Palace of Westminster: Restoration and Renewal Debate
Full Debate: Read Full DebateDavid Winnick
Main Page: David Winnick (Labour - Walsall North)Department Debates - View all David Winnick's debates with the HM Treasury
(7 years, 10 months ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
I am sure that the right hon. Member for Saffron Walden (Sir Alan Haselhurst) will not misunderstand when I say that neither he nor I will be likely to sit in the reconstructed Chamber. It can safely be said of both of us that we are not speaking out of personal self-interest.
In a debate in November 2012, I urged that work should be undertaken so that we can be prepared from 2020 onwards, so I have some form on this. I congratulate my hon. Friend the Member for Rhondda (Chris Bryant) on making a very good speech outlining, as did the right hon. Member for Saffron Walden, why the work is essential. I hope that whether we agree to option 1, 2 or 3—and there is bound to be division not only today but when the matter is debated in the Chamber—we will agree on one thing. I hope that even the hon. Member for North Dorset (Simon Hoare), who intervened earlier, will agree on this: the work is essential. I fear, as I said in the Chamber four years ago, that we will find ways and means of delaying the decision—because of finance, because there are other problems that the Government or Parliament must deal with, because it is not possible to reach a decision along the lines that so many of us want. The decision I want is simple: that from 2020 the work will begin, either through a total decant—I share the view of my hon. Friend the Member for Rhondda that that would be right—or otherwise. However, the Parliament elected in 2020, if that is when we have a general election, would sit in a different place.
May I just clarify something? No one doubts—I certainly do not—the scale of the work that needs to be done, the need for it, or the underlying urgency. We question the means of delivery of the works.
I do not disagree, obviously. The hon. Gentleman clearly accepts that the work needs to be done. One reason for today’s debate is to look at ways of delivery; but obviously there must be a major debate in the Chamber.
My hon. Friend the Member for Rhondda mentioned the possibility of a meltdown of mechanical and electrical services. It is all in the report, and I am sure we have all read it. In many instances the cables and pipes are surrounded by dangerous asbestos. The report says that much of the building is riddled with asbestos. As to water penetration, we know from experience that when there is heavy rain there is flooding in parts of the building. We have seen it with our own eyes, let alone what the report states about the situation.
The key issue about asbestos, with which my hon. Friend rightly says the building is riddled, is that we do not know where it is. When there is drilling, or when things are taken out, the starting presumption must be that there is asbestos there. That would add massively to the cost of working in a fully occupied building.
My hon. Friend certainly makes a powerful case for a full decant.
It should not be forgotten that, as has been mentioned, every year the cost of maintaining the building goes up. The figure given in the report for 2014-15—the latest figures, unless the Deputy Leader of the House has further information—is nearly £50 million. That is public money that is essential just so that the building can be in some kind of working condition. I agree that full decanting is essential. I understand why some feel that for historical and ceremonial reasons, and so that people can come to this building, there is a case for partial decanting, but in practice and when we consider the amount of work involved on what would be a huge building site, how on earth could we continue to debate in the present Commons or Lords Chambers, or the Robing Room? Imagine the constant pleas to the Speaker or Lord Speaker: “It is impossible to hear. Can the work stop for a while?” and the rest of it. It is not practical—and I do not understand how anyone could argue otherwise—to work with the constant noise and disruption and constant changes of location between the two Chambers. That is not the way to proceed, even if it was done after the 1834 fire. I think we have made some progress since then.
I am the chairman of the all-party group on the events industry; is the hon. Gentleman aware that the delay in making a decision is having an impact on event and conference bookings at the Queen Elizabeth II centre, and that, more generally, the cost of a decant in which the conference centre was used for the Lords would have an impact of hundreds of millions of pounds on the wider Westminster economy that comes with all those conferences and events?
The hon. Gentleman makes a valid point.
I am speaking in the debate because I want to urge that a decision be reached as quickly as possible. It has been said in some parts of the media that the work is for ourselves. It is not: we come and go; we are tenants. Neither is it for our staff, the officers or anyone else working in the building. That is not why the work should be undertaken, despite the cost. It is for the democratic process. It is for British democracy to have its traditional home, which is recognised throughout the world. We should take pride in the building, and we should take pride in the fact that British democracy is recognised in the way it is, especially in countries in which, unfortunately, the rule of law and civil liberties are totally absent. That is why it is so essential that a decision is taken in the very near future. I want to see a building fit for purpose, a place that ensures the continuation of the democratic process and the rule of law.
Of course, we could go elsewhere. Parliamentary democracy in the United Kingdom certainly does not depend on one particular building—it would be farcical if it did—but this is our traditional home, and hopefully will be for future generations. That is why it is so important that what the report outlines should be seriously considered and a decision should be reached in the near future.
When the Deputy Leader of the House of Commons responds, I hope he has the authority to say that a major debate will take place on the subject this year—in the first part of 2017. The House itself can then reach a decision on option 1, 2 or 3. Whatever it may be, at least the decision will be reached that work should commence following the 2020 general election.
What we decide to do is a matter for the House. I reiterate that we aim to bring the matter to a vote as soon as possible. We have to take the time—and have taken the time—to consider very carefully the details of the proposed recommendations and their implications. It is not simply a question of reading a report that has taken a year to prepare. We want to consider those recommendations and their implications carefully. We have taken advice on a range of technical and governance issues made by the Joint Committee report by, for example, consulting with the Infrastructure and Projects Authority. It is only right, too, that Members consider the report of the Joint Committee carefully. I urge all of them to read it in full if they have not done so already.
The House rises for the Easter recess on 30 March. Is there a reasonable chance that we will have the debate before then?
We aim to bring the matter to a vote as soon as is reasonably practicable. As has been made clear this morning, in recent weeks colleagues have suggested a number of alternative proposals, some of which the House authorities have commissioned additional research on. Those also need to be considered, and that includes the proposals made by my hon. Friend the Member for Gainsborough, which have been analysed in detail. A copy of the House’s report will be placed in the Library later today and is available electronically now.
The House authorities have been keen to engage with Members, most recently through two well-attended drop-in sessions—we organised those—with the programme team. Members are also encouraged to arrange to be taken on a tour of the basement areas. It is not compulsory to go with the hon. Member for Rhondda—