Duke of Montrose Portrait The Duke of Montrose (Con)
- Hansard - - - Excerpts

My Lords, my experience of water retention on this scale is that I was involved in the transformation of Loch Lomond into a reservoir capable of supplying 450 million litres of water a day.

On the volume of water held back by a dam being increased from 10 million to 30 million cubic litres, perhaps the Minister can say whether the noble Lord, Lord Campbell-Savours, can take some comfort from the fact that the smaller reservoirs would still be subject to all the regulations in the 1975 Act. I have just come from a meeting where we were addressed by an executive from Anglian Water. He said that it was under severe pressure this summer and that, if it has to extract any more water from ground sources, it feels that it will be moving into an area where damage might be caused. This must be quite a worry.

Baroness Redfern Portrait Baroness Redfern (Con)
- Hansard - -

My Lords, I too welcome the SI and agree with many of the comments of my noble friend Lady Byford. We have droughts in the eastern part of the UK, so I welcome looking at our reservoirs and desalination plants.

I have a query about the impact on costs to local authorities. In paragraph 12.3 of the Explanatory Memorandum, it says that,

“there will be a slight increase in costs to Local Authorities … as more resource will be required in order to advise on applications”.

Is that for central government or for local authorities? Budgets are tight and I should like some clarification, particularly on that explanatory note.

Baroness Bakewell of Hardington Mandeville Portrait Baroness Bakewell of Hardington Mandeville (LD)
- Hansard - - - Excerpts

My Lords, I declare my interest as a district councillor. I thank the Minister for his opening remarks and for setting the scene so clearly.

Water is a natural resource which is not finite. Our lives and livelihoods depend on it, and the well-being of all living creatures, trees and plants relies on there being a ready and plentiful supply of fresh water.

As the Minister has said, the change to the Planning Act 2008 for nationally significant infrastructure projects was out to consultation for six weeks during November 2017 and then for a shorter, three-week period in April this year. The first consultation resulted in a significant number of responses but no definitive consensus. The second consultation received 20 responses from those bodies directly affected by the change to the law. There was broad agreement with the proposed amendments. I find this encouraging, as it is quite a significant alteration to the capacity currently covered by the 2008 Act.

The change from 10 million to 30 million cubic metres represents a trebling of dam or reservoir capacity. This is likely to have some impact on the surrounding area and, no doubt, the people affected will have views that they wish to express.

To avoid drought conditions in parts of the country—such as we have heard about—it is imperative for major projects which both conserve and move water to be streamlined to ensure they proceed on time.