High Speed 2 Line: Iron and Steel

(asked on 23rd June 2026) - View Source

Question to the Department for Transport:

To ask His Majesty's Government what percentage of the total steel requirement for HS2 has been procured.


Answered by
Lord Hendy of Richmond Hill Portrait
Lord Hendy of Richmond Hill
Minister of State (Department for Transport)
This question was answered on 7th July 2026

94% of structural steel and 90% of the steel rebar required for the HS2’s Main Works Civils has been procured. Assessments from the Main Works Contractors working on the Civils structures indicate that around 70% of Rebar and over 80% of Structural Steel required across the programme has been delivered.

Steel procurement has also progressed for other aspects of the programme; however, exact percentages are not available at this time for the Stations or Systems contracts as the designs are under development alongside ongoing HS2 reset activities.