Roads: East of England

(asked on 7th December 2023) - View Source

Question to the Department for Transport:

To ask His Majesty's Government what major roadworks are in progress on (1) the A12 Trunk Road between the M25 and Ipswich, and (2) the A14 between Cambridge and Ipswich; when each such undertaking is expected to be completed; and what further major roadworks are expected to start within the next 12 months.


Answered by
Lord Davies of Gower Portrait
Lord Davies of Gower
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 19th December 2023
  1. The following major roadworks are in progress on:

The A12 Trunk Road between the M25 and Ipswich

National Highways is currently working through an extensive programme to rebuild concrete roads which have come to the end of their serviceable life, and which require high levels of intervention to maintain them. National Highways will be reconstructing the carriageway and replacing it with a modern asphalt surface. This will improve safety, create smoother quieter journeys and extend the life of the A12 to make it fit for the future. There are two such schemes currently underway on the A12:

A12 Margaretting Bypass (junctions 13 to 15) a £65million concrete road reconstruction scheme – expected completion by summer 2024.

A12 Marks Tey (junction 25) to Stanway (junction 26) a £37milllion concrete road reconstruction scheme – expected completion by summer 2024.

National Highways is also delivering major improvements to increase capacity, reduce congestion and improve safety at M25 junction 28. This circa £160million junctions enhancement scheme is expected to complete by summer 2025.

The A14 between Cambridge and Ipswich

There are ongoing road works on the A14 Haughley (junction 47a) to Tothill (junction 49) as part of a £37 million concrete road reconstruction scheme expected to be completed by summer 2024. National Highways is currently reconstructing the carriageway and replacing it with a modern asphalt surface.

  1. In July 2023, National Highways published its Delivery Plan which sets out its plan to start works on the A12 Chelmsford to A120 improvement scheme by the end of March 2024. A decision on the Development Consent Order for this scheme is to be made by 12 January 2024.