Helen Jones
Main Page: Helen Jones (Labour - Warrington North)Department Debates - View all Helen Jones's debates with the Department for Transport
(9 years, 8 months ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
I congratulate the right hon. Member for Chesham and Amersham (Mrs Gillan) on securing this debate. In the short time available to me, I will focus on an issue of great concern to my constituents. The Hoo Green to Bamfurlong spur would be the whitest of white elephants. Building it would destroy two villages in my constituency, Culcheth and Hollins Green, and inflict serious environemtnal damage.
The case for the spur has now been seriously undermined. The spur results from a perverse decision to join the west coast main line north of Warrington, rather than north of Crewe. The original cost of the spur was estimated to be £800 million, which has now risen to £1 billion. HS2 justified that cost, as opposed to the £750 million original estimate for joining the west coast main line south of Warrington, on the grounds that it would otherwise have to do a great deal of work to Crewe station. That has now fallen apart because, after the Government accepted the recommendations of the Higgins report, Crewe will now be the main transport hub for the area.
There is no justification for not joining the main line near Crewe. The costings given for that were, to say the very least, dubious. The average cost works out at £22.9 million a kilometre. That sounds a lot, but it is only 28.6% of the cost of building the line elsewhere, which includes building a huge viaduct over the Manchester ship canal, bridges over the motorways and big embankments running through the village of Hollins Green. The costings simply do not stack up.
The second part of the case against the spur is the economic damage that would be caused to the villages of Hollins Green and Culcheth. The line would destroy a business park just outside Culcheth, with the loss of 500 jobs. The knock-on effect would mean that the village of Culcheth and all its businesses not only lose business from those people but lose outside trade because three of the four main routes into the village would be closed during construction, possibly causing many businesses to fold. Culcheth is a large village that relies on trade from outside coming into its shops and restaurants.
Similarly, a viaduct on Hollins Green would bisect the ancient parish of Rixton-with-Glazebrook and destroy businesses in the area, and the prospect has blighted homes, yet the Government cannot give us the figures. In other words, the economic case is being made without making the case for the damage caused to the economy elsewhere. Warrington will not benefit from this part of the line because it will not get a station. Nor is there a knock-on effect elsewhere in the constituency, which, as one gentleman said to me, might have justified what is happening. We have the pain, but we do not have the gain. In fact, we would probably end up with a worse service from Warrington than we have now, given that we already have one train an hour to London and one train an hour to Glasgow. We can get to London in just under two hours on a direct train.
I say to the Minister that the case does not stack up. The Government have not looked at the whole economic benefit, and they need to save £1 billion of public money by abandoning the spur.
I should add, Mr Betts, that the people who have been making those preposterous estimates, coming up with ludicrous proposals that will not work, are all very well-rewarded consultants. I believe that they have already had three quarters of a billion pounds in fees, so hard-working consultants are doing rather well. As far as I can see, the only train that has actually moved is the consultancy gravy train.
I advise people that if we want to benefit the cities of the north, the answer is to invest in the cities of the north and their immediate transport requirements, rather than spending what it is now believed will be £7 billion on a full-scale development of Euston. Will Sheffield, Leeds or Manchester benefit from an investment of £7 billion in Euston? Euston certainly will not benefit, and I do not think anywhere else will.
On a point of order, Mr Betts. Would it be possible at this point, as this is possibly my right hon. Friend’s last speech in the House, to record our appreciation of his service over many years, particularly to his constituents, and his devoted service to the national health service, from which we have all benefited?
Of course, that is not a point of order for the Chair, but the Chair’s inability to comment on it should not be taken as disagreement with it.
I will not give way because I have very limited time; I am sorry.
It is sometimes said that we should just upgrade what we have, and of course we need to invest in the existing network, but the delayed and over-budget Great Western works are showing just how difficult such upgrading can be in practice. Opponents of HS2 are rightly concerned about costs and it is vital that taxpayers get the best value for their investment, so it should be a great concern to us all that the estimated cost of electrifying the Great Western main line has more than trebled, from £540 million in 2011 to more than £1.7 billion today, and the price is still rising. As Lord Adonis has said, it is like performing open heart surgery on a Victorian railway. Let there be no mistake: tracks may have been relayed and signals may have been upgraded since the Victorian railways were put down, but almost all our alignments are inherited from an age of slower traction, and almost 200 years later they have given us compromises.
It may be asked, “What is the alternative to HS2?” The truth is that the alternative, if it can be called that, is to prioritise the needs of one passenger against another. It is to make fast trains compete with commuter and freight services, and to spend even greater sums to extract diminishing returns from our eccentric and increasingly sclerotic network. To my mind, that is no alternative at all. It would lead to a meaner, less socially accessible and more London-centric railway. We urgently need new capacity and HS2 is the right project to provide it.
A number of concerns have been raised, both outside and inside this House. Much has been said about the project’s costs and it is certainly true that there was a loss of focus on costs after the election. That is why Labour successfully amended the High Speed Rail (Preparation) Act 2013 to enforce a much tougher scrutiny regime around the project’s budget. I will add that after the investment in High Speed 1, in Crossrail, in Thameslink and in Reading station, HS2 is a welcome commitment to building world-class infrastructure in the midlands and the north, and not just in London and the south-east.
I will not give way, because I have such limited time and I want the Minister to be able to respond to points.
We cannot and should not ignore environmental concerns, and I am grateful for the briefings and constructive dialogue that I have had with groups such as the Campaign to Protect Rural England and the Woodland Trust. Unlike the current Mayor of London, we do not dismiss legitimate environmental concerns raised by people who live along the proposed route of HS2, and we want the environmental benefits of HS2 to be enhanced through an early commitment to decarbonising the electricity market. We also want to ensure that the concerns of community groups are looked at, and that disruption is mitigated wherever possible.