(8 months ago)
Lords ChamberI have numerous statistics in terms of the number of buildings that are involved in this programme. Of course, what we know is how many of those buildings over 18 metres are left without a programme or have completed their programme. Some 10 are left, and they all have programmes in place, so they will be completed as soon as possible. The highest-risk ACM cladding buildings are being dealt with, so we will get very close, in that 98% of them have now started or completed their works.
On buildings of lesser height, of 11 to 18 metres, because the fund was established only last July some of those buildings will not be known to us. We are still working on an estimated number for those requiring remediation. In England, that number is somewhere between 6,220 and 8,890. That figure is based on an estimation and, therefore, a methodology behind it. We expect those numbers to come forward as that fund is called on; as people utilise it to put pressure on the owners of those buildings to deal with this, we expect that number to rise.
I shall come back to the House regularly to update it on progress. We believe that pressure is the right way here, and pressure across the House is definitely the right way to keep up the work and get this done at pace.
My Lords, the Minister has indicated a number of times that the Government are focused on buildings over 11 metres in height and suggested that other buildings are not really a priority. Is she aware of the Moss Hall Grove fire in Finchley, north London, a few weeks ago, where four terraced houses went up in flames astonishingly quickly? There were 70 firefighters there and a significant number of engines had to be called to this blaze. Luckily, it happened at 10.30 am, so eight people were able easily to flee the circumstances, but this has led Barnet Council to recognise that there are significant problems particularly with timber-framed homes with plastic cladding on the outside. This one council in north London has identified 580 low-rise homes in need of urgent remediation. These are mostly 1930s to 1960s-built timber-framed homes with uPVC panels fitted in the 1980s. Are the Government looking into this issue? The identification of 580 homes in one London borough suggests a very large problem across the country.
I thank the noble Baroness for her question; however, I do not have any data with me on that. I will make sure that the department looks into it and I will write to her with an answer.
Of the funds that have been made available, there are a number for different sizes of buildings; the fund for buildings between 11 and 18 metres was available from July last year. Therefore, from that perspective, everyone is open to being able to use them. Regarding how the issue sits as a priority, it certainly sits with me as a priority and, as a new Minister in the department, I will ensure that I do everything I can to monitor progress. The monthly data will be checked and we will put pressure not only on developers but on the enforcement side, with regards to the regulators and the local authorities working hand in hand.
My Lords, I raise an issue relating to what has happened with high-rise buildings since the Grenfell tragedy. This week, the Independent reported that, in high-rise buildings that have been declared safe, substantial numbers of leaseholders and residents are seeing massive increases of up 1,000% in insurance premiums. To give an example, there is a one-bedroom flat occupied by a single parent and a baby where the insurance has gone up over two years from £274 a year to more than £2,600, making it essentially unaffordable. Will the Government look into why, if buildings have been declared safe, the insurance premiums are going through the roof? Surely risk to life and risk to the fabric of the building, which the insurance primarily relates to, have to be interrelated?
If there are instances where that is the case, then you can either work with our department, or directly through the Association of British Insurers to alert them to the fact that it is happening. There is an agreement with insurance companies that, if remediation work has been done, the insurance premiums should not be excessive.
With regards to other parts of the insurance market and those buildings which have not yet had full remediation work done, they are also expected to be working with residents to ensure that insurance is affordable. There is a fire-safety reinsurance facility led by the Association of British Insurers, which reinsurance brokers can utilise. There are a number of insurance-led schemes which are supposed to be helping. If noble Lords know of any instances where they are not, please let us know.
Sorry, bear with me for a second. I need to go back to an earlier section—I have ripped all my papers out and therefore they are in the wrong place—to allow me to help the noble Lord.
The commitment made by the ABI and its members is that the premiums should reduce where buildings have completed remediation, or have achieved the PAS 9980-compliant external wall assessment, and have therefore shown a reduction in risk. We are working with the insurers to build a better understanding of these building standards, and we expect insurers to honour their commitments and ensure that premiums are fairly priced and appropriate to the level of risk after remediation.
Since there is time, I will follow through on that—for public information, really. If it is not happening, and if we have a case such as the one I cited, from £270 to £2,600, who does an individual or a campaigning organisation go to in the Government? What are the actual steps to say that this is not happening and the ABI is not delivering? What is the mechanism that can be implemented?
In the first instance, I suggest that they go to their insurance company directly and notify it of the requirement that this should be fair and assessed based upon the existing current risk rather than prior risk. If that does not yield results and the ABI is unable to help, I am more than happy, as the Minister here, to have those sent to me.
(8 months, 1 week ago)
Lords ChamberI thank the noble Lord for his question. I already have an outstanding question from one of his colleagues on his Benches from the debate last week. I am trying to find the exact numbers for how much is in progress, given that there is lag between the money being allocated and being spent. I am chasing that and will come back to the House as soon as I have the number.
My Lords, returning to the Teesworks project, in writing to the mayor—the noble Lord, Lord Houchen—the Secretary of State said:
“Improvement takes time, and where the recommendations related to cultural change especially it is important that sufficient time is given”.
But is it really right to leave a six-month hiatus? Should the Government not monitor what is happening much more regularly than that, given the level of concern expressed by the independent inquiry into what is happening at Teesworks?
Again, I can only give an assurance that this will not be waiting for six months. A number of these actions are required immediately and are therefore ongoing. We will be monitoring it both centrally and locally.