Question to the Department for Transport:
To ask the Secretary of State for Transport, what recent assessment her Department has made of a) the structural condition of the A180 between the M180 and Immingham Port, b) the adequacy of current life-extending works to support projected increases in HGV traffic, c) the number of delays to freight movements arising from ongoing National Highways works on the A180 and adjacent links, and d) the expected timetable for completing those works.
There are no current Life Extension Works (LEW) underway on the A180. A LEW scheme was completed in 2024/25 on this section to provide an operational life extension of 5+ years and intended to ensure the section remained safe and operational, until a planned reconstruction scheme in Road Investment Strategy 3 (RIS3), planned to be undertaken in 2030/31. As part of the design activity related to the planned RIS3 reconstruction scheme, traffic management options and journey time impact studies will be undertaken to ensure impacts to road users are minimised.