(2 years, 10 months ago)
Commons ChamberSorry, no—I have a general habit of wearing a mask whenever possible.
The Bill essentially falls into three parts. Part 1 concerns the designation of a company for the receipt of regulated asset base payments. Part 2 concerns the collection and disbursement of funds through the regulated asset base arrangements. Part 3 sets out a special administration regime, should a nuclear power plant be unable to carry out its obligations arising from the institution of the regulated asset base arrangement.
The Bill, essentially, is trying to produce a method for funding and getting over the line one particular nuclear power plant: Sizewell C. That is the only plant that is developed enough to be able to generate by 2030. A substantial part of the Bill is not about the general future of nuclear, or the relationship with nuclear renewables; it is about how one plant is to be financed over the next period so that it can actually start producing energy, hopefully by the end of this decade or shortly thereafter.
The Labour party supports nuclear power for the future and is particularly concerned that, for example, the Climate Change Committee has indicated that some 8 GW of nuclear power might be put in the mix for low-carbon renewable power for the future. Sizewell C is an important part of that process—indeed, getting it going is long overdue. Perhaps I can put the record straight, because the previous Labour Government, as the 2007 nuclear White Paper and the strategic planning documents of 2009-10 show, laid the basis for the present number of sites to be considered and, therefore, for nuclear power going forward.
The hon. Gentleman is absolutely right, but unfortunately we lost a decade, from 1997 to 2007, when nuclear was taken off the table. Because of the timescales, which he is well aware of, will he just accept—this is not necessarily party political—that losing that decade put us back and is costing us now?
The hon. Member is quite right that prior to 2007 the Labour Government did not consider the development of nuclear power by state means to be an appropriate way forward, although they never suggested that the development of nuclear power by private means could not be countenanced. However, we have since had more than 10 years of Conservative-led Government, which has produced precisely no nuclear power plants. Indeed, there is one nuclear power plant in the pipeline, and we hope a nuclear power plant that can be financed by reasonable means. One of the problems with the previous plant, Hinkley Point C, which the present Government got off the ground, was the funding arrangements, with EDF supplying most of the capital for the plant and then a CfD for the plant at the end, which looks like it will be quite disastrous, with future electricity prices being completely uneconomic.
It is therefore important that we get a method for funding those nuclear plants, and particularly Sizewell C, that does not fall into those traps and is also secure for the future. That is the concern of our amendments 1 and 2. To put the record straight, anyone who looks at those amendments reasonably closely will see that amendment 1 defines what is stated in amendment 2, and that it is defined as
“means owned by a company controlled by a foreign state and operating for investment purposes.”
That does not include EDF. Let us be clear from the outset that EDF is not
“a company controlled by a foreign state.”
Although it is substantially owned by a foreign state, it is not operating for investment purposes, but for production purposes. Let us be clear about what the particular concern is for the future.