Type 45 Destroyers: Repairs and Maintenance

(asked on 4th February 2022) - View Source

Question to the Ministry of Defence:

To ask Her Majesty's Government why the Power Improvement Project for HMS Dauntless has taken 21 months so far, instead of the planned six to eight months.


Answered by
Baroness Goldie Portrait
Baroness Goldie
This question was answered on 18th February 2022

HMS DAUNTLESS is the first of class to undergo Power Improvement Project (PIP) conversion. The next phase of the programme will see HMS DAUNTLESS undertake a rigorous harbour trials programme, before returning to sea later this year for sea trials.

The PIP conversion is a complex engineering project and delivering it against the backdrop of the Covid-19 pandemic has been a significant challenge which has impacted the schedule.

The lessons learned from the first of class PIP conversion will be applied to subsequent ships, whilst taking into account that the programme is balanced against the Royal Navy's standing and future operational commitments. It is planned that all six Type 45 ships will have received the PIP conversion by 2028.

Reticulating Splines