Hinkley Point C Power Station

(asked on 12th March 2018) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask Her Majesty's Government what is the expected total number of tons of waste material arising from the construction of the new Hinkley Point power station to be deposited in the Cardiff Grounds.


Answered by
Lord Henley Portrait
Lord Henley
This question was answered on 26th March 2018

The amount of dredge material requested by the applicant in the marine licence application is for a maximum of 280,000 tonnes. The original figure was higher than this, however the licence holder now requires dredging from a smaller area.