a result of the decision taken yesterday.
(7 years, 10 months ago)
Commons ChamberThe Secretary of State continues to use the word “allegation”, but this is no longer an allegation—it is a proven fact that a British cluster bomb has been used in the conflict in Yemen. Given that it has taken seven months for the Saudi Arabian authorities to, in his words, be “transparent”, is he honestly saying that the Government’s sanction on Saudi Arabia is merely to accept its reassurance?
The hon. Gentleman is right that from today we should probably describe this as a fact rather than an allegation. I was calling it an allegation because that is what it was when it was first brought before this House back in May, but now we have the confirmation from Saudi Arabia that coalition aircraft did drop one of these cluster munitions around the turn of the year. As far as sanctions are concerned, it is this country, as I have said, that has pressed for all these allegations—some of them are still allegations—to be properly investigated, for the findings to be published and, where necessary, for evidence to be provided by the Saudi coalition authorities that changes have been made in their command-and-control, rules-of-engagement or targeting procedures. Those are the results that we want to see.
(8 years ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
The hon. Gentleman may say that, and I may come on to that point, but the Government have never confirmed that that is the reason for the delay, and it would be useful if they were to say that today. If he is correct that there was a lack of money, I am sure that there are Committees and hon. Members in the House who would want to ask what happened with the money.
Lord West suggested to the Defence Committee that the defence budget for shipbuilding was spent. In answer to a question from my hon. Friend the Member for Dunfermline and West Fife (Douglas Chapman), he said:
“Shall I tell you what the problem is? Notwithstanding having said how much extra money there is for defence, in the near years there is not. There is almost no extra money available this year, and we are really strapped next year. The Government aren’t coming clean about that. I think if they did, people would understand.”
In answer to further questions, he outlined that delays can be costly in the long run. In response to the Chair of the Committee, he said:
“Every delay costs you money. These delays all cost money. You need a steady drumbeat of orders to keep high-tech industries going. Our complex surface warship building industry, like the submarine one, needs a steady drumbeat of orders.”
My hon. Friend talks about the drumbeat and the starting point for the project. Is it not one of the key concerns that, even when the project starts, if the drumbeat is extended and the length of time for the completion of each ship is extended, by the nature of that equation, fewer workers will be needed?
That concern is felt not only by my hon. Friends, but by me and, crucially, the trade unions and workforce on the Clyde. What economic impact assessment has been carried out on delaying the Type 26 frigates? We know from an excellent report by the Fraser of Allander Institute, which was commissioned by GMB Scotland, that the two BAE yards at Govan and Scotstoun directly employ a total of 2,723 people. More than 1,000 of them, men and women, are skilled tradespersons. I am delighted that there has been an increase in women apprentices and women workers highly involved in high-tech industry. The report estimates that the two yards in Glasgow support a total of 5,943 jobs and, through that, £162.7 million of wages across Scotland as a whole. Returning to my original “eight plus five” question, will the Minister confirm whether the general purpose frigates will also be built on the Clyde, as confirmed by the former Prime Minister in the strategic defence and security review in November 2015?
We know that a national shipbuilding strategy will be announced soon. I am looking forward to that, when it comes, but I reiterate that we should not underestimate the frustrations of the workforce. They want to build ships. They want a long-term future for the Clyde that will begin with cutting steel for Type 26 frigates. I look forward to the Minister’s response to my questions.
My hon. Friend is absolutely correct. It is one of many broken promises that I am sure will not be forgotten.
I will. I thought the hon. Gentleman might want to intervene on this point.
I am sorry that the cross-party consensus on such an important issue has been so inelegantly broken, but will the hon. Gentleman tell the House how many frigates would have been built had people voted yes in 2014?
Had the hon. Gentleman been in his place at the start of the debate, he would have seen that there was cross-party consensus. We were being very consensual. The Scottish people and the Scottish workforce have been betrayed by the Government. The hon. Gentleman would do well to focus on the Government and their betrayal, rather than attacking people who are defending Scottish workers.
With the old Type 23 frigates being withdrawn from service in 2023, the Type 26 programme had to start in early 2015, but the manufacturing of the eight ships will now not begin until the summer of 2017 at the earliest, with at least one union convener saying that it will not begin until 2018. That is a delay of at least two years, and possibly three. As we have heard, the lesson from all defence procurement deals is that if there are delays, costs will always increase.
What is the reason for the delay? Is it that the Government think that we no longer need Type 26s? That is not the case. As Peter Roberts, a senior research fellow at the Royal United Service Institute, said, the Government are talking about
“a level of Russian submarine activity that we have not seen since the 1980s…That poses a significant threat for the UK”.
If the delay is not on the grounds of national security, and it is not a strategic decision, it can only be based on cost. Perhaps Lord West of Spithead, the former First Sea Lord, was absolutely right when he said that
“there is not enough money in the MOD”
to start construction. He said that before Brexit, and he could say it with bells on now.
Despite the Minister’s protestations that the
“national shipbuilding strategy…is not something that is affected by the outcome of the referendum”,
we all know that if prices are denominated in dollars, costs will soar.
When the Secretary of State for Defence came to the House on 27 June—the first day the House sat after the EU referendum—he said that he was
“not prepared to sign a contract with BAE Systems until I am absolutely persuaded that it is in the best interests of the taxpayer”.—[Official Report, 12 September 2016; Vol. 614, c. 592.]
Are we to assume that that was mere coincidence? The hon. and gallant Member for Beckenham (Bob Stewart) got it absolutely right when he said that the project has been delayed because the Government have run out of money. They have run out of money because they have committed far too much of their procurement budget to Trident. It would be an unforgivable betrayal of the Clyde workers if they were the ones who had to pay not only the price of Brexit, but the price of Trident, which has been ring-fenced within defence procurement. Once again, it appears that the Government are prepared to sacrifice our conventional defence capabilities to their obsession with Trident and nuclear weapons. I look forward to the Minister letting me know about that.
If there is not a lack of will and there is sufficient money, prove us wrong and give us a start date. The workers on the Clyde have had far too many broken promises. An important supply chain is at risk in the defence manufacturing sector. We need confirmation that the five general purpose frigates will also be built on the Clyde. I would appreciate it if the Minister addressed that point in her remarks. The work needs to start now. The workers on the Clyde have been betrayed too often. Will the Minister break that chain of betrayal and let-down? Give us a date for when work on the Type 26 programme will start.
(8 years, 4 months ago)
Commons ChamberI should maybe come to questions more often.
A former First Sea Lord told the Defence Committee that the delay in the Type 26 frigate programme was due to money problems in the Ministry of Defence budget. Will the Minister tell the House, and more importantly tell the workers on the Clyde, how many jobs will be lost and what the impact will be on its world-class apprenticeship programme?
(12 years, 3 months ago)
Commons ChamberUrgent Questions are proposed each morning by backbench MPs, and up to two may be selected each day by the Speaker. Chosen Urgent Questions are announced 30 minutes before Parliament sits each day.
Each Urgent Question requires a Government Minister to give a response on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
My hon. Friend makes a good point. Even under the proposed model, we will continue to have quite a lot of military personnel inside DE&S, which it needs to give it insight into the user requirement. I agree with my hon. Friend that short rotations have not served DE&S well. It would be to the benefit of both the individuals and the organisation if postings were for longer periods.
Thousands of jobs in Edinburgh rely on companies such as SELEX Galileo. What relationship will the new body have with such private sector companies?
(13 years, 10 months ago)
Commons Chamber1. What assessment he has made of the capacity of the Afghan national security forces to assume responsibility for the security of Afghanistan by 2015; and if he will make a statement.
Assessments of the Afghan national security forces are regularly carried out by the NATO training mission in Afghanistan, of which UK forces form an important part. There are currently around 144,000 Afghan national army personnel and around 116,000 Afghan national police. The October 2010 targets were exceeded two months ahead of schedule and we assess that the growth in both capacity and capability of the Afghan forces is on track to meet the target of transferring lead responsibility for security to the Afghans by the end of 2014.
When in Afghanistan, the Prime Minister said he was confident that troops could begin to return home in 2011, but the Chief of the Defence Staff has said that we will not “cut and run”, and the Defence Secretary has said that we will be there for as long as it takes. That causes confusion and could make the situation in Afghanistan worse, and it causes a great deal of uncertainty for both our troops and their families. Will the Secretary of State categorically state whether UK troops will begin to depart from Afghanistan in 2011?
The Prime Minister made it clear on his visit to Afghanistan, as the Chief of the Defence Staff and I have done, that if conditions allow, we may be able to see a reduction in 2011 of some UK forces. We may also decide to use UK forces in a different way, particular in more of a training mission, but that will depend on what happens on the ground next year.