Type 45 Destroyers

(asked on 22nd February 2018) - View Source

Question to the Ministry of Defence:

To ask Her Majesty's Government what is the programme for returning the UK's Type 45 destroyers to full capability; and when they anticipate this will be achieved.


Answered by
Earl Howe Portrait
Earl Howe
Deputy Leader of the House of Lords
This question was answered on 5th March 2018

Improvements to the resilience of the Type 45 Destroyers' power and propulsion system will be delivered through the Power Improvement Project, which involves fitting additional diesel generators to provide the ships with increased electrical generation capacity. The programme is the subject of an ongoing competitive procurement and it would not be appropriate to release details of the programme schedule until the competitive process has completed and the contract has been agreed. The Type 45 Destroyers continue to be deployed on operations and contribute to the defence of the UK and our international partners.