Commons ChamberThe fundamental difference between an air accident investigation and a public inquiry is that as culpability is identified it is then passed on for action. This lies at the heart of the problem, which is the slow pace of bringing about justice. An extended period for a public inquiry has prevented and inhibited the delivery of justice for the people of Grenfell. Does the hon. Gentleman—
Order. I remind Members that interventions need to be pithy and short.
I have got the point. The problem with a public inquiry is that it starts from ground zero. It assembles a group of people who may be expert, but most of the lawyers will not be expert and will have to learn everything from scratch. The advantage of a standing capability is that there are experts who are permanently employed and who really understand everything about building safety, as it would be in this case. There would be human factors analysts, structural engineers, architects—key people with key skills, fully knowledgeable about the safety system that exists. They would start immediately after a tragedy, and they would conclude much more quickly on the basis of much better expertise.
I had hoped that the inquiry would adopt this recommendation, as did the Cullen inquiry into Ladbroke Grove, and also the inquiry into offshore safety following the Piper Alpha disaster. It now falls to the Government and Parliament to get this right.
The second recommendation in our submission is for a comprehensive reform of building control. Building control is the inspection system which should ensure that building regulations are followed, but Grenfell demonstrated its failure. I accept that there has already been some reform here since we wrote our submission. Much has been said, as we heard earlier, about how private sector building inspectors are endemically conflicted because they are appointed and paid by constructors and others, but that misses a horrible truth about the Grenfell case. Ironically, it was the building control function of a local authority, the Royal Borough of Kensington and Chelsea, that failed so disastrously in Grenfell’s case. Despite that, everyone’s emphasis still seems to be more focused on restricting private sector involvement than on reform of the whole building control sector.
I simply wanted to ask for a clarification. Surely the issue, which was raised earlier, is that there is a conflict of interests when you are paying to have your product assessed. As we know from Sir Martin’s report, there was a cover-up of testing results. If you accept that, how do you get around the “conflict of interests” issue?
Order. I am not going to admonish the hon. Member for using the word “you”, but, Sir Bernard, you have now spoken for longer than both Front Benchers put together, and many other Members wish to get in.
I will be as quick as I can, Madam Deputy Speaker, but I am extremely grateful for the hon. Gentleman’s question, because that was a failure of regulation. The crucial point is this. In other safety-critical industries, such as the civil aviation, rail and marine sectors, there is no ban on the private sector being selected to perform inspections. Employees of airlines, of aircraft manufacturers and of aircraft engine manufacturers perform the inspections, but they are independently regulated, overseen and certified by the Civil Aviation Authority. The fact that they are employed by the airlines or by commercial interests does not make them incapable of objective judgment. The whole aviation sector flies incredibly safely on the basis of aircraft being inspected not by Government inspectors or public employees, but by the private sector.