Broadband: North Herefordshire

(asked on 13th November 2025) - View Source

Question to the Department for Science, Innovation & Technology:

To ask the Secretary of State for Science, Innovation and Technology, what steps she is taking to provide timelines to North Herefordshire constituents on when they will be able to access a gigabit-capable broadband connection, in the context of the delay to Project Gigabit's completion date until 2032.


Answered by
Kanishka Narayan Portrait
Kanishka Narayan
Parliamentary Under Secretary of State (Department for Science, Innovation and Technology)
This question was answered on 21st November 2025

As part of Project Gigabit, Openreach is contracted to provide gigabit-capable broadband to approximately 3,050 premises in the North Herefordshire constituency that are not included in suppliers’ commercial plans. This coverage is contracted to be completed by 2030 and the first connections are expected to be ready for service by March 2026.