Question to the Department for Transport:
To ask His Majesty's Government what assessment they have made of the performance of South Western Railways since it entered public ownership on 25 May 2025.
The Department is closely monitoring South Western Railway’s (SWR’s) performance following its transfer into public ownership on 25 May 2025 through a range of measures, including punctuality, cancellations, and passenger experience.
When SWR entered public ownership, eighty-four out of ninety of the new Arterio trains had not entered service. The new Arterio fleet is being rolled out and will support more reliable services over time, providing modern, higher capacity trains with improved performance and reduced maintenance requirements.
SWR also inherited a shortage of train drivers when it moved into public ownership, which contributed to high levels of driver-related cancellations.
South Western Railway is subject to bespoke and rigorous performance standards, and the Department continues to work with the operator to improve reliability, capacity, and service quality for passengers.