Smart Meters Bill (Fourth sitting) Debate
Full Debate: Read Full DebateGrahame Morris
Main Page: Grahame Morris (Labour - Easington)Department Debates - View all Grahame Morris's debates with the Department for Business, Energy and Industrial Strategy
(6 years, 12 months ago)
Public Bill CommitteesWill the Minister clarify that point on the SMETS 2 meters for my benefit and that of the Committee? The key issue that was raised originally with the witnesses was interoperability. Obviously, that problem is being solved by the SMETS 2 meters, so theoretically it is possible to solve the problem of interoperability. Will the SMETS 1 generation of smart meters require a different methodology to solve that problem in order to recalibrate them to give them that interoperability functionality—if that makes sense?
The hon. Gentleman makes a lot of sense, but not in a technical way. I cannot answer him in a technical way, other than to say that my understanding is that the software is remotely operated—in our day we might have called it via the lines—through the air to the meter, so it is not a question of people coming out to revisit them to make them nearly as good as SMETS 2s. The SIM card on the dumb ones is reactivated remotely.
One of the good points about SMETS 2s is that they allow energy suppliers to roll out smart meters to premises that just have gas customers. They allow distribution network operators to view maximum electricity demand for a premises in order to plan their network investments. There are a number of specialist types of smart meters, for example, polyphase meters for large electricity users, and smart meters that can be used to replace traditional Economy 7 and 10 teleswitches, which we may have come across in our constituencies, and they can only be SMETS 2. But when upgraded—if I may call it that—with the DCC software, SMETS 1s do most of the smart things that SMETS 2s do. It is just how things move on. We must accept the fact that the foundation stage of the programme was based on SMETS 1, which was infinitely better than the previous option of different companies manufacturing different types of meters for their own customers, perfectly properly, with the technology that there was. This system has replaced that anarchy—although it was legal anarchy—in terms of national organisation.
I accept the point about timing, but the foundation stage was always intended to be different from the main installation phase. We have to see this transition from SMETS 1 to SMETS 2, because it is the latest technology and we want as many people as possible to have it. I feel it is fair to say that the foundation stage has provided real benefits. We are seeing savings. Mr Bullen, in particular, spoke about his 600,000 prepayment customers with the key system, which is very old fashioned and difficult for elderly people and vulnerable people. Anyone can recognise objectively that that has been a very good thing; had we waited for SMETS 2 to be developed, those people would not have had the benefit of smart meters. It is fair to say, like with any new technology, that we want to see the industry move from SMETS 1 to SMETS 2 as soon as possible, for the reasons I have explained.
The witness from the supplier company, Secure Meters Ltd, was basically arguing very much for SMETS 1, presumably because that company is a big supplier of SMETS 1 meters. I do not mean that in any sarcastic or improper way; that is what the company does. It was said very clearly that at the moment 250 SMETS 2 meters have been connected. I hope that in the two days since then, it is a lot more than that, but it is a small number. [Interruption.] Well, at least 251, if I may say so to the shadow Minister. Anyway, they are being installed.