Level Crossings: Tilbury

(asked on 1st December 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, whether Network Rail has provided her with data on (a) barrier-down times, (b) duration of delays or (c) frequency of freight movements at the East Tilbury Level Crossing.


Answered by
Keir Mather Portrait
Keir Mather
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 9th December 2025

At this level crossing, there are around 150 scheduled passenger trains passing through each day and up to 45 freight services in both directions per day. During the last risk assessment, Network Rail identified that there were 102 level crossing activations, with an average barrier down time of four minutes and seven seconds, over a 24-hour period.